FL Florida DOT · Bid Tabulation

Contract T7587

SR 597 (N DALE MABRY HWY) FROM N OF W SOUTH AVE TO N OF W...

County
HILLSBOROUGH
Letting
May 20, 2026
Bidders
5
Apparent low bid HUBBARD CONSTRUCTION COMPANY $7,418,952.86
Other bidders C.W. ROBERTS CONTRACTING, INC. $7,469,177.33 PREFERRED MATERIALS INC. $8,978,340.43 AJAX PAVING INDUSTRIES OF FLORIDA LLC $10,788,825.03 SUPERIOR ASPHALT, INC. $12,612,001.00

Bid Items - unit price and extension by bidder

Item Description Qty UOM HUBBARD CONSTRUCTION COMPANY $7,418,952.86 C.W. ROBERTS CONTRACTING, INC. $7,469,177.33 PREFERRED MATERIALS INC. $8,978,340.43 AJAX PAVING INDUSTRIES OF FLORIDA LLC $10,788,825.03 SUPERIOR ASPHALT, INC. $12,612,001.00
Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension
0101 1 MOBILIZATION 1 LS $397,113.2300 $397,113.23 $819,000.0000 $819,000.00 $698,648.3500 $698,648.35 $690,000.0000 $690,000.00 $850,000.0000 $850,000.00
0102 1 MAINTENANCE OF TRAFFIC 225 DA (LS) $237,800.4800 $237,800.48 $343,000.0000 $343,000.00 $640,726.1200 $640,726.12 $680,000.0000 $680,000.00 $665,120.7200 $665,120.72
0102 14 TRAFFIC CONTROL OFFICER 1,512 HR $93.0300 $140,661.36 $88.2500 $133,434.00 $8.0000 $12,096.00 $113.7900 $172,050.48 $115.0000 $173,880.00
0102 4 1 PEDESTRIAN OR BICYCLE SPECIAL DETOUR 516 SY (LS) $20,013.0300 $20,013.03 $30,300.0000 $30,300.00 $47,089.2000 $47,089.20 $120,162.6800 $120,162.68 $44,500.0000 $44,500.00
0102 5 PEDESTRIAN ESCORT/FLAGGER 201 HR $38.6800 $7,774.68 $47.7500 $9,597.75 $29.7600 $5,981.76 $108.4400 $21,796.44 $60.0000 $12,060.00
0102 60 WORK ZONE SIGN 20,668 ED $0.2100 $4,340.28 $0.2000 $4,133.60 $0.2000 $4,133.60 $0.2100 $4,340.28 $0.2500 $5,167.00
0102 71 13 TEMPORARY BARRIER, F&I, LOW PROFILE, CONCRETE 1,404 LF $42.2200 $59,276.88 $39.4500 $55,387.80 $40.5500 $56,932.20 $49.6900 $69,764.76 $45.5000 $63,882.00
0102 71 23 TEMPORARY BARRIER, RELOCATE, LOW PROFILE CONCRETE 264 LF $20.0000 $5,280.00 $18.7000 $4,936.80 $19.2100 $5,071.44 $23.5400 $6,214.56 $21.5000 $5,676.00
0102 74 1 CHANNELIZING DEVICE- TYPES I, II, DI, VP, DRUM, OR LCD 41,919 ED $0.1100 $4,611.09 $0.1000 $4,191.90 $0.1100 $4,611.09 $0.1100 $4,611.09 $0.1500 $6,287.85
0102 74 8 CHANNELIZING DEVICE- PEDESTRIAN LCD (LONGITUDINAL CHANNELIZING DEVICE) 17,473 FD $0.0400 $698.92 $0.0500 $873.65 $0.0400 $698.92 $0.0400 $698.92 $0.0500 $873.65
0102 76 ARROW BOARD / ADVANCE WARNING ARROW PANEL 496 ED $4.4400 $2,202.24 $4.1500 $2,058.40 $4.2700 $2,117.92 $4.3300 $2,147.68 $4.8000 $2,380.80
0102 99 PORTABLE CHANGEABLE MESSAGE SIGN, TEMPORARY 790 ED $10.0000 $7,900.00 $9.3500 $7,386.50 $9.6000 $7,584.00 $9.7500 $7,702.50 $10.0000 $7,900.00
0102104 TEMPORARY SIGNALIZATION AND MAINTENANCE, INTERSECTION 705 ED $6.9100 $4,871.55 $17.0500 $12,020.25 $6.6400 $4,681.20 $14.9000 $10,504.50 $16.5000 $11,632.50
0102107 1 TEMPORARY TRAFFIC DETECTION AND MAINTENANCE, INTERSECTION 675 ED $28.9200 $19,521.00 $17.0500 $11,508.75 $27.7800 $18,751.50 $8.9400 $6,034.50 $10.0000 $6,750.00
0102112 EXISTING ITS MAINTENANCE 225 DA $143.7200 $32,337.00 $106.0000 $23,850.00 $138.0300 $31,056.75 $200.4800 $45,108.00 $225.0000 $50,625.00
0102115 TYPE III BARRICADE 990 ED $0.3900 $386.10 $0.3500 $346.50 $0.3700 $366.30 $0.3800 $376.20 $0.4500 $445.50
0104 18 INLET PROTECTION SYSTEM 92 EA $104.2200 $9,588.24 $377.0000 $34,684.00 $98.1800 $9,032.56 $151.5300 $13,940.76 $150.0000 $13,800.00
0107 1 LITTER REMOVAL 268.32 AC $56.9100 $15,270.09 $67.8500 $18,205.51 $64.1900 $17,223.46 $80.4200 $21,578.29 $62.5000 $16,770.00
0107 2 MOWING 166.52 AC $129.1500 $21,506.06 $115.0000 $19,149.80 $103.4100 $17,219.83 $80.4200 $13,391.54 $141.7500 $23,604.21
0110 1 1 CLEARING & GRUBBING 0.34 AC (LS) $230,255.1500 $230,255.15 $30,500.0000 $30,500.00 $195,425.3500 $195,425.35 $89,765.3600 $89,765.36 $250,000.0000 $250,000.00
0110 4 10 REMOVAL OF EXISTING CONCRETE 842 SY $47.2100 $39,750.82 $62.2500 $52,414.50 $45.3500 $38,184.70 $82.0400 $69,077.68 $51.5000 $43,363.00
0120 1 REGULAR EXCAVATION 1,710.8 CY $30.6200 $52,384.70 $10.2500 $17,535.70 $29.4100 $50,314.63 $39.2000 $67,063.36 $33.3500 $57,055.18
0120 6 EMBANKMENT 1,747.2 CY $42.8700 $74,902.46 $10.6500 $18,607.68 $41.1700 $71,932.22 $38.3800 $67,057.54 $46.5000 $81,244.80
0160 4 TYPE B STABILIZATION 350 SY $67.1800 $23,513.00 $61.8500 $21,647.50 $64.2100 $22,473.50 $73.9900 $25,896.50 $73.0000 $25,550.00
0285706 OPTIONAL BASE, BASE GROUP 06 350 SY $76.8500 $26,897.50 $61.8500 $21,647.50 $104.3900 $36,536.50 $79.9400 $27,979.00 $66.0000 $23,100.00
0327 70 2 MILLING EXISTING ASPHALT PAVEMENT, 3 1/2" AVG DEPTH 87,056 SY $1.9200 $167,147.52 $2.8500 $248,109.60 $1.9700 $171,500.32 $5.3700 $467,490.72 $4.0000 $348,224.00
0327 70 4 MILLING EXISTING ASPHALT PAVEMENT, 3" AVG DEPTH 8,415 SY $3.4600 $29,115.90 $3.0000 $25,245.00 $4.3800 $36,857.70 $7.2300 $60,840.45 $5.5000 $46,282.50
0327 70 6 MILLING EXISTING ASPHALT PAVEMENT, 1 1/2" AVG DEPTH 46,873 SY $3.4000 $159,368.20 $3.8000 $178,117.40 $4.5100 $211,397.23 $5.4900 $257,332.77 $5.7500 $269,519.75
0334 1 53 SUPERPAVE ASPHALTIC CONCRETE, TRAFFIC C, PG76-22 10,615.9 TN $149.5400 $1,587,501.69 $140.0000 $1,486,226.00 $165.7200 $1,759,266.95 $165.5000 $1,756,931.45 $221.5000 $2,351,421.85
0337 7 83 ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-12.5, PG 76-22 11,460.7 TN $154.8900 $1,775,147.82 $158.0000 $1,810,790.60 $215.2300 $2,466,686.46 $184.4000 $2,113,353.08 $228.3500 $2,617,050.85
0339 1 MISCELLANEOUS ASPHALT PAVEMENT 37.2 TN $410.6900 $15,277.67 $263.0000 $9,783.60 $563.2400 $20,952.53 $641.0100 $23,845.57 $350.0000 $13,020.00
0350 5 CLEANING & SEALING JOINTS- CONCRETE PAVEMENT 89 LF $65.6700 $5,844.63 $77.9000 $6,933.10 $64.0300 $5,698.67 $113.7300 $10,121.97 $90.0000 $8,010.00
0400 2 1 CONCRETE CLASS II, CULVERTS 6.2 CY $2,273.6200 $14,096.44 $2,280.0000 $14,136.00 $2,187.7600 $13,564.11 $2,175.2800 $13,486.74 $2,450.0000 $15,190.00
0400 4 5 CONCRETE CLASS IV, BRIDGE SUBSTRUCTURE 76.6 CY $2,457.0500 $188,210.03 $2,330.0000 $178,478.00 $2,347.8400 $179,844.54 $2,709.2300 $207,527.02 $7,200.0000 $551,520.00
0415 1 1 REINFORCING STEEL- ROADWAY 1,241 LB $8.3800 $10,399.58 $2.7000 $3,350.70 $2.7700 $3,437.57 $1.3500 $1,675.35 $9.0000 $11,169.00
0415 1 5 REINFORCING STEEL- BRIDGE SUBSTRUCTURE 21,006 LB $6.3700 $133,808.22 $6.0500 $127,086.30 $6.0800 $127,716.48 $3.2500 $68,269.50 $6.6500 $139,689.90
0425 1315 INLETS, CURB TYPE P-1, PARTIAL 2 EA $10,606.6700 $21,213.34 $10,100.0000 $20,200.00 $10,186.9600 $20,373.92 $19,506.4600 $39,012.92 $24,000.0000 $48,000.00
0425 1325 INLETS, CURB, TYPE P-2, PARTIAL 1 EA $10,606.6600 $10,606.66 $4,940.0000 $4,940.00 $10,186.9600 $10,186.96 $21,673.8400 $21,673.84 $28,300.0000 $28,300.00
0425 1411 INLETS, CURB TYPE J-1, <10' 2 EA $30,040.0000 $60,080.00 $22,300.0000 $44,600.00 $28,851.3100 $57,702.62 $61,770.4400 $123,540.88 $69,600.0000 $139,200.00
0425 1421 INLETS, CURB, TYPE J-2, <10' 1 EA $20,552.8500 $20,552.85 $15,300.0000 $15,300.00 $19,739.5800 $19,739.58 $59,603.0600 $59,603.06 $44,500.0000 $44,500.00
0425 1441 INLETS, CURB, TYPE J-4, <10' 1 EA $30,039.9900 $30,039.99 $22,500.0000 $22,500.00 $28,851.3100 $28,851.31 $63,937.8300 $63,937.83 $72,275.0000 $72,275.00
0425 2 91 MANHOLES, J-8, <10' 1 EA $20,552.8500 $20,552.85 $15,300.0000 $15,300.00 $19,739.5800 $19,739.58 $45,515.0600 $45,515.06 $55,000.0000 $55,000.00
0430175118 PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 18"S/CD 17 LF $287.9400 $4,894.98 $304.0000 $5,168.00 $276.5400 $4,701.18 $2,709.2300 $46,056.91 $1,035.0000 $17,595.00
0430175124 PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 24"S/CD 8 LF $404.0900 $3,232.72 $417.0000 $3,336.00 $388.1000 $3,104.80 $7,044.0000 $56,352.00 $1,540.0000 $12,320.00
0430175142 PIPE CULVERT, OPT MATERIAL, ROUND, 42"S/CD 44 LF $891.5300 $39,227.32 $592.0000 $26,048.00 $856.2500 $37,675.00 $4,334.7700 $190,729.88 $1,120.0000 $49,280.00
0430175154 PIPE CULVERT, OPT MATERIAL, ROUND, 54"S/CD 16 LF $994.4600 $15,911.36 $1,000.0000 $16,000.00 $955.1100 $15,281.76 $7,585.8400 $121,373.44 $2,360.0000 $37,760.00
0430175160 PIPE CULVERT, OPT MATERIAL, ROUND, 60"S/CD 8 LF $1,080.1500 $8,641.20 $1,070.0000 $8,560.00 $1,037.4100 $8,299.28 $7,802.5800 $62,420.64 $3,035.0000 $24,280.00
0430185148 PIPE CULVERT,OPTIONAL MATERIAL,ROUND, JACK & BORE, 48", STORM AND CROSS DRAIN 108 LF $2,599.7300 $280,770.84 $1,860.0000 $200,880.00 $3,821.0000 $412,668.00 $11,703.8700 $1,264,017.96 $14,500.0000 $1,566,000.00
0430830 PIPE FILLING AND PLUGGING- PLACE OUT OF SERVICE 37.9 CY $507.8700 $19,248.27 $517.0000 $19,594.30 $487.7800 $18,486.86 $975.3200 $36,964.63 $1,080.0000 $40,932.00
0515 1 2 PIPE HANDRAIL - GUIDERAIL, ALUMINUM 105 LF $61.1100 $6,416.55 $57.1000 $5,995.50 $58.7000 $6,163.50 $59.6000 $6,258.00 $66.0000 $6,930.00
0520 1 10 CONCRETE CURB & GUTTER, TYPE F 494 LF $61.8400 $30,548.96 $31.2000 $15,412.80 $59.3900 $29,338.66 $61.1100 $30,188.34 $62.5000 $30,875.00
0520 5 41 TRAFFIC SEPARATOR CONCRETE- TYPE IV, 4' WIDE 46 LF $162.7100 $7,484.66 $44.6500 $2,053.90 $156.2700 $7,188.42 $109.5100 $5,037.46 $165.0000 $7,590.00
0520 70 CONCRETE TRAFFIC SEPARATOR, SPECIAL- VARIABLE WIDTH 1 SY $617.2600 $617.26 $366.0000 $366.00 $592.8300 $592.83 $2,226.9000 $2,226.90 $630.0000 $630.00
0522 1 CONCRETE SIDEWALK AND DRIVEWAYS, 4" THICK 513 SY $93.9200 $48,180.96 $84.1000 $43,143.30 $90.2000 $46,272.60 $125.2900 $64,273.77 $95.0000 $48,735.00
0522 2 CONCRETE SIDEWALK AND DRIVEWAYS, 6" THICK 293 SY $140.9100 $41,286.63 $117.0000 $34,281.00 $135.3300 $39,651.69 $140.7600 $41,242.68 $145.0000 $42,485.00
0524 1 1 CONCRETE DITCH PAVT, NON REINFORCED, 3" 27 SY $168.4400 $4,547.88 $306.0000 $8,262.00 $161.7800 $4,368.06 $175.2800 $4,732.56 $170.0000 $4,590.00
0524 2 2 CONCRETE SLOPE PAVEMENT,NON REINFORCED, 4" 113 SY $148.8700 $16,822.31 $258.0000 $29,154.00 $142.9800 $16,156.74 $122.4600 $13,837.98 $150.0000 $16,950.00
0527 2 DETECTABLE WARNINGS 59 SF $49.9100 $2,944.69 $55.0500 $3,247.95 $47.9400 $2,828.46 $22.7600 $1,342.84 $30.0000 $1,770.00
0536 1 1 GUARDRAIL -ROADWAY, GENERAL TL-3 454 LF $27.7800 $12,612.12 $25.9500 $11,781.30 $26.6800 $12,112.72 $27.0900 $12,298.86 $28.0000 $12,712.00
0536 1 3 GUARDRAIL- ROADWAY, DOUBLE FACE 141 LF $38.8900 $5,483.49 $36.3500 $5,125.35 $37.3500 $5,266.35 $37.9300 $5,348.13 $40.0000 $5,640.00
0536 6 PIPE RAIL FOR GUARDRAIL 200 LF $16.6700 $3,334.00 $15.6000 $3,120.00 $16.0100 $3,202.00 $16.2600 $3,252.00 $17.0000 $3,400.00
0536 73 GUARDRAIL REMOVAL 494 LF $2.2200 $1,096.68 $2.1000 $1,037.40 $2.1300 $1,052.22 $2.1700 $1,071.98 $2.3000 $1,136.20
0536 85 20 GUARDRAIL END TREATMENT- TRAILING ANCHORAGE 2 EA $2,222.3400 $4,444.68 $2,080.0000 $4,160.00 $2,134.4100 $4,268.82 $2,167.3800 $4,334.76 $2,265.0000 $4,530.00
0536 85 24 GUARDRAIL END TREATMENT- PARALLEL APPROACH TERMINAL 1 EA $3,889.1000 $3,889.10 $3,630.0000 $3,630.00 $3,735.2100 $3,735.21 $3,792.9200 $3,792.92 $3,960.0000 $3,960.00
0536 85 27 GUARDRAIL END TREATMENT- DOUBLE FACE APPROACH TERMINAL 1 EA $8,333.7800 $8,333.78 $7,790.0000 $7,790.00 $8,004.0200 $8,004.02 $8,127.6900 $8,127.69 $8,500.0000 $8,500.00
0538 1 GUARDRAIL RESET 200 LF $16.6700 $3,334.00 $15.6000 $3,120.00 $16.0100 $3,202.00 $16.2600 $3,252.00 $17.0000 $3,400.00
0570 1 2 PERFORMANCE TURF, SOD 3,468 SY $5.8200 $20,183.76 $3.6500 $12,658.20 $5.5900 $19,386.12 $10.2400 $35,512.32 $4.5000 $15,606.00
0630 2 11 CONDUIT, FURNISH & INSTALL, OPEN TRENCH 213 LF $43.5650 $9,009.22 $32.2750 $6,931.45 $41.8400 $8,652.42 $43.8100 $9,433.78 $45.7500 $9,851.00
0630 2 12 CONDUIT, FURNISH & INSTALL, DIRECTIONAL BORE 506 LF $65.7150 $34,245.71 $54.1500 $27,777.50 $63.1100 $32,888.54 $60.6350 $31,568.99 $62.7500 $32,743.50
0630 2 14 CONDUIT, FURNISH & INSTALL, ABOVEGROUND 80 LF $86.9700 $6,957.60 $58.5000 $4,680.00 $83.5300 $6,682.40 $47.0300 $3,762.40 $50.0000 $4,000.00
0632 7 1 SIGNAL CABLE- NEW OR RECONSTRUCTED INTERSECTION, FURNISH & INSTALL 2 PI $12,069.0600 $24,138.12 $13,000.0000 $26,000.00 $11,591.4800 $23,182.96 $11,920.6100 $23,841.22 $12,450.0000 $24,900.00
0632 7 6 SIGNAL CABLE, REMOVE- INTERSECTION 2 PI $2,424.3800 $4,848.76 $904.0000 $1,808.00 $2,328.4400 $4,656.88 $866.9500 $1,733.90 $900.0000 $1,800.00
0633 6 FIBER OPTIC CABLE LOCATOR 225 DA $207.8800 $46,773.00 $53.8500 $12,116.25 $199.6500 $44,921.25 $197.2300 $44,376.75 $210.0000 $47,250.00
0635 2 11 PULL & SPLICE BOX, F&I, 13" x 24" COVER SIZE 4 EA $1,545.6500 $6,182.60 $2,490.0000 $9,960.00 $1,484.4900 $5,937.96 $2,015.6700 $8,062.68 $2,100.0000 $8,400.00
0635 2 14 PULL & SPLICE BOX, F&I, 17" X 30" COVER SIZE 9 EA $1,710.4100 $15,393.69 $2,880.0000 $25,920.00 $1,642.7300 $14,784.57 $2,492.4900 $22,432.41 $2,600.0000 $23,400.00
0641 2 70 PRESTRESSED CONCRETE POLE, SHALLOW POLE REMOVAL- POLE 30' AND GREATER 1 EA $4,722.4800 $4,722.48 $8,510.0000 $8,510.00 $4,535.6100 $4,535.61 $9,509.4000 $9,509.40 $9,900.0000 $9,900.00
0650 2109 VEHICULAR SIGNAL AUXILIARIES, REPAIR/REPLACE/RETROFIT- FURNISH & INSTALL, BACKPLATE- FLEXIBLE REQUIRED 26 EA $875.8000 $22,770.80 $484.0000 $12,584.00 $841.1500 $21,869.90 $774.8400 $20,145.84 $810.0000 $21,060.00
0660 4 11 VEHICLE DETECTION SYSTEM- VIDEO, FURNISH & INSTALL CABINET EQUIPMENT 2 EA $34,256.0600 $68,512.12 $31,200.0000 $62,400.00 $32,900.5400 $65,801.08 $32,679.8200 $65,359.64 $34,000.0000 $68,000.00
0660 4 12 VEHICLE DETECTION SYSTEM- VIDEO, FURNISH & INSTALL ABOVE GROUND EQUIPMENT 4 EA $15,135.3200 $60,541.28 $8,380.0000 $33,520.00 $14,536.4100 $58,145.64 $7,897.9500 $31,591.80 $8,250.0000 $33,000.00
0660 4 51 VEHICLE DETECTION SYSTEM- VIDEO, ADJUST/MODIFY CABINET EQUIPMENT 1 EA $1,212.1800 $1,212.18 $904.0000 $904.00 $1,164.2200 $1,164.22 $654.5500 $654.55 $680.0000 $680.00
0671 2 40 TRAFFIC CONTROLLER, MODIFY 3 EA $1,624.1000 $4,872.30 $3,890.0000 $11,670.00 $1,559.8300 $4,679.49 $574.3600 $1,723.08 $600.0000 $1,800.00
0676 1500 TRAFFIC SIGNAL CONTROLLER CABINET, ADJUST/MODIFY 1 EA $2,275.3100 $2,275.31 $4,980.0000 $4,980.00 $2,185.2700 $2,185.27 $2,659.3800 $2,659.38 $2,780.0000 $2,780.00
0695 1 1 TRAFFIC MONITORING SITE VEHICLE SENSOR-NON-WEIGHT, FURNISH & INSTALL 12 EA $2,754.0900 $33,049.08 $2,370.0000 $28,440.00 $2,645.1100 $31,741.32 $3,578.3500 $42,940.20 $3,740.0000 $44,880.00
0695 6 12 TRAFFIC MONITORING SITE INDUCTIVE LOOP ASSEMBLY, FURNISH & INSTALL, 2 LOOPS 12 EA $2,985.7300 $35,828.76 $2,700.0000 $32,400.00 $2,867.5800 $34,410.96 $3,190.3900 $38,284.68 $3,335.0000 $40,020.00
0695 7162 TRAFFIC MONITORING SITE CABINET, F&I, TYPE 3, 2 PANE BACK, PEDESTAL MOUNT 2 EA $8,026.4200 $16,052.84 $7,870.0000 $15,740.00 $7,708.8200 $15,417.64 $7,954.3000 $15,908.60 $8,300.0000 $16,600.00
0695 7600 TRAFFIC MONITORING SITE CABINET, REMOVE EXISTING CABINET 2 EA $808.1200 $1,616.24 $904.0000 $1,808.00 $776.1400 $1,552.28 $1,725.2400 $3,450.48 $1,800.0000 $3,600.00
0700 1111 SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, LESS THAN 12 SF 118 EA $500.0300 $59,003.54 $467.0000 $55,106.00 $480.2400 $56,668.32 $487.6600 $57,543.88 $510.0000 $60,180.00
0700 1112 SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, 12.0- 20.0 SF 22 EA $1,888.9900 $41,557.78 $1,770.0000 $38,940.00 $1,814.2400 $39,913.28 $1,842.2800 $40,530.16 $1,925.0000 $42,350.00
0700 1113 SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I GROUND MOUNT, 20.1- 30.0 SF 3 EA $2,777.9300 $8,333.79 $2,600.0000 $7,800.00 $2,668.0100 $8,004.03 $2,709.2300 $8,127.69 $2,830.0000 $8,490.00
0700 13 15 RETROREFLECTIVE SIGN STRIP- FURNISH AND INSTALL, 5' 18 EA $111.1200 $2,000.16 $104.0000 $1,872.00 $106.7200 $1,920.96 $108.3700 $1,950.66 $115.0000 $2,070.00
0700 1600 SINGLE COLUMN GROUND SIGN ASSEMBLY, REMOVE 113 EA $27.7800 $3,139.14 $25.9500 $2,932.35 $26.6800 $3,014.84 $27.0900 $3,061.17 $28.0000 $3,164.00
0700 3101 SIGN PANEL, FURNISH & INSTALL GROUND MOUNT, UP TO 12 SF 9 EA $388.9100 $3,500.19 $363.0000 $3,267.00 $373.5200 $3,361.68 $379.2900 $3,413.61 $395.0000 $3,555.00
0700 3102 SIGN PANEL, FURNISH & INSTALL GROUND MOUNT, 12-20 SF 2 EA $666.7000 $1,333.40 $623.0000 $1,246.00 $640.3200 $1,280.64 $650.2200 $1,300.44 $680.0000 $1,360.00
0700 3103 SIGN PANEL, FURNISH & INSTALL GROUND MOUNT, 21-30 SF 3 EA $833.3800 $2,500.14 $779.0000 $2,337.00 $800.4000 $2,401.20 $812.7700 $2,438.31 $850.0000 $2,550.00
0700 3104 SIGN PANEL, FURNISH & INSTALL GROUND MOUNT, 31-50 SF 2 EA $1,722.3200 $3,444.64 $1,610.0000 $3,220.00 $1,654.1700 $3,308.34 $1,679.7200 $3,359.44 $1,755.0000 $3,510.00
0700 3106 SIGN PANEL, FURNISH & INSTALL GROUND MOUNT, 101-200 SF 1 EA $7,778.2000 $7,778.20 $7,270.0000 $7,270.00 $7,470.4100 $7,470.41 $7,585.8400 $7,585.84 $7,925.0000 $7,925.00
0700 3206 SIGN PANEL, FURNISH & INSTALL OVERHEAD MOUNT, 101-200 SF 1 EA $7,778.2000 $7,778.20 $7,270.0000 $7,270.00 $7,470.4100 $7,470.41 $7,585.8400 $7,585.84 $7,925.0000 $7,925.00
0700 3207 SIGN PANEL, FURNISH & INSTALL OVERHEAD MOUNT, 201-300 SF 2 EA $11,111.7200 $22,223.44 $10,400.0000 $20,800.00 $10,672.0200 $21,344.04 $10,836.9200 $21,673.84 $11,320.0000 $22,640.00
0700 3601 SIGN PANEL, REMOVE, UP TO 12 SF 9 EA $27.7800 $250.02 $25.9500 $233.55 $26.6800 $240.12 $27.0900 $243.81 $28.0000 $252.00
0700 3602 SIGN PANEL, REMOVE, 12-20 SF 2 EA $55.5600 $111.12 $51.9000 $103.80 $53.3600 $106.72 $54.1800 $108.36 $55.0000 $110.00
0700 3603 SIGN PANEL, REMOVE, 21-30 SF 3 EA $55.5600 $166.68 $51.9000 $155.70 $53.3600 $160.08 $54.1800 $162.54 $55.0000 $165.00
0700 3604 SIGN PANEL, REMOVE, 31-50 SF 2 EA $111.1200 $222.24 $104.0000 $208.00 $106.7200 $213.44 $108.3700 $216.74 $115.0000 $230.00
0700 3605 SIGN PANEL, REMOVE, 51-100 SF 2 EA $222.2400 $444.48 $208.0000 $416.00 $213.4400 $426.88 $216.7400 $433.48 $225.0000 $450.00
0700 3606 SIGN PANEL, REMOVE, 101-200 SF 2 EA $277.7900 $555.58 $260.0000 $520.00 $266.8000 $533.60 $270.9200 $541.84 $280.0000 $560.00
0700 3607 SIGN PANEL, REMOVE, 201-300 SF 2 EA $555.5900 $1,111.18 $519.0000 $1,038.00 $533.6000 $1,067.20 $541.8500 $1,083.70 $565.0000 $1,130.00
0704 1 3 TUBULAR MARKER, 36" WHITE POST 28 EA $166.6800 $4,667.04 $156.0000 $4,368.00 $160.0800 $4,482.24 $162.5500 $4,551.40 $170.0000 $4,760.00
0704 1 4 TUBULAR MARKER, 36" YELLOW POST 27 EA $166.6800 $4,500.36 $156.0000 $4,212.00 $160.0800 $4,322.16 $162.5500 $4,388.85 $170.0000 $4,590.00
0706 1 3 RAISED PAVEMENT MARKER, TYPE B 5,406 EA $4.0900 $22,110.54 $4.1500 $22,434.90 $3.9500 $21,353.70 $4.4100 $23,840.46 $5.0500 $27,300.30
0710 11101 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 6" 7.482 GM $1,878.9500 $14,058.30 $1,560.0000 $11,671.92 $1,813.7600 $13,570.55 $2,027.7600 $15,171.70 $1,360.0000 $10,175.52
0710 11102 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR INTERCHANGE AND URBAN ISLAND, 8" 0.744 GM $2,639.0700 $1,963.47 $1,650.0000 $1,227.60 $2,547.5100 $1,895.35 $2,862.7100 $2,129.86 $1,700.0000 $1,264.80
0710 11123 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR CROSSWALK AND ROUNDABOUT, 12" 5,050 LF $1.3300 $6,716.50 $0.8000 $4,040.00 $1.2800 $6,464.00 $1.4300 $7,221.50 $1.1500 $5,807.50
0710 11124 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR DIAGONAL OR CHEVRON, 18" 1,763 LF $1.4400 $2,538.72 $1.3000 $2,291.90 $1.3900 $2,450.57 $1.5500 $2,732.65 $2.3000 $4,054.90
0710 11125 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID FOR STOP LINE OR CROSSWALK, 24" 4,390 LF $1.5500 $6,804.50 $1.5500 $6,804.50 $1.4900 $6,541.10 $1.6700 $7,331.30 $2.3000 $10,097.00
0710 11131 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SKIP, 10-30 OR 3-9 SKIP, 6" WIDE 7.679 GM $552.1300 $4,239.81 $726.0000 $5,574.95 $532.9800 $4,092.75 $596.4000 $4,579.76 $565.0000 $4,338.64
0710 11133 PAINTED PAVEMENT MARKING, STANDARD,WHITE, 3'-9' SKIP DROP LINE AND APPROACH TO TOLL PLAZA, 12" WIDE, 0.157 GM $1,056.3100 $165.84 $1,190.0000 $186.83 $1,019.6200 $160.08 $1,192.8000 $187.27 $1,130.0000 $177.41
0710 11141 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, 2-4 DOTTED GUIDELINE/ 6-10 DOTTED EXTENSION, 6" 1.411 GM $718.1100 $1,013.25 $726.0000 $1,024.39 $693.1900 $978.09 $775.3200 $1,093.98 $680.0000 $959.48
0710 11160 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, MESSAGE OR SYMBOL 73 EA $38.6900 $2,824.37 $67.5000 $4,927.50 $37.3500 $2,726.55 $41.7500 $3,047.75 $55.0000 $4,015.00
0710 11170 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, ARROWS 201 EA $38.6900 $7,776.69 $31.1500 $6,261.15 $37.3500 $7,507.35 $41.7500 $8,391.75 $34.0000 $6,834.00
0710 11201 PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SOLID, 6" 5.241 GM $1,879.0900 $9,848.31 $1,560.0000 $8,175.96 $1,813.9000 $9,506.65 $2,027.7600 $10,627.49 $1,360.0000 $7,127.76
0710 11224 PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SOLID FOR DIAGONAL OR CHEVRON, 18" 63 LF $1.5500 $97.65 $1.3000 $81.90 $1.4900 $93.87 $1.6700 $105.21 $2.3000 $144.90
0710 11231 PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SKIP, 6" 0.353 GM $548.1000 $193.48 $721.0000 $254.51 $529.0700 $186.76 $596.4000 $210.53 $680.0000 $240.04
0710 11241 PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, 2-4 DOTTED GUIDELINE/6-10 DOTTED EXTENSION, 6" 0.387 GM $705.6100 $273.07 $714.0000 $276.32 $681.1400 $263.60 $775.3200 $300.05 $680.0000 $263.16
0710 12290 PAINTED PAVEMENT MARKINGS, DURABLE PAINT, YELLOW, ISLAND NOSE 148 SF $5.5300 $818.44 $5.2000 $769.60 $5.3400 $790.32 $5.9600 $882.08 $5.7000 $843.60
0710 90 PAINTED PAVEMENT MARKINGS, FINAL SURFACE 1 LS $65,393.8200 $65,393.82 $57,100.0000 $57,100.00 $63,125.0100 $63,125.01 $70,553.9700 $70,553.97 $60,000.0000 $60,000.00
0711 11123 THERMOPLASTIC, STANDARD, WHITE, SOLID, 12" FOR CROSSWALK AND ROUNDABOUT 5,050 LF $3.2200 $16,261.00 $3.6500 $18,432.50 $3.1100 $15,705.50 $3.4700 $17,523.50 $5.0000 $25,250.00
0711 11124 THERMOPLASTIC, STANDARD, WHITE, SOLID, 18" FOR DIAGONALS AND CHEVRONS 1,763 LF $4.7900 $8,444.77 $4.6500 $8,197.95 $4.6200 $8,145.06 $5.1600 $9,097.08 $6.2000 $10,930.60
0711 11125 THERMOPLASTIC, STANDARD, WHITE, SOLID, 24" FOR STOP LINE AND CROSSWALK 849 LF $6.4300 $5,459.07 $6.2500 $5,306.25 $6.2100 $5,272.29 $6.9400 $5,892.06 $7.3500 $6,240.15
0711 11141 THERMOPLASTIC, STANDARD, WHITE, 2-4 DOTTED GUIDELINE/ 6-10 GAP EXTENSION, 6" 1.411 GM $2,209.5500 $3,117.68 $3,110.0000 $4,388.21 $2,132.8900 $3,009.51 $2,385.5900 $3,366.07 $3,965.0000 $5,594.62
0711 11160 THERMOPLASTIC, STANDARD, WHITE, MESSAGE OR SYMBOL 15 EA $81.8100 $1,227.15 $234.0000 $3,510.00 $78.9700 $1,184.55 $88.2700 $1,324.05 $225.0000 $3,375.00
0711 11170 THERMOPLASTIC, STANDARD, WHITE, ARROW 143 EA $55.2800 $7,905.04 $77.9000 $11,139.70 $53.3600 $7,630.48 $59.6400 $8,528.52 $85.0000 $12,155.00
0711 11224 THERMOPLASTIC, STANDARD, YELLOW, SOLID, 18" FOR DIAGONAL OR CHEVRON 63 LF $4.4200 $278.46 $6.2500 $393.75 $4.2700 $269.01 $4.7700 $300.51 $6.8000 $428.40
0711 11241 THERMOPLASTIC, STANDARD, YELLOW, 2-4 DOTTED GUIDE LINE /6-10 DOTTED EXTENSION LINE, 6" 0.387 GM $2,171.1400 $840.23 $3,570.0000 $1,381.59 $2,095.7900 $811.07 $2,385.5900 $923.22 $3,965.0000 $1,534.46
0711 14125 THERMOPLASTIC, PREFORMED, WHITE, SOLID, 24" FOR CROSSWALK 3,541 LF $16.3100 $57,753.71 $15.6000 $55,239.60 $15.7400 $55,735.34 $17.5900 $62,286.19 $17.0000 $60,197.00
0711 14160 THERMOPLASTIC, PREFORMED, WHITE, MESSAGE 58 EA $204.5300 $11,862.74 $208.0000 $12,064.00 $197.4300 $11,450.94 $220.6700 $12,798.86 $255.0000 $14,790.00
0711 14170 THERMOPLASTIC, PREFORMED, WHITE, ARROW 58 EA $88.4400 $5,129.52 $83.0500 $4,816.90 $85.3800 $4,952.04 $95.4200 $5,534.36 $140.0000 $8,120.00
0711 16101 THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SOLID, 6" 7.482 GM $4,946.0500 $37,006.35 $5,400.0000 $40,402.80 $4,774.4500 $35,722.43 $5,337.7700 $39,937.20 $7,360.0000 $55,067.52
0711 16102 THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SOLID, 8" 0.744 GM $6,560.3000 $4,880.86 $5,990.0000 $4,456.56 $6,332.7000 $4,711.53 $7,116.2300 $5,294.48 $8,490.0000 $6,316.56
0711 16131 THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SKIP, 6",10-30 SKIP OR 3-9 LANE DROP 7.679 GM $1,236.7700 $9,497.16 $2,590.0000 $19,888.61 $1,193.8700 $9,167.73 $1,335.9300 $10,258.61 $2,265.0000 $17,392.94
0711 16133 THERMOPLASTIC, STANDARD-OTHER SURFACES WHITE, SKIP, 12"- APPROACH TO TOLL PLAZA OR 3-9 LANE DROP 0.157 GM $2,365.9900 $371.46 $4,960.0000 $778.72 $2,283.9500 $358.58 $2,671.8700 $419.48 $5,660.0000 $888.62
0711 16201 THERMOPLASTIC, STANDARD-OTHER SURFACES, YELLOW, SOLID, 6" 5.241 GM $4,642.4600 $24,331.13 $5,400.0000 $28,301.40 $4,481.3900 $23,486.96 $5,009.7500 $26,256.10 $7,360.0000 $38,573.76
0711 16231 THERMOPLASTIC, STANDARD-OTHER SURFACES, YELLOW, SKIP, 6" 0.353 GM $1,150.9600 $406.29 $3,090.0000 $1,090.77 $1,111.0500 $392.20 $1,252.4400 $442.11 $2,265.0000 $799.55
0713103101 PERMANENT TAPE, WHITE, SOLID, 6" FOR CONCRETE BRIDGES 0.085 GM $35,835.7600 $3,046.04 $31,300.0000 $2,660.50 $34,592.4700 $2,940.36 $41,079.9400 $3,491.79 $39,600.0000 $3,366.00
0713103181 PERMANENT TAPE, WHITE, 10-30 SKIP, 6" WIDE, FOR CONCRETE SURFACES 0.17 GM $9,518.8200 $1,618.20 $12,500.0000 $2,125.00 $9,188.5900 $1,562.06 $10,269.9900 $1,745.90 $13,580.0000 $2,308.60
0713103201 PERMANENT TAPE, YELLOW, SOLID, 6" FOR CONCRETE BRIDGES 0.085 GM $35,835.7600 $3,046.04 $31,300.0000 $2,660.50 $34,592.4700 $2,940.36 $41,079.9400 $3,491.79 $39,600.0000 $3,366.00
0713103381 PERMANENT TAPE, BLACK, 10-30 SKIP, 6" WIDE, FOR CONCRETE SURFACES 0.17 GM $9,518.8200 $1,618.20 $12,500.0000 $2,125.00 $9,188.5900 $1,562.06 $10,269.9900 $1,745.90 $13,585.0000 $2,309.45
0906173200 TWO COMPONENT POLYURETHANE INJECTION 14,250 LB $7.6100 $108,442.50 $8.8500 $126,112.50 $7.4200 $105,735.00 $7.1000 $101,175.00 $20.0000 $285,000.00
0999 25 INITIAL CONTINGENCY AMOUNT, DO NOT BID 1 LS $91,000.0000 $91,000.00 $91,000.0000 $91,000.00 $91,000.0000 $91,000.00 $91,000.0000 $91,000.00 $91,000.0000 $91,000.00
0999 26 LOCAL AGENCY INITIAL CONTINGENCY AMOUNT (DO NOT BID) 1 LS $1,335.0000 $1,335.00 $1,335.0000 $1,335.00 $1,335.0000 $1,335.00 $1,335.0000 $1,335.00 $1,335.0000 $1,335.00
1050 16002 UTILITY PIPE,REMOVE & DISPOSE, 2- 4.9" 56 LF $21.0000 $1,176.00 $56.4000 $3,158.40 $21.3400 $1,195.04 $54.1800 $3,034.08 $230.0000 $12,880.00
1050 31204 UTILITY PIPE- POLY VINYL CHLORIDE, FURNISH & INSTALL, WATER/SEWER, 4" 56 LF $59.5000 $3,332.00 $77.6000 $4,345.60 $149.4100 $8,366.96 $541.8500 $30,343.60 $340.0000 $19,040.00
1050 42204 UTILITY PIPE- HIGH DENSITY POLYETHYLENE, FURNISH & INSTALL, WATER/SEWER, 4" 84 LF $68.4100 $5,746.44 $76.9000 $6,459.60 $168.6200 $14,164.08 $433.4800 $36,412.32 $230.0000 $19,320.00
1080 29104 UTILITY FIXTURE, MECHANICAL JOINT RESTRAINT, FURNISH & INSTALL, 4" 2 EA $1,026.1000 $2,052.20 $699.0000 $1,398.00 $747.0400 $1,494.08 $1,625.5400 $3,251.08 $10,250.0000 $20,500.00