AL
Alabama DOT · Bid Tabulation
Contract 20260327010
PLANING, RESURFACING, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-59 FROM THE JUNCTION OF SR-16 (US-90) IN LOXLEY TO THE JUNCTION OF CHURCH STREET IN STAPLETON
- County
- BALDWIN
- District
- 0902
- Letting
- March 27, 2026
- Bidders
- 2
Apparent low bid
WIREGRASS CONSTRUCTION COMPANY, INC.
$6,109,700.00
Other bidders
APAC-ALABAMA, INC.
$6,224,112.30
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | WIREGRASS CONSTRUCTION COMPANY, INC. $6,109,700.00 | APAC-ALABAMA, INC. $6,224,112.30 | ||
|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | ||||
| 206D001 | Removing Guardrail | 525 | LF | $3.5300 | $1,853.25 | $3.3800 | $1,774.50 |
| 206E008 | Removing Guardrail End Anchor (All Type) | 1 | EACH | $411.2500 | $411.25 | $394.0300 | $394.03 |
| 212A000 | Machine Grading Shoulders | 6 | STA | $553.3200 | $3,319.92 | $381.6200 | $2,289.72 |
| 405A000 | Tack Coat | 37,727 | GAL | $3.8400 | $144,871.68 | $4.2900 | $161,848.83 |
| 408A052 | Planing Existing Pavement (Approximately 1.10" Thru 2.0" Thick) | 377,267 | SQYD | $1.0100 | $381,039.67 | $1.7300 | $652,671.91 |
| 410H000 | Material Remixing Device | 1 | EACH | $1.2900 | $1.29 | $83,753.7700 | $83,753.77 |
| 424A361 | Superpave Bituminous Concrete Wearing Surface Layer, 3/4" Maximum Aggregate Size Mix, ESAL Range C/D | 35,968 | TON | $119.9000 | $4,312,563.20 | $114.8000 | $4,129,126.40 |
| 424A370 | Superpave Bituminous Concrete Wearing Surface Layer, Widening, 3/4" Maximum Aggregate Size Mix, ESAL Range C/D | 1,119 | TON | $169.6800 | $189,871.92 | $166.4600 | $186,268.74 |
| 424B654 | Superpave Bituminous Concrete Upper Binder Layer, Patching, 3/4" Maximum Aggregate Size Mix, ESAL Range C/D | 560 | TON | $171.9100 | $96,269.60 | $174.5800 | $97,764.80 |
| 424B658 | Superpave Bituminous Concrete Upper Binder Layer, Leveling, 3/4" Maximum Aggregate Size Mix, ESAL Range C/D | 150 | TON | $184.3800 | $27,657.00 | $164.9200 | $24,738.00 |
| 428A001 | Scoring Bituminous Pavement Surface | 23 | MILE | $718.8200 | $16,532.86 | $661.1000 | $15,205.30 |
| 600A000 | Mobilization | 1 | LS | $151,913.6600 | $151,913.66 | $93,150.3600 | $93,150.36 |
| 630A001 | Steel Beam Guardrail, Class A, Type | 525 | LF | $28.2000 | $14,805.00 | $27.0200 | $14,185.50 |
| 630C077 | Guardrail End Anchor, Type 8 (MASH) | 1 | EACH | $1,703.7500 | $1,703.75 | $1,632.4100 | $1,632.41 |
| 650A000 | Topsoil | 1,500 | CUYD | $47.9300 | $71,895.00 | $61.2300 | $91,845.00 |
| 652A100 | Seeding | 4 | ACRE | $1,410.0000 | $5,640.00 | $1,350.9700 | $5,403.88 |
| 652C000 | Mowing | 162 | ACRE | $111.6300 | $18,084.06 | $106.9500 | $17,325.90 |
| 654A001 | Solid Sodding (Bermuda) | 319 | SQYD | $5.8800 | $1,875.72 | $5.6300 | $1,795.97 |
| 656A010 | Mulching | 4 | ACRE | $822.5000 | $3,290.00 | $788.0600 | $3,152.24 |
| 665J002 | Silt Fence | 750 | LF | $5.5800 | $4,185.00 | $5.3500 | $4,012.50 |
| 665O001 | Silt Fence Removal | 750 | LF | $1.4700 | $1,102.50 | $1.4100 | $1,057.50 |
| 665Q002 | Wattle | 150 | LF | $14.1000 | $2,115.00 | $13.5100 | $2,026.50 |
| 666A001 | Pest Control Treatment | 1 | ACRE | $587.5000 | $587.50 | $562.9000 | $562.90 |
| 698A000 | Construction Fuel (Maximum Bid Limited to $ 311,000.00) | 1 | LS | $0.0000 | $0.00 | $0.0000 | $0.00 |
| 701A227 | Solid White, Class 2, Type A Traffic Stripe (5" Wide) | 23 | MILE | $4,230.0000 | $97,290.00 | $4,109.1800 | $94,511.14 |
| 701A230 | Solid Yellow, Class 2, Type A Traffic Stripe (5" Wide) | 17 | MILE | $4,230.0000 | $71,910.00 | $4,109.1800 | $69,856.06 |
| 701A239 | Broken White, Class 2, Type A Traffic Stripe (5" Wide) | 16 | MILE | $2,173.7500 | $34,780.00 | $2,026.4500 | $32,423.20 |
| 701A244 | Broken Yellow, Class 2, Type A Traffic Stripe (5" Wide) | 6 | MILE | $2,173.7500 | $13,042.50 | $2,026.4500 | $12,158.70 |
| 701B207 | Dotted, Class 2, Type A Traffic Stripe (5" Wide) | 15,825 | LF | $1.0000 | $15,825.00 | $3.1000 | $49,057.50 |
| 701C000 | Broken Temporary Traffic Stripe | 63 | MILE | $470.0000 | $29,610.00 | $394.0300 | $24,823.89 |
| 701C001 | Solid Temporary Traffic Stripe | 116 | MILE | $822.5000 | $95,410.00 | $844.3500 | $97,944.60 |
| 703A002 | Traffic Control Markings, Class 2, Type A | 18,942 | SQFT | $4.7000 | $89,027.40 | $3.3800 | $64,023.96 |
| 703B002 | Traffic Control Legends, Class 2, Type A | 2,636 | SQFT | $4.7000 | $12,389.20 | $3.3800 | $8,909.68 |
| 703D001 | Temporary Traffic Control Markings | 7,042 | SQFT | $1.7600 | $12,393.92 | $1.1300 | $7,957.46 |
| 703E001 | Temporary Traffic Control Legends | 2,636 | SQFT | $1.7600 | $4,639.36 | $1.1300 | $2,978.68 |
| 705A030 | Pavement Markers, Class A-H, Type 2-C | 4,910 | EACH | $5.2900 | $25,973.90 | $4.5000 | $22,095.00 |
| 705A031 | Pavement Markers, Class A-H, Type 1-A | 250 | EACH | $5.2900 | $1,322.50 | $4.5000 | $1,125.00 |
| 705A032 | Pavement Markers, Class A-H, Type 1-B | 600 | EACH | $5.2900 | $3,174.00 | $4.5000 | $2,700.00 |
| 705A037 | Pavement Markers, Class A-H, Type 2-D | 650 | EACH | $5.2900 | $3,438.50 | $4.5000 | $2,925.00 |
| 705A038 | Pavement Markers, Class A-H, Type 2-E | 300 | EACH | $5.2900 | $1,587.00 | $4.5000 | $1,350.00 |
| 730H001 | Loop Wire | 5,250 | LF | $5.5100 | $28,927.50 | $5.2800 | $27,720.00 |
| 730I001 | Loop Detector Lead-In-Cable | 4,075 | LF | $3.2100 | $13,080.75 | $3.0700 | $12,510.25 |
| 730J010 | Vehicle Loop Detector | 5 | EACH | $1,337.8200 | $6,689.10 | $1,281.8100 | $6,409.05 |
| 730K001 | Traffic Signal Junction Box Type S1 | 8 | EACH | $1,286.6600 | $10,293.28 | $1,232.7900 | $9,862.32 |
| 730L005 | 2", Non-Metallic, Conduit | 1,625 | LF | $13.8200 | $22,457.50 | $13.2400 | $21,515.00 |
| 730Q020 | Miscellaneous Equipment, Backplate for Existing Vehicular Signal Head, 3 Section | 35 | EACH | $466.9900 | $16,344.65 | $447.4400 | $15,660.40 |
| 730Q021 | Miscellaneous Equipment, Backplate for Existing Vehicular Signal Head, 4 Section | 3 | EACH | $600.1700 | $1,800.51 | $575.0400 | $1,725.12 |
| 730Q022 | Miscellaneous Equipment, Backplate for Existing Vehicular Signal Head, 5 Section | 2 | EACH | $676.8500 | $1,353.70 | $648.5100 | $1,297.02 |
| 740B000 | Construction Signs | 2,430 | SQFT | $6.1700 | $14,993.10 | $6.7500 | $16,402.50 |
| 740D000 | Channelizing Drums | 300 | EACH | $21.1500 | $6,345.00 | $29.2700 | $8,781.00 |
| 740E000 | Cones (36 Inches High) | 250 | EACH | $42.3000 | $10,575.00 | $0.0100 | $2.50 |
| 741C010 | Portable Sequential Arrow And Chevron Sign Unit | 2 | EACH | $1,138.9900 | $2,277.98 | $1,857.5800 | $3,715.16 |
| 742A001 | Portable Changeable Message Sign, Type 2 | 1 | EACH | $2,982.2200 | $2,982.22 | $3,850.2500 | $3,850.25 |
| 756A028 | 6" Electrical Conduit, 1 Line, Type 5 Installation | 160 | LF | $51.1100 | $8,177.60 | $48.9700 | $7,835.20 |
Source: public Alabama DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →