Florida DOT · Bid Tabulation
Contract T4737
SR 9 (I-95) AND SR 862 (I-595) AT VARIOUS LOCATIONS AS...
- County
- BROWARD, PALM BEACH
- Letting
- May 20, 2026
- Bidders
- 7
Apparent low bid
TRAFFIC MANAGEMENT SOLUTIONS, LLC
$2,856,390.99
Other bidders
AMERICAN LIGHTING AND SIGNALIZATION, LLC.
$3,049,595.68
SICE INC
$3,103,188.08
RTECH ENGINEERING, LLC
$3,363,406.66
ARC ELECTRIC INC
$3,456,789.00
AUM CONSTRUCTION INC.
$3,469,999.00
SIGNAL TECHNOLOGY AND INSTALLATION
$3,900,737.18
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | TRAFFIC MANAGEMENT SOLUTIONS, LLC $2,856,390.99 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. $3,049,595.68 | SICE INC $3,103,188.08 | RTECH ENGINEERING, LLC $3,363,406.66 | ARC ELECTRIC INC $3,456,789.00 | AUM CONSTRUCTION INC. $3,469,999.00 | SIGNAL TECHNOLOGY AND INSTALLATION $3,900,737.18 | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 0101 1 | MOBILIZATION | 2 | LS | $114,722.9106 | $229,445.82 | $107,988.0000 | $215,976.00 | $164,532.8200 | $329,065.64 | $147,500.0000 | $295,000.00 | $75,000.0000 | $150,000.00 | $135,000.0000 | $270,000.00 | $146,709.6450 | $293,419.29 |
| 0102 1 | MAINTENANCE OF TRAFFIC | 188 | DA (LS) | $157,454.0750 | $314,908.15 | $26,825.0000 | $53,650.00 | $88,301.4050 | $176,602.81 | $84,650.0000 | $169,300.00 | $75,000.0000 | $150,000.00 | $125,000.0000 | $250,000.00 | $63,666.7200 | $127,333.44 |
| 0102 60 | WORK ZONE SIGN | 1,892 | ED | $0.2800 | $529.76 | $0.2900 | $548.68 | $0.2600 | $491.92 | $0.3500 | $662.20 | $0.3000 | $567.60 | $1.0000 | $1,892.00 | $0.3600 | $681.12 |
| 0102 74 1 | CHANNELIZING DEVICE- TYPES I, II, DI, VP, DRUM, OR LCD | 6,404 | ED | $0.1300 | $832.52 | $0.1700 | $1,088.68 | $0.1200 | $768.48 | $0.2100 | $1,344.84 | $0.1500 | $960.60 | $0.3000 | $1,921.20 | $0.1800 | $1,152.72 |
| 0102 99 | PORTABLE CHANGEABLE MESSAGE SIGN, TEMPORARY | 342 | ED | $13.9200 | $4,760.64 | $17.0000 | $5,814.00 | $12.8100 | $4,381.02 | $23.0000 | $7,866.00 | $20.0000 | $6,840.00 | $15.0000 | $5,130.00 | $18.5000 | $6,327.00 |
| 0102112 | EXISTING ITS MAINTENANCE | 188 | DA | $280.9600 | $52,820.48 | $156.0000 | $29,328.00 | $178.1300 | $33,488.44 | $160.0000 | $30,080.00 | $450.0000 | $84,600.00 | $100.0000 | $18,800.00 | $192.0700 | $36,109.16 |
| 0102115 | TYPE III BARRICADE | 188 | ED | $0.3800 | $71.44 | $0.4000 | $75.20 | $0.3500 | $65.80 | $0.3500 | $65.80 | $1.0000 | $188.00 | $1.0000 | $188.00 | $0.9300 | $174.84 |
| 0107 1 | LITTER REMOVAL | 133.48 | AC | $32.5600 | $4,346.11 | $40.0000 | $5,339.20 | $27.6400 | $3,689.39 | $35.0000 | $4,671.80 | $50.0000 | $6,674.00 | $45.0000 | $6,006.60 | $71.0300 | $9,481.08 |
| 0107 2 | MOWING | 107.69 | AC | $40.8500 | $4,399.14 | $58.0000 | $6,246.02 | $142.7500 | $15,372.75 | $55.0000 | $5,922.95 | $20.0000 | $2,153.80 | $30.0000 | $3,230.70 | $66.5900 | $7,171.08 |
| 0327 70 5 | MILLING EXISTING ASPHALT PAVEMENT, 2" AVG DEPTH | 8,543 | SY | $5.7000 | $48,695.10 | $12.0000 | $102,516.00 | $10.1500 | $86,711.45 | $2.1500 | $18,367.45 | $5.0000 | $42,715.00 | $10.0000 | $85,430.00 | $20.9900 | $179,317.57 |
| 0334 1 13 | SUPERPAVE ASPHALTIC CONC, TRAFFIC C | 472.8 | TN | $255.7100 | $120,899.69 | $231.0000 | $109,216.80 | $362.9900 | $171,621.67 | $208.0000 | $98,342.40 | $285.0000 | $134,748.00 | $385.0000 | $182,028.00 | $490.8400 | $232,069.15 |
| 0337 7 82 | ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-9.5, PG 76-22 | 472.8 | TN | $298.7500 | $141,249.00 | $289.0000 | $136,639.20 | $419.6500 | $198,410.52 | $230.0000 | $108,744.00 | $240.0000 | $113,472.00 | $385.0000 | $182,028.00 | $526.4100 | $248,886.65 |
| 0611 1 1 | ITSFM SUBSURFACE DOCUMENTATION- PROJECT LENGTH | 3.205 | MI | $3,071.9600 | $9,845.63 | $3,808.0000 | $12,204.64 | $3,843.2400 | $12,317.58 | $3,450.0000 | $11,057.25 | $3,500.0000 | $11,217.50 | $4,300.0000 | $13,781.50 | $4,694.9800 | $15,047.41 |
| 0611 2 2 | ITSFM LOCATION DOCUMENTATION- ITS SITE | 11 | EA | $1,843.1800 | $20,274.98 | $2,187.0000 | $24,057.00 | $2,206.9500 | $24,276.45 | $2,900.0000 | $31,900.00 | $2,000.0000 | $22,000.00 | $2,400.0000 | $26,400.00 | $2,696.0600 | $29,656.66 |
| 0630 2 12 | CONDUIT, FURNISH & INSTALL, DIRECTIONAL BORE | 13,531 | LF | $24.0200 | $325,014.62 | $52.0000 | $703,612.00 | $29.1100 | $393,887.41 | $40.0000 | $541,240.00 | $40.0000 | $541,240.00 | $38.0000 | $514,178.00 | $41.0800 | $555,853.48 |
| 0630 2 14 | CONDUIT, FURNISH & INSTALL, ABOVEGROUND | 386 | LF | $42.4700 | $16,393.42 | $27.0000 | $10,422.00 | $69.8800 | $26,973.68 | $45.0000 | $17,370.00 | $45.0000 | $17,370.00 | $70.0000 | $27,020.00 | $45.0300 | $17,381.58 |
| 0633 1121 | FIBER OPTIC CABLE, F&I, UNDERGROUND,2-12 FIBERS | 17,251 | LF | $4.8700 | $84,012.37 | $4.0000 | $69,004.00 | $4.4800 | $77,284.48 | $4.2000 | $72,454.20 | $3.7500 | $64,691.25 | $4.7000 | $81,079.70 | $5.4800 | $94,535.48 |
| 0633 2 31 | FIBER OPTIC CONNECTION, INSTALL, SPLICE | 192 | EA | $56.9600 | $10,936.32 | $52.0000 | $9,984.00 | $52.4100 | $10,062.72 | $58.0000 | $11,136.00 | $55.0000 | $10,560.00 | $56.0000 | $10,752.00 | $64.0300 | $12,293.76 |
| 0633 3 11 | FIBER OPTIC CONNECTION HARDWARE, F&I, SPLICE ENCLOSURE | 2 | EA | $1,582.3400 | $3,164.68 | $1,443.0000 | $2,886.00 | $1,455.7700 | $2,911.54 | $1,595.0000 | $3,190.00 | $1,500.0000 | $3,000.00 | $1,550.0000 | $3,100.00 | $1,778.4100 | $3,556.82 |
| 0633 3 12 | FIBER OPTIC CONNECTION HARDWARE, F&I, SPLICE TRAY | 7 | EA | $63.2900 | $443.03 | $58.0000 | $406.00 | $58.2300 | $407.61 | $62.0000 | $434.00 | $65.0000 | $455.00 | $62.0000 | $434.00 | $71.1400 | $497.98 |
| 0633 3 16 | FIBER OPTIC CONNECTION HARDWARE, F&I, PATCH PANEL- FIELD TERMINATED | 12 | EA | $1,753.2400 | $21,038.88 | $1,598.0000 | $19,176.00 | $1,613.0000 | $19,356.00 | $1,850.0000 | $22,200.00 | $1,350.0000 | $16,200.00 | $1,700.0000 | $20,400.00 | $1,970.4700 | $23,645.64 |
| 0633 3 51 | FIBER OPTIC CONNECTION HARDWARE, ADJUST/MODIFY SPLICE ENCLOSURE | 5 | EA | $917.7600 | $4,588.80 | $837.0000 | $4,185.00 | $844.3500 | $4,221.75 | $875.0000 | $4,375.00 | $900.0000 | $4,500.00 | $900.0000 | $4,500.00 | $1,031.4800 | $5,157.40 |
| 0633 6 | FIBER OPTIC CABLE LOCATOR | 213 | DA | $191.1100 | $40,706.43 | $156.0000 | $33,228.00 | $157.2200 | $33,487.86 | $205.0000 | $43,665.00 | $200.0000 | $42,600.00 | $75.0000 | $15,975.00 | $192.0700 | $40,910.91 |
| 0635 2 11 | PULL & SPLICE BOX, F&I, 13" x 24" COVER SIZE | 67 | EA | $1,218.4000 | $81,632.80 | $1,463.0000 | $98,021.00 | $1,418.5100 | $95,040.17 | $1,525.0000 | $102,175.00 | $1,600.0000 | $107,200.00 | $1,500.0000 | $100,500.00 | $1,894.9300 | $126,960.31 |
| 0635 2 12 | PULL & SPLICE BOX, F&I, 24" X 36" COVER SIZE | 40 | EA | $2,333.1900 | $93,327.60 | $3,354.0000 | $134,160.00 | $2,551.6800 | $102,067.20 | $2,600.0000 | $104,000.00 | $3,200.0000 | $128,000.00 | $2,500.0000 | $100,000.00 | $2,845.4400 | $113,817.60 |
| 0635 3 12 | JUNCTION BOX, FURNISH & INSTALL, MOUNTED | 1 | EA | $1,080.7400 | $1,080.74 | $1,380.0000 | $1,380.00 | $1,164.6200 | $1,164.62 | $984.7700 | $984.77 | $2,088.0000 | $2,088.00 | $2,000.0000 | $2,000.00 | $1,344.4900 | $1,344.49 |
| 0639 2 1 | ELECTRICAL SERVICE WIRE, FURNISH & INSTALL | 5,741 | LF | $18.2500 | $104,773.25 | $13.0000 | $74,633.00 | $7.2700 | $41,737.07 | $20.0000 | $114,820.00 | $15.0000 | $86,115.00 | $24.0000 | $137,784.00 | $6.3300 | $36,340.53 |
| 0639 3 11 | ELECTRICAL SERVICE DISCONNECT, F&I, POLE MOUNT | 12 | EA | $3,120.6100 | $37,447.32 | $1,570.0000 | $18,840.00 | $3,617.8900 | $43,414.68 | $2,550.0000 | $30,600.00 | $4,000.0000 | $48,000.00 | $2,500.0000 | $30,000.00 | $5,005.8500 | $60,070.20 |
| 0639 6111 | ELECTRICAL POWER SERVICE- TRANSFORMER, F&I, <5 KVA, SINGLE PHASE, COPPER WINDINGS | 10 | EA | $2,493.7700 | $24,937.70 | $1,321.0000 | $13,210.00 | $3,306.3500 | $33,063.50 | $3,050.0000 | $30,500.00 | $7,410.0000 | $74,100.00 | $5,000.0000 | $50,000.00 | $5,179.0600 | $51,790.60 |
| 0641 2 12 | PRESTRESSED CONCRETE POLE, F&I, TYPE P-II SERVICE POLE | 12 | EA | $1,492.0700 | $17,904.84 | $1,734.0000 | $20,808.00 | $2,795.0000 | $33,540.00 | $2,800.0000 | $33,600.00 | $3,500.0000 | $42,000.00 | $2,500.0000 | $30,000.00 | $3,454.3400 | $41,452.08 |
| 0660 7 21 | VEHICLE DETECTION SYSTEM- WRONG WAY FOR EXIT RAMP, 1 OR 2 LANES, AC POWERED | 3 | EA | $32,777.4800 | $98,332.44 | $37,295.0000 | $111,885.00 | $40,535.7400 | $121,607.22 | $58,500.0000 | $175,500.00 | $70,000.0000 | $210,000.00 | $50,000.0000 | $150,000.00 | $55,416.4200 | $166,249.26 |
| 0660 7 22 | VEHICLE DETECTION SYSTEM- WRONG WAY FOR EXIT RAMP, 3 OR MORE LANES, AC POWERED | 8 | EA | $32,777.4800 | $262,219.84 | $37,523.0000 | $300,184.00 | $40,753.0300 | $326,024.24 | $60,500.0000 | $484,000.00 | $70,000.0000 | $560,000.00 | $50,000.0000 | $400,000.00 | $55,416.4200 | $443,331.36 |
| 0676 2143 | ITS CABINET, FURNISH & INSTALL, BASE MOUNT, 334, 24" W X 66" H X 30" D | 12 | EA | $10,701.2300 | $128,414.76 | $8,486.0000 | $101,832.00 | $15,503.8900 | $186,046.68 | $11,950.0000 | $143,400.00 | $9,000.0000 | $108,000.00 | $14,500.0000 | $174,000.00 | $14,611.3000 | $175,335.60 |
| 0684 1 1 | MANAGED FIELD ETHERNET SWITCH, FURNISH & INSTALL | 12 | EA | $11,754.5500 | $141,054.60 | $15,176.0000 | $182,112.00 | $10,349.6200 | $124,195.44 | $11,500.0000 | $138,000.00 | $6,500.0000 | $78,000.00 | $13,500.0000 | $162,000.00 | $13,115.9100 | $157,390.92 |
| 0685 1 11 | UNINTERRUPTIBLE POWER SUPPLY, FURNISH AND INSTALL, LINE INTERACTIVE | 12 | EA | $4,223.8600 | $50,686.32 | $8,187.0000 | $98,244.00 | $3,531.4200 | $42,377.04 | $7,950.0000 | $95,400.00 | $10,000.0000 | $120,000.00 | $6,500.0000 | $78,000.00 | $5,700.7300 | $68,408.76 |
| 0685 2 1 | REMOTE POWER MANAGEMENT UNIT- RPMU, FURNISH AND INSTALL | 12 | EA | $1,184.5300 | $14,214.36 | $864.0000 | $10,368.00 | $840.1000 | $10,081.20 | $1,150.0000 | $13,800.00 | $1,000.0000 | $12,000.00 | $1,500.0000 | $18,000.00 | $1,251.0200 | $15,012.24 |
| 0700 1111 | SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, LESS THAN 12 SF | 20 | EA | $659.0100 | $13,180.20 | $750.0000 | $15,000.00 | $698.7700 | $13,975.40 | $690.0000 | $13,800.00 | $750.0000 | $15,000.00 | $600.0000 | $12,000.00 | $1,102.6100 | $22,052.20 |
| 0700 1113 | SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, 20.1- 30.0 SF | 1 | EA | $3,268.5100 | $3,268.51 | $2,885.0000 | $2,885.00 | $3,843.2400 | $3,843.24 | $2,885.0000 | $2,885.00 | $4,000.0000 | $4,000.00 | $3,300.0000 | $3,300.00 | $1,397.1200 | $1,397.12 |
| 0700 1211 | SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I BARRIER TOP-MOUNT, LESS THAN 12 SF | 1 | EA | $3,199.8900 | $3,199.89 | $2,539.0000 | $2,539.00 | $3,610.3200 | $3,610.32 | $2,570.0000 | $2,570.00 | $3,600.2500 | $3,600.25 | $3,100.0000 | $3,100.00 | $4,835.8400 | $4,835.84 |
| 0700 13 12 | RETROREFLECTIVE SIGN STRIP- FURNISH AND INSTALL, 2' | 22 | EA | $84.6800 | $1,862.96 | $129.0000 | $2,838.00 | $110.6400 | $2,434.08 | $110.0000 | $2,420.00 | $110.0000 | $2,420.00 | $100.0000 | $2,200.00 | $177.8400 | $3,912.48 |
| 0700 13 15 | RETROREFLECTIVE SIGN STRIP- FURNISH AND INSTALL, 5' | 16 | EA | $131.7600 | $2,108.16 | $181.0000 | $2,896.00 | $139.7500 | $2,236.00 | $135.0000 | $2,160.00 | $145.0000 | $2,320.00 | $150.0000 | $2,400.00 | $211.9900 | $3,391.84 |
| 0700 1600 | SINGLE COLUMN GROUND SIGN ASSEMBLY, REMOVE | 24 | EA | $75.2000 | $1,804.80 | $87.0000 | $2,088.00 | $40.7600 | $978.24 | $230.0000 | $5,520.00 | $200.0000 | $4,800.00 | $50.0000 | $1,200.00 | $106.7100 | $2,561.04 |
| 0700 3201 | SIGN PANEL, FURNISH & INSTALL OVERHEAD MOUNT, UP TO 12 SF | 4 | EA | $898.7900 | $3,595.16 | $1,117.0000 | $4,468.00 | $1,281.0800 | $5,124.32 | $847.5000 | $3,390.00 | $1,200.0000 | $4,800.00 | $1,500.0000 | $6,000.00 | $980.4900 | $3,921.96 |
| 0700 3204 | SIGN PANEL, FURNISH & INSTALL OVERHEAD MOUNT, 31-50 SF | 2 | EA | $3,138.4700 | $6,276.94 | $2,496.0000 | $4,992.00 | $3,493.8600 | $6,987.72 | $3,262.5000 | $6,525.00 | $3,300.0000 | $6,600.00 | $3,000.0000 | $6,000.00 | $4,268.1600 | $8,536.32 |
| 0700141140 | ENHANCED HIGHWAY SIGN ASSEMBLY, AC POWERED, F&I GROUND MOUNT, HIGHLIGHTED SIGN <12 SF | 11 | EA | $8,299.6400 | $91,296.04 | $5,692.0000 | $62,612.00 | $5,526.3800 | $60,790.18 | $7,000.0000 | $77,000.00 | $12,500.0000 | $137,500.00 | $6,200.0000 | $68,200.00 | $12,534.4500 | $137,878.95 |
| 0700141440 | ENHANCED HIGHWAY SIGN ASSEMBLY, AC POWERED, F&I BARRIER SIDE MOUNT, HIGHLIGHTED SIGN <12 SF | 1 | EA | $10,666.1600 | $10,666.16 | $4,175.0000 | $4,175.00 | $8,949.2800 | $8,949.28 | $8,500.0000 | $8,500.00 | $15,000.0000 | $15,000.00 | $6,500.0000 | $6,500.00 | $15,155.8700 | $15,155.87 |
| 0700142140 | ENHANCED HIGHWAY SIGN ASSEMBLY, SOLAR POWERED, F&I GROUND MOUNT, HIGHLIGHTED SIGN <12 SF | 7 | EA | $7,949.8200 | $55,648.74 | $6,998.0000 | $48,986.00 | $7,443.3500 | $52,103.45 | $8,750.0000 | $61,250.00 | $12,000.0000 | $84,000.00 | $7,500.0000 | $52,500.00 | $12,965.2700 | $90,756.89 |
| 0700142240 | ENHANCED HIGHWAY SIGN ASSEMBLY, SOLAR POWERED, F&I BARRIER TOP MOUNT, HIGHLIGHTED SIGN <12 SF | 3 | EA | $9,499.6400 | $28,498.92 | $5,422.0000 | $16,266.00 | $10,851.2900 | $32,553.87 | $10,500.0000 | $31,500.00 | $15,000.0000 | $45,000.00 | $8,000.0000 | $24,000.00 | $16,009.8900 | $48,029.67 |
| 0700142440 | ENHANCED HIGHWAY SIGN ASSEMBLY, SOLAR POWERED, F&I BARRIER SIDE MOUNT, HIGHLIGHTED SIGN <12 SF | 2 | EA | $9,194.8800 | $18,389.76 | $5,422.0000 | $10,844.00 | $10,810.1700 | $21,620.34 | $11,500.0000 | $23,000.00 | $15,000.0000 | $30,000.00 | $8,000.0000 | $16,000.00 | $15,586.6900 | $31,173.38 |
| 0706 1 3 | RAISED PAVEMENT MARKER, TYPE B | 1,066 | EA | $6.3300 | $6,747.78 | $6.0000 | $6,396.00 | $5.8200 | $6,204.12 | $4.8500 | $5,170.10 | $7.0000 | $7,462.00 | $10.0000 | $10,660.00 | $7.1200 | $7,589.92 |
| 0710 90 | PAINTED PAVEMENT MARKINGS, FINAL SURFACE | 2 | LS | $6,012.8900 | $12,025.78 | $26,435.0000 | $52,870.00 | $7,628.2550 | $15,256.51 | $39,250.0000 | $78,500.00 | $5,250.0000 | $10,500.00 | $5,490.1500 | $10,980.30 | $20,763.7650 | $41,527.53 |
| 0711 11125 | THERMOPLASTIC, STANDARD, WHITE, SOLID, 24" FOR STOP LINE AND CROSSWALK | 24 | LF | $15.1900 | $364.56 | $9.0000 | $216.00 | $13.9800 | $335.52 | $7.5000 | $180.00 | $15.0000 | $360.00 | $25.0000 | $600.00 | $5.8700 | $140.88 |
| 0711 11160 | THERMOPLASTIC, STANDARD, WHITE, MESSAGE OR SYMBOL | 6 | EA | $379.7600 | $2,278.56 | $127.0000 | $762.00 | $349.3900 | $2,096.34 | $185.0000 | $1,110.00 | $325.0000 | $1,950.00 | $500.0000 | $3,000.00 | $284.5500 | $1,707.30 |
| 0711 11170 | THERMOPLASTIC, STANDARD, WHITE, ARROW | 97 | EA | $113.9300 | $11,051.21 | $130.0000 | $12,610.00 | $104.8200 | $10,167.54 | $89.0000 | $8,633.00 | $120.0000 | $11,640.00 | $150.0000 | $14,550.00 | $142.2800 | $13,801.16 |
| 0711 15101 | THERMOPLASTIC, STANDARD-OPEN GRADED ASPHALT SURFACES WHITE, SOLID, 6" | 0.702 | GM | $10,759.9100 | $7,553.46 | $17,265.0000 | $12,120.03 | $9,899.2600 | $6,949.28 | $6,150.0000 | $4,317.30 | $9,500.0000 | $6,669.00 | $12,000.0000 | $8,424.00 | $7,139.2400 | $5,011.75 |
| 0711 15131 | THERMOPLASTIC, STANDARD-OPEN GRADED ASPHALT SURFACES, WHITE, SKIP, 6",10-30 SKIP OR 3-9 LANE DROP | 0.152 | GM | $5,696.4200 | $865.86 | $4,316.0000 | $656.03 | $5,240.7800 | $796.60 | $2,550.0000 | $387.60 | $6,000.0000 | $912.00 | $6,750.0000 | $1,026.00 | $2,205.4000 | $335.22 |
| 0711 15201 | THERMOPLASTIC, STANDARD-OPEN GRADED ASPHALT SURFACES, YELLOW, SOLID, 6" | 0.4 | GM | $10,759.9100 | $4,303.96 | $15,243.0000 | $6,097.20 | $9,899.2600 | $3,959.70 | $6,050.0000 | $2,420.00 | $10,000.0000 | $4,000.00 | $12,000.0000 | $4,800.00 | $7,139.2300 | $2,855.69 |
| 0999 16 | PARTNERING, DO NOT BID | 1 | LS | $6,000.0000 | $6,000.00 | $6,000.0000 | $6,000.00 | $6,000.0000 | $6,000.00 | $6,000.0000 | $6,000.00 | $6,000.0000 | $6,000.00 | $6,000.0000 | $6,000.00 | $6,000.0000 | $6,000.00 |
| 0999 25 | INITIAL CONTINGENCY AMOUNT, DO NOT BID | 2 | LS | $25,000.0000 | $50,000.00 | $25,000.0000 | $50,000.00 | $25,000.0000 | $50,000.00 | $25,000.0000 | $50,000.00 | $25,000.0000 | $50,000.00 | $25,000.0000 | $50,000.00 | $25,000.0000 | $50,000.00 |
Source: public Florida DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.