Georgia DOT · Bid Tabulation
Contract B1CBA2601731-1
BRIDGE REHABILITATION AT VARIOUS LOCATIONS IN CLAYTON COUNTY. (E)
- County
- Clayton
- Letting
- June 12, 2026
- Bidders
- 6
Apparent low bid
COMANCHE CONSTRUCTION OF GEORGIA, LLC
$2,035,515.70
Other bidders
MASSANA CONSTRUCTION, INC.
$2,268,609.00
THE L. C. WHITFORD CO., INC.
$2,483,887.00
WILSON CONSTRUCTION MANAGEMENT, LLC
$3,034,072.00
AMERICAN CONTRACTING & SERVICES, INC
$3,578,683.00
CEKRA, INC.
$4,235,526.53
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | COMANCHE CONSTRUCTION OF GEORGIA, LLC $2,035,515.70 | MASSANA CONSTRUCTION, INC. $2,268,609.00 | THE L. C. WHITFORD CO., INC. $2,483,887.00 | WILSON CONSTRUCTION MANAGEMENT, LLC $3,034,072.00 | AMERICAN CONTRACTING & SERVICES, INC $3,578,683.00 | CEKRA, INC. $4,235,526.53 | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 150-1000 | TRAFFIC CONTROL - M006738 | 1 | LS | $420,000.0000 | $420,000.00 | $264,987.0000 | $264,987.00 | $504,268.2000 | $504,268.20 | $702,115.0000 | $702,115.00 | $745,000.0000 | $745,000.00 | $536,799.3300 | $536,799.33 |
| 150-5010 | TRAFFIC CONTROL, PORTABLE IMPACT ATTENUATOR | 1 | EA | $8,500.0000 | $8,500.00 | $5,000.0000 | $5,000.00 | $8,000.0000 | $8,000.00 | $13,450.0000 | $13,450.00 | $40,000.0000 | $40,000.00 | $11,371.7200 | $11,371.72 |
| 210-0100 | GRADING COMPLETE - M006738 | 1 | LS | $170,000.0000 | $170,000.00 | $275,713.0000 | $275,713.00 | $250,000.0000 | $250,000.00 | $747,827.0000 | $747,827.00 | $250,000.0000 | $250,000.00 | $1,212,035.4700 | $1,212,035.47 |
| 310-1101 | GR AGGR BASE CRS, INCL MATL | 112 | TN | $148.0000 | $13,192.00 | $295.0000 | $13,770.00 | $275.0000 | $30,800.00 | $75.0000 | $8,400.00 | $525.0000 | $23,550.00 | $43.6600 | $4,889.92 |
| 402-3121 | RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM MATL & H LIME | 619 | TN | $187.0000 | $115,753.00 | $187.0000 | $115,753.00 | $200.0000 | $123,800.00 | $132.0000 | $81,708.00 | $250.0000 | $154,750.00 | $121.8000 | $75,394.20 |
| 402-3190 | RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2,INCL BITUM MATL & H LIME | 155 | TN | $194.0000 | $30,070.00 | $192.0000 | $29,760.00 | $200.0000 | $31,000.00 | $160.0000 | $24,800.00 | $250.0000 | $38,750.00 | $129.4300 | $20,061.65 |
| 402-4510 | RECYCLED ASPH CONC 12.5 MM SUPERPAVE, GP 2 ONLY, INCL POLYMER-MODIFIED BITUM MATL & H LIME | 117 | TN | $199.0000 | $23,283.00 | $348.0000 | $40,716.00 | $200.0000 | $23,400.00 | $185.0000 | $21,645.00 | $250.0000 | $29,250.00 | $121.2800 | $14,189.76 |
| 413-0750 | TACK COAT | 170 | GL | $6.0000 | $1,020.00 | $5.0000 | $850.00 | $10.0000 | $1,700.00 | $10.0000 | $1,700.00 | $15.0000 | $2,550.00 | $1.6500 | $280.50 |
| 441-0004 | CONC SLOPE PAV, 4 IN | 6 | SY | $750.0000 | $4,500.00 | $500.0000 | $3,000.00 | $500.0000 | $3,000.00 | $1,518.0000 | $9,108.00 | $2,300.0000 | $13,800.00 | $103.9700 | $623.82 |
| 446-1100 | PVMT REINF FABRIC STRIPS, TP 2, 18 INCH WIDTH | 1,059 | LF | $11.0000 | $11,649.00 | $11.0000 | $11,649.00 | $10.0000 | $10,590.00 | $5.0000 | $5,295.00 | $10.0000 | $10,590.00 | $7.9200 | $8,387.28 |
| 449-1350 | PREFORMED SILICONE JOINT SEAL, BR NO. - 3 - BT 3 | 472 | LF | $90.0000 | $42,480.00 | $85.0000 | $40,120.00 | $125.0000 | $59,000.00 | $100.0000 | $47,200.00 | $225.0000 | $106,200.00 | $72.6800 | $34,304.96 |
| 456-2040 | FREEWAY-SHOULDER RUMBLE STRIPS, GROUND IN PLACE (CONTINUOUS), 16 IN (400 MM) | 0.21 | GLM | $98,000.0000 | $20,580.00 | $60,000.0000 | $12,600.00 | $85,000.0000 | $17,850.00 | $20,000.0000 | $4,200.00 | $80,000.0000 | $16,800.00 | $50,000.0000 | $10,500.00 |
| 461-2000 | RESEALING BRIDGE JOINTS, TP - D | 779 | LF | $40.0000 | $31,160.00 | $35.0000 | $27,265.00 | $55.0000 | $42,845.00 | $50.0000 | $38,950.00 | $100.0000 | $77,900.00 | $38.1300 | $29,703.27 |
| 500-0100 | GROOVED CONCRETE | 811 | SY | $26.0000 | $21,086.00 | $29.0000 | $23,519.00 | $13.0000 | $10,543.00 | $15.0000 | $12,165.00 | $45.0000 | $36,495.00 | $14.0400 | $11,386.44 |
| 500-9999 | CLASS B CONC, BASE OR PVMT WIDENING | 4 | CY | $1,790.0000 | $7,160.00 | $4,200.0000 | $16,800.00 | $1,500.0000 | $6,000.00 | $1,250.0000 | $5,000.00 | $2,000.0000 | $8,000.00 | $414.1700 | $1,656.68 |
| 501-3000 | STR STEEL, