AL
Alabama DOT · Bid Tabulation
Contract 20260327038
SAFETY WIDENING, MICRO-MILLING, RESURFACING, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-123 FROM A POINT NORTH OF THE CHOCTAWHATCHEE RIVER BRIDGE (MP 21.030) TO THE JUNCTION OF SR-53 (US-231)
- County
- DALE
- District
- 0704
- Letting
- March 27, 2026
- Bidders
- 3
Apparent low bid
WIREGRASS CONSTRUCTION COMPANY, INC.
$2,196,115.17
Other bidders
SOUTHEAST CONSTRUCTION COMPANY, LLC
$2,555,563.05
APAC-ALABAMA, INC.
$2,740,675.73
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | WIREGRASS CONSTRUCTION COMPANY, INC. $2,196,115.17 | SOUTHEAST CONSTRUCTION COMPANY, LLC $2,555,563.05 | APAC-ALABAMA, INC. $2,740,675.73 | |||
|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 206D001 | Removing Guardrail | 2,363 | LF | $2.9900 | $7,065.37 | $3.5000 | $8,270.50 | $3.0500 | $7,207.15 |
| 206E008 | Removing Guardrail End Anchor (All Type) | 16 | EACH | $249.5200 | $3,992.32 | $274.9400 | $4,399.04 | $255.0000 | $4,080.00 |
| 209A000 | Mailbox Reset, Single | 20 | EACH | $390.7700 | $7,815.40 | $300.0000 | $6,000.00 | $300.0000 | $6,000.00 |
| 209A001 | Mailbox Reset, Double | 1 | EACH | $508.0900 | $508.09 | $400.0000 | $400.00 | $395.0000 | $395.00 |
| 209A002 | Mailbox Reset, Multiple | 1 | EACH | $625.4100 | $625.41 | $450.0000 | $450.00 | $512.0000 | $512.00 |
| 210D021 | Borrow Excavation (Loose Truckbed Measurement)(A4 or Better) | 100 | CUYD | $67.4800 | $6,748.00 | $30.0000 | $3,000.00 | $80.0000 | $8,000.00 |
| 212A000 | Machine Grading Shoulders | 659 | STA | $62.9600 | $41,490.64 | $60.0000 | $39,540.00 | $56.0000 | $36,904.00 |
| 405A000 | Tack Coat | 11,934 | GAL | $4.3700 | $52,151.58 | $5.0000 | $59,670.00 | $4.1000 | $48,929.40 |
| 408B001 | Micro-Milling Existing Pavement (Approximately 1.10" Thru 2.00" Thick) | 105,389 | SQYD | $0.8300 | $87,472.87 | $2.0000 | $210,778.00 | $1.8500 | $194,969.65 |
| 410H000 | Material Remixing Device | 1 | EACH | $18,000.0000 | $18,000.00 | $36,500.0000 | $36,500.00 | $19,200.0000 | $19,200.00 |
| 424A340 | Superpave Bituminous Concrete Wearing Surface Layer, 1/2" Maximum Aggregate Size Mix, ESAL Range A/B | 9,053 | TON | $102.4000 | $927,027.20 | $115.0000 | $1,041,095.00 | $131.4400 | $1,189,926.32 |
| 424A349 | Superpave Bituminous Concrete Wearing Surface Layer, Widening, 1/2" Maximum Aggregate Size Mix, ESAL Range A/B | 854 | TON | $202.7000 | $173,105.80 | $165.0000 | $140,910.00 | $252.3500 | $215,506.90 |
| 424B640 | Superpave Bituminous Concrete Upper Binder Layer, Patching, 1" Maximum Aggregate Size Mix, ESAL Range A/B | 100 | TON | $164.7000 | $16,470.00 | $200.0000 | $20,000.00 | $249.8000 | $24,980.00 |
| 424B648 | Superpave Bituminous Concrete Upper Binder Layer, Widening, 1 1/2" Maximum Aggregate Size Mix, ESAL Range A/B | 2,691 | TON | $84.0000 | $226,044.00 | $115.0000 | $309,465.00 | $111.4500 | $299,911.95 |
| 424B700 | Superpave Bituminous Concrete Upper Binder Layer, Leveling, 3/8" Maximum Aggregate Size mix, ESAL Range A/B | 100 | TON | $164.9200 | $16,492.00 | $130.0000 | $13,000.00 | $172.2500 | $17,225.00 |
| 428A001 | Scoring Bituminous Pavement Surface | 13 | MILE | $307.9200 | $4,002.96 | $350.0000 | $4,550.00 | $532.0000 | $6,916.00 |
| 430B043 | Aggregate Surfacing (1" Down, Crusher Run) | 183 | TON | $146.2000 | $26,754.60 | $110.0000 | $20,130.00 | $240.0000 | $43,920.00 |
| 600A000 | Mobilization | 1 | LS | $100,490.1500 | $100,490.15 | $191,040.0000 | $191,040.00 | $160,183.0000 | $160,183.00 |
| 630A001 | Steel Beam Guardrail, Class A, Type | 2,263 | LF | $19.4600 | $44,037.98 | $21.4500 | $48,541.35 | $19.5000 | $44,128.50 |
| 630C079 | Guardrail End Anchor, Type 13 (MASH) | 4 | EACH | $3,992.3400 | $15,969.36 | $4,400.0000 | $17,600.00 | $4,000.0000 | $16,000.00 |
| 630C080 | Guardrail End Anchor, Type 20 Series (MASH) | 12 | EACH | $3,792.7200 | $45,512.64 | $4,180.0000 | $50,160.00 | $3,800.0000 | $45,600.00 |
| 630G003 | Steel Beam Guardrail for Culvert, Class A, Type 2, Case 3 | 100 | LF | $199.6200 | $19,962.00 | $220.0000 | $22,000.00 | $200.0000 | $20,000.00 |
| 650A000 | Topsoil | 500 | CUYD | $45.6700 | $22,835.00 | $17.0000 | $8,500.00 | $129.9200 | $64,960.00 |
| 652A100 | Seeding | 13 | ACRE | $748.5600 | $9,731.28 | $965.0000 | $12,545.00 | $765.0000 | $9,945.00 |
| 652C000 | Mowing | 28 | ACRE | $129.7500 | $3,633.00 | $145.0000 | $4,060.00 | $132.0000 | $3,696.00 |
| 656A010 | Mulching | 13 | ACRE | $359.3100 | $4,671.03 | $485.0000 | $6,305.00 | $367.0000 | $4,771.00 |
| 659C002 | Erosion Control Product, Type S2 | 2,000 | SQYD | $3.6500 | $7,300.00 | $4.0000 | $8,000.00 | $3.7500 | $7,500.00 |
| 665E000 | Polyethylene | 1,000 | SQYD | $2.3500 | $2,350.00 | $0.2700 | $270.00 | $5.1000 | $5,100.00 |
| 665G000 | Sand Bags | 100 | EACH | $5.8400 | $584.00 | $6.0000 | $600.00 | $6.0000 | $600.00 |
| 665J002 | Silt Fence | 970 | LF | $1.0600 | $1,028.20 | $1.5000 | $1,455.00 | $1.0800 | $1,047.60 |
| 665O001 | Silt Fence Removal | 970 | LF | $0.0100 | $9.70 | $0.1000 | $97.00 | $0.0000 | $0.00 |
| 665P005 | Inlet Protection, Stage 3 Or 4 | 4 | EACH | $65.8700 | $263.48 | $75.0000 | $300.00 | $67.0000 | $268.00 |
| 665Q002 | Wattle | 1,020 | LF | $1.0600 | $1,081.20 | $1.5000 | $1,530.00 | $1.0800 | $1,101.60 |
| 698A000 | Construction Fuel (Maximum Bid Limited to $ 110,000.00) | 1 | LS | $55,000.0000 | $55,000.00 | $0.0000 | $0.00 | $0.0000 | $0.00 |
| 701A227 | Solid White, Class 2, Type A Traffic Stripe (5" Wide) | 13 | MILE | $3,795.9100 | $49,346.83 | $4,182.5300 | $54,372.89 | $3,646.0000 | $47,398.00 |
| 701A230 | Solid Yellow, Class 2, Type A Traffic Stripe (5" Wide) | 10 | MILE | $3,795.9100 | $37,959.10 | $4,182.5300 | $41,825.30 | $3,646.0000 | $36,460.00 |
| 701A244 | Broken Yellow, Class 2, Type A Traffic Stripe (5" Wide) | 3 | MILE | $1,900.6100 | $5,701.83 | $2,094.1900 | $6,282.57 | $1,825.0000 | $5,475.00 |
| 701B207 | Dotted, Class 2, Type A Traffic Stripe (5" Wide) | 703 | LF | $1.0600 | $745.18 | $1.1700 | $822.51 | $1.0500 | $738.15 |
