FL Florida DOT · Bid Tabulation

Contract T3996

SR 77 (MAIN ST) FROM S OF 5TH ST TO S OF SR 273 (GLENWOOD...

County
WASHINGTON
Letting
April 29, 2026
Bidders
4
Apparent low bid AMERICAN SAND & X-CAVATION, INC. DBA AMERICAN SAND & ASPHALT PAVING $1,446,950.16
Other bidders C.W. ROBERTS CONTRACTING, INC. $1,497,745.71 SOUTHEAST CONSTRUCTION COMPANY LLC $1,599,481.44 ANDERSON COLUMBIA CO., INC. $1,628,439.66

Bid Items - unit price and extension by bidder

Item Description Qty UOM AMERICAN SAND & X-CAVATION, INC. DBA AMERICAN SAND & ASPHALT PAVING $1,446,950.16 C.W. ROBERTS CONTRACTING, INC. $1,497,745.71 SOUTHEAST CONSTRUCTION COMPANY LLC $1,599,481.44 ANDERSON COLUMBIA CO., INC. $1,628,439.66
Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension
0101 1 MOBILIZATION 1 LS $40,000.0000 $40,000.00 $61,500.0000 $61,500.00 $119,750.0000 $119,750.00 $156,547.5000 $156,547.50
0102 1 MAINTENANCE OF TRAFFIC 120 DA (LS) $60,000.0000 $60,000.00 $69,640.0000 $69,640.00 $57,500.0000 $57,500.00 $33,697.8600 $33,697.86
0102 14 TRAFFIC CONTROL OFFICER 236 HR $90.0000 $21,240.00 $125.5100 $29,620.36 $115.0000 $27,140.00 $112.1600 $26,469.76
0102 60 WORK ZONE SIGN 7,710 ED $0.3000 $2,313.00 $0.4000 $3,084.00 $0.4500 $3,469.50 $0.4500 $3,469.50
0102 74 1 CHANNELIZING DEVICE- TYPES I, II, DI, VP, DRUM, OR LCD 1,207 ED $0.2000 $241.40 $0.2000 $241.40 $0.2200 $265.54 $0.2200 $265.54
0102 74 8 CHANNELIZING DEVICE- PEDESTRIAN LCD (LONGITUDINAL CHANNELIZING DEVICE) 156 FD $3.0000 $468.00 $2.5100 $391.56 $2.6500 $413.40 $2.8000 $436.80
0102 99 PORTABLE CHANGEABLE MESSAGE SIGN, TEMPORARY 271 ED $35.0000 $9,485.00 $20.0800 $5,441.68 $22.0000 $5,962.00 $22.4300 $6,078.53
0102104 TEMPORARY SIGNALIZATION AND MAINTENANCE, INTERSECTION 360 ED $20.7000 $7,452.00 $15.7500 $5,670.00 $11.0000 $3,960.00 $11.2200 $4,039.20
0102107 1 TEMPORARY TRAFFIC DETECTION AND MAINTENANCE, INTERSECTION 360 ED $20.7000 $7,452.00 $15.7500 $5,670.00 $11.0000 $3,960.00 $11.2200 $4,039.20
0102115 TYPE III BARRICADE 6 ED $50.0000 $300.00 $50.2000 $301.20 $55.0000 $330.00 $56.0800 $336.48
0104 10 3 SEDIMENT BARRIER 389 LF $10.0000 $3,890.00 $9.7500 $3,792.75 $3.5000 $1,361.50 $3.9300 $1,528.77
0104 18 INLET PROTECTION SYSTEM 19 EA $300.0000 $5,700.00 $184.7100 $3,509.49 $200.0000 $3,800.00 $168.2400 $3,196.56
0107 1 LITTER REMOVAL 33.14 AC $140.0000 $4,639.60 $130.5300 $4,325.76 $40.0000 $1,325.60 $112.1700 $3,717.31
0107 2 MOWING 28.96 AC $140.0000 $4,054.40 $130.5300 $3,780.15 $40.0000 $1,158.40 $112.1700 $3,248.44
0110 1 1 CLEARING & GRUBBING 0.06 AC (LS) $20,000.0000 $20,000.00 $1,437.3800 $1,437.38 $26,500.0000 $26,500.00 $17,581.8100 $17,581.81
0110 2 2 SELECTIVE CLEARING AND GRUBBING, AREAS WITH TREES TO REMAIN 0.01 AC $100,000.0000 $1,000.00 $329,523.0000 $3,295.23 $150,000.0000 $1,500.00 $234,291.6700 $2,342.92
0110 21 TREE PROTECTION BARRIER 25 LF $100.0000 $2,500.00 $20.0800 $502.00 $5.0000 $125.00 $5.6100 $140.25
0110 4 10 REMOVAL OF EXISTING CONCRETE 174 SY $36.0000 $6,264.00 $12.3000 $2,140.20 $50.0000 $8,700.00 $35.5900 $6,192.66
0120 2 2 BORROW EXCAVATION, TRUCK MEASURE 174.4 CY $35.0000 $6,104.00 $28.5100 $4,972.14 $25.0000 $4,360.00 $31.1700 $5,436.05
0160 4 TYPE B STABILIZATION 157 SY $30.0000 $4,710.00 $15.9800 $2,508.86 $54.0000 $8,478.00 $43.0000 $6,751.00
0285706 OPTIONAL BASE, BASE GROUP 06 153 SY $45.0000 $6,885.00 $28.7300 $4,395.69 $80.0000 $12,240.00 $51.2100 $7,835.13
0285711 OPTIONAL BASE, BASE GROUP 11 99 SY $65.0000 $6,435.00 $41.3600 $4,094.64 $110.0000 $10,890.00 $103.4900 $10,245.51
0327 70 5 MILLING EXISTING ASPHALT PAVEMENT, 2" AVG DEPTH 23,111 SY $2.0000 $46,222.00 $3.1700 $73,261.87 $3.0000 $69,333.00 $2.5500 $58,933.05
0327 70 6 MILLING EXISTING ASPHALT PAVEMENT, 1 1/2" AVG DEPTH 4,787 SY $2.5000 $11,967.50 $10.6500 $50,981.55 $4.0000 $19,148.00 $8.2100 $39,301.27
0327 70 7 MILLING EXISTING ASPHALT PAVEMENT, 4" AVG DEPTH 7,974 SY $2.9000 $23,124.60 $6.9800 $55,658.52 $4.5000 $35,883.00 $2.4600 $19,616.04
0334 1 53 SUPERPAVE ASPHALTIC CONCRETE, TRAFFIC C, PG76-22 904.8 TN $130.0000 $117,624.00 $159.6500 $144,451.32 $164.0000 $148,387.20 $154.9500 $140,198.76
0337 7 83 ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-12.5, PG 76-22 3,791 TN $143.0000 $542,113.00 $154.6100 $586,126.51 $168.0000 $636,888.00 $158.1900 $599,698.29
0425 1341 INLETS, CURB, TYPE P-4, <10' 1 EA $12,000.0000 $12,000.00 $13,200.0100 $13,200.01 $10,500.0000 $10,500.00 $10,464.1600 $10,464.16
0425 2 63 MANHOLES, P-8, PARTIAL 1 EA $7,500.0000 $7,500.00 $6,667.1600 $6,667.16 $6,500.0000 $6,500.00 $8,288.0100 $8,288.01
0425 5 MANHOLE, ADJUST 3 EA $2,500.0000 $7,500.00 $1,884.8800 $5,654.64 $1,500.0000 $4,500.00 $2,437.7900 $7,313.37
0425 5 1 MANHOLE, ADJUST, UTILITIES 20 EA $2,500.0000 $50,000.00 $1,841.5900 $36,831.80 $1,500.0000 $30,000.00 $2,437.7900 $48,755.80
0425 6 VALVE BOXES, ADJUST 20 EA $2,500.0000 $50,000.00 $1,000.5600 $20,011.20 $1,000.0000 $20,000.00 $2,437.7900 $48,755.80
0430175115 PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 15"S/CD 22 LF $135.0000 $2,970.00 $220.1100 $4,842.42 $200.0000 $4,400.00 $195.1900 $4,294.18
0520 1 10 CONCRETE CURB & GUTTER, TYPE F 157 LF $68.0000 $10,676.00 $45.3500 $7,119.95 $75.0000 $11,775.00 $168.2400 $26,413.68
0520 1 12 CONCRETE CURB & GUTTER, TYPE F WITH SPECIAL GUTTER PROFILE 29 LF $78.0000 $2,262.00 $114.5200 $3,321.08 $125.0000 $3,625.00 $168.2400 $4,878.96
0522 2 CONCRETE SIDEWALK AND DRIVEWAYS, 6" THICK 112 SY $135.0000 $15,120.00 $99.5600 $11,150.72 $150.0000 $16,800.00 $112.1700 $12,563.04
0527 2 DETECTABLE WARNINGS 82 SF $80.0000 $6,560.00 $24.1000 $1,976.20 $40.0000 $3,280.00 $56.0800 $4,598.56
0570 1 2 PERFORMANCE TURF, SOD 889 SY $7.0000 $6,223.00 $10.5600 $9,387.84 $4.0000 $3,556.00 $4.4900 $3,991.61
0630 2 11 CONDUIT, FURNISH & INSTALL, OPEN TRENCH 3 LF $28.7500 $86.25 $21.0000 $63.00 $110.0000 $330.00 $112.1700 $336.51
0630 2 12 CONDUIT, FURNISH & INSTALL, DIRECTIONAL BORE 143 LF $66.7000 $9,538.10 $58.7900 $8,406.97 $45.0000 $6,435.00 $160.3900 $22,935.77
0632 7 1 SIGNAL CABLE- NEW OR RECONSTRUCTED INTERSECTION, FURNISH & INSTALL 2 PI $8,625.0000 $17,250.00 $3,674.2300 $7,348.46 $10,000.0000 $20,000.00 $10,094.4100 $20,188.82
0632 7 6 SIGNAL CABLE, REMOVE- INTERSECTION 2 PI $1,035.0000 $2,070.00 $314.9400 $629.88 $565.0000 $1,130.00 $560.8100 $1,121.62
0635 2 11 PULL & SPLICE BOX, F&I, 13" x 24" COVER SIZE 7 EA $1,840.0000 $12,880.00 $944.8000 $6,613.60 $1,450.0000 $10,150.00 $1,458.0800 $10,206.56
0646 1 11 ALUMINUM SIGNALS POLE, PEDESTAL 1 EA $3,795.0000 $3,795.00 $2,624.4500 $2,624.45 $3,750.0000 $3,750.00 $3,925.6000 $3,925.60
0646 1 60 ALUMINUM SIGNALS POLE, REMOVE 2 EA $517.5000 $1,035.00 $209.9600 $419.92 $550.0000 $1,100.00 $560.8100 $1,121.62
0650 2109 VEHICULAR SIGNAL AUXILIARIES, REPAIR/REPLACE/RETROFIT- FURNISH & INSTALL, BACKPLATE- FLEXIBLE REQUIRED 8 EA $862.5000 $6,900.00 $393.6700 $3,149.36 $550.0000 $4,400.00 $560.8100 $4,486.48
0653 1 12 PEDESTRIAN SIGNAL, FURNISH & INSTALL LED COUNTDOWN, 2 WAYS 1 AS $3,162.5000 $3,162.50 $1,616.6700 $1,616.67 $1,650.0000 $1,650.00 $1,682.4100 $1,682.41
0660 2101 LOOP ASSEMBLY- F&I, TYPE A 12 AS $1,955.0000 $23,460.00 $1,364.7200 $16,376.64 $1,350.0000 $16,200.00 $1,345.9200 $16,151.04
0660 2102 LOOP ASSEMBLY, F&I, TYPE B 2 AS $2,070.0000 $4,140.00 $1,154.7600 $2,309.52 $165.0000 $330.00 $168.2400 $336.48
0660 2106 LOOP ASSEMBLY, F&I, TYPE F 10 AS $2,530.0000 $25,300.00 $1,574.6700 $15,746.70 $2,250.0000 $22,500.00 $2,243.2000 $22,432.00
0665 1 11 PEDESTRIAN DETECTOR, FURNISH & INSTALL, STANDARD 4 EA $517.5000 $2,070.00 $498.6500 $1,994.60 $665.0000 $2,660.00 $672.9600 $2,691.84
0665 1 50 PEDESTRIAN DETECTOR, ADJUST/MODIFY ON EXISTING POLE 1 EA $287.5000 $287.50 $52.4900 $52.49 $335.0000 $335.00 $336.4900 $336.49
0665 1 60 PEDESTRIAN DETECTOR, REMOVE- POLE/PEDESTAL TO REMAIN 2 EA $115.0000 $230.00 $52.4900 $104.98 $115.0000 $230.00 $112.1700 $224.34
0700 1111 SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, LESS THAN 12 SF 4 EA $678.5000 $2,714.00 $451.8300 $1,807.32 $500.0000 $2,000.00 $504.7300 $2,018.92
0700 1112 SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, 12.0- 20.0 SF 1 EA $2,300.0000 $2,300.00 $2,008.1300 $2,008.13 $2,250.0000 $2,250.00 $2,243.2000 $2,243.20
0700 1500 SINGLE COLUMN GROUND SIGN ASSEMBLY, RELOCATE 1 EA $86.2500 $86.25 $251.0200 $251.02 $265.0000 $265.00 $280.4000 $280.40
0700 1600 SINGLE COLUMN GROUND SIGN ASSEMBLY, REMOVE 2 EA $51.7500 $103.50 $50.2100 $100.42 $55.0000 $110.00 $56.0800 $112.16
0700 5 22 INTERNALLY ILLUMINATED SIGN, FURNISH & INSTALL, OVERHEAD MOUNT, 12-18 SF 4 EA $8,625.0000 $34,500.00 $6,817.2800 $27,269.12 $4,200.0000 $16,800.00 $4,262.0900 $17,048.36
0706 1 3 RAISED PAVEMENT MARKER, TYPE B 935 EA $5.1750 $4,838.63 $4.5200 $4,226.20 $8.2500 $5,709.00 $8.4150 $5,823.18
0710 11101 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 6" 0.55 GM $1,725.0000 $948.75 $1,506.0900 $828.35 $1,500.0000 $825.00 $1,570.2400 $863.63
0710 11102 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR INTERCHANGE AND URBAN ISLAND, 8" 0.013 GM $1,725.0000 $22.43 $1,158.4600 $15.06 $1,150.0000 $14.95 $1,570.2400 $20.41
0710 11123 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR CROSSWALK AND ROUNDABOUT, 12" 301 LF $2.5875 $778.84 $2.2600 $680.26 $1.1000 $331.10 $1.1200 $337.12
0710 11124 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR DIAGONAL OR CHEVRON, 18" 91 LF $2.7600 $251.16 $2.4100 $219.31 $1.1000 $100.10 $1.1200 $101.92
0710 11125 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR STOP LINE OR CROSSWALK, 24" 322 LF $2.8750 $925.75 $2.5100 $808.22 $1.6500 $531.30 $1.6800 $540.96
0710 11170 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, ARROWS 5 EA $57.5000 $287.50 $50.2000 $251.00 $28.0000 $140.00 $28.0400 $140.20
0710 11201 PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SOLID, 6" 0.509 GM $1,725.0000 $878.03 $1,509.0600 $768.11 $2,000.0000 $1,018.00 $2,074.9700 $1,056.16
0710 11241 PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, 2-4 DOTTED GUIDELINE/6-10 DOTTED EXTENSION, 6" 0.131 GM $1,380.0000 $180.78 $1,195.6500 $156.63 $1,050.0000 $137.55 $1,121.6000 $146.93
0710 90 PAINTED PAVEMENT MARKINGS, FINAL SURFACE 1 LS $27,025.0000 $27,025.00 $23,595.5600 $23,595.56 $14,500.0000 $14,500.00 $14,446.2400 $14,446.24
0711 11123 THERMOPLASTIC, STANDARD, WHITE, SOLID, 12" FOR CROSSWALK AND ROUNDABOUT 2,046 LF $5.0025 $10,235.12 $4.3700 $8,941.02 $4.0000 $8,184.00 $3.9300 $8,040.78
0711 11124 THERMOPLASTIC, STANDARD, WHITE, SOLID, 18" FOR DIAGONALS AND CHEVRONS 292 LF $5.6925 $1,662.21 $4.9700 $1,451.24 $6.5000 $1,898.00 $6.7300 $1,965.16
0711 11125 THERMOPLASTIC, STANDARD, WHITE, SOLID, 24" FOR STOP LINE AND CROSSWALK 480 LF $7.0725 $3,394.80 $6.1800 $2,966.40 $7.7500 $3,720.00 $7.8500 $3,768.00
0711 11160 THERMOPLASTIC, STANDARD, WHITE, MESSAGE OR SYMBOL 2 EA $258.7500 $517.50 $225.9200 $451.84 $160.0000 $320.00 $168.2400 $336.48
0711 11170 THERMOPLASTIC, STANDARD, WHITE, ARROW 40 EA $86.2500 $3,450.00 $75.3100 $3,012.40 $100.0000 $4,000.00 $100.9400 $4,037.60
0711 11180 THERMOPLASTIC, STANDARD, WHITE, YIELD LINE 13 LF $19.8375 $257.89 $17.3200 $225.16 $11.0000 $143.00 $11.2200 $145.86
0711 11224 THERMOPLASTIC, STANDARD, YELLOW, SOLID, 18" FOR DIAGONAL OR CHEVRON 460 LF $5.6925 $2,618.55 $4.9700 $2,286.20 $6.5000 $2,990.00 $6.7300 $3,095.80
0711 11241 THERMOPLASTIC, STANDARD, YELLOW, 2-4 DOTTED GUIDE LINE /6-10 DOTTED EXTENSION LINE, 6" 0.131 GM $4,197.5000 $549.87 $3,636.8700 $476.43 $2,750.0000 $360.25 $2,804.0000 $367.32
0711 14125 THERMOPLASTIC, PREFORMED, WHITE, SOLID, 24" FOR CROSSWALK 1,087 LF $12.8225 $13,938.06 $11.2000 $12,174.40 $19.5000 $21,196.50 $19.0700 $20,729.09
0711 14191 THERMOPLASTIC, PREFORMED, 6" WHITE, RAILROAD DYNAMIC ENVELOPE 51 LF $5.1750 $263.93 $4.5200 $230.52 $5.6000 $285.60 $5.6100 $286.11
0711 14193 THERMOPLASTIC, PREFORMED, 12" WHITE ON ASPHALT PAVEMENT, RAILROAD DYNAMIC ENVELOPE 286 LF $5.9225 $1,693.84 $5.1700 $1,478.62 $11.0000 $3,146.00 $11.2200 $3,208.92
0711 16101 THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SOLID, 6" 3.095 GM $5,692.5000 $17,618.29 $4,978.1600 $15,407.41 $6,000.0000 $18,570.00 $5,720.1600 $17,703.90
0711 16102 THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SOLID, 8" 0.099 GM $6,842.5000 $677.41 $6,034.5500 $597.42 $6,100.0000 $603.90 $5,720.1600 $566.30
0711 16131 THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SKIP, 6",10-30 SKIP OR 3-9 LANE DROP 0.004 GM $5,750.0000 $23.00 $12,550.0000 $50.20 $5,100.0000 $20.40 $5,720.1600 $22.88
0711 16201 THERMOPLASTIC, STANDARD-OTHER SURFACES, YELLOW, SOLID, 6" 3.111 GM $5,692.5000 $17,709.37 $4,968.5300 $15,457.10 $6,100.0000 $18,977.10 $5,720.1600 $17,795.42
0711 16231 THERMOPLASTIC, STANDARD-OTHER SURFACES, YELLOW, SKIP, 6" 0.428 GM $2,875.0000 $1,230.50 $2,521.8900 $1,079.37 $2,850.0000 $1,219.80 $2,804.0000 $1,200.11
0711 17 1 THERMOPLASTIC, REMOVE EXISTING THERMOPLASTIC PAVEMENT MARKINGS- SURFACE TO REMAIN 45 SF $1.5410 $69.35 $1.3500 $60.75 $3.3500 $150.75 $3.3600 $151.20
0999 25 INITIAL CONTINGENCY AMOUNT, DO NOT BID 1 LS $50,000.0000 $50,000.00 $50,000.0000 $50,000.00 $50,000.0000 $50,000.00 $50,000.0000 $50,000.00