| 701C000 | Broken Temporary Traffic Stripe | 7 | MILE | $663.6200 | $4,645.34 | $731.2100 | $5,118.47 | $637.0000 | $4,459.00 |
| 701C001 | Solid Temporary Traffic Stripe | 68 | MILE | $690.1600 | $46,930.88 | $760.4600 | $51,711.28 | $663.0000 | $45,084.00 |
| 701D007 | Solid Traffic Stripe Removed (Paint) | 1 | MILE | $10.6200 | $10.62 | $11.7000 | $11.70 | $10.2000 | $10.20 |
| 701D008 | Solid Traffic Stripe Removed (Plastic) | 1 | MILE | $10.6200 | $10.62 | $11.7000 | $11.70 | $10.2000 | $10.20 |
| 701D014 | Broken Traffic Stripe Removed (Paint) | 1 | MILE | $10.6200 | $10.62 | $11.7000 | $11.70 | $10.2000 | $10.20 |
| 701D015 | Broken Traffic Stripe Removed (Plastic) | 1 | MILE | $10.6200 | $10.62 | $11.7000 | $11.70 | $10.2000 | $10.20 |
| 701G146 | Solid White, Class W, Type A Traffic Stripe (5" Wide) | 1,249 | LF | $4.7800 | $5,970.22 | $5.2600 | $6,569.74 | $4.6000 | $5,745.40 |
| 701G150 | Broken Yellow, Class W, Type A Traffic Stripe (5" Wide) | 625 | LF | $2.6500 | $1,656.25 | $2.9200 | $1,825.00 | $2.5500 | $1,593.75 |
| 703A002 | Traffic Control Markings, Class 2, Type A | 7,407 | SQFT | $4.2500 | $31,479.75 | $4.6800 | $34,664.76 | $4.0800 | $30,220.56 |
| 703B002 | Traffic Control Legends, Class 2, Type A | 249 | SQFT | $5.3100 | $1,322.19 | $5.8500 | $1,456.65 | $5.1000 | $1,269.90 |
| 703D001 | Temporary Traffic Control Markings | 7,437 | SQFT | $1.0600 | $7,883.22 | $1.1700 | $8,701.29 | $1.0000 | $7,437.00 |
| 703E001 | Temporary Traffic Control Legends | 274 | SQFT | $1.5900 | $435.66 | $1.7500 | $479.50 | $1.5500 | $424.70 |
| 705A030 | Pavement Markers, Class A-H, Type 2-C | 176 | EACH | $4.2500 | $748.00 | $4.6800 | $823.68 | $4.0800 | $718.08 |
| 705A032 | Pavement Markers, Class A-H, Type 1-B | 1,008 | EACH | $4.2500 | $4,284.00 | $4.6800 | $4,717.44 | $4.0800 | $4,112.64 |
| 705A037 | Pavement Markers, Class A-H, Type 2-D | 641 | EACH | $4.2500 | $2,724.25 | $4.6800 | $2,999.88 | $4.0800 | $2,615.28 |
| 705A038 | Pavement Markers, Class A-H, Type 2-E | 439 | EACH | $4.2500 | $1,865.75 | $4.6800 | $2,054.52 | $4.0800 | $1,791.12 |
| 705A039 | Pavement Markers, Class A-H, Type 2-A | 16 | EACH | $4.2500 | $68.00 | $4.6800 | $74.88 | $4.0800 | $65.28 |
| 731A021 | Traffic Counting Units, Type R | 1 | EACH | $14,334.1900 | $14,334.19 | $13,750.0000 | $13,750.00 | $11,985.0000 | $11,985.00 |
| 731B000 | Pole for Mounting Traffic Detection Equipment | 1 | EACH | $14,334.1900 | $14,334.19 | $12,345.0000 | $12,345.00 | $10,760.0000 | $10,760.00 |
| 740B000 | Construction Signs | 1,166 | SQFT | $6.3700 | $7,427.42 | $7.0000 | $8,162.00 | $6.1000 | $7,112.60 |
| 740C000 | Special Construction Signs | 14 | SQFT | $6.3700 | $89.18 | $7.0000 | $98.00 | $6.1000 | $85.40 |
| 740E000 | Cones (36 Inches High) | 200 | EACH | $26.9800 | $5,396.00 | $20.0000 | $4,000.00 | $23.0000 | $4,600.00 |
| 740O000 | Pilot Car | 1 | EACH | $500.0000 | $500.00 | $1,500.0000 | $1,500.00 | $1,000.0000 | $1,000.00 |
Source: public Alabama DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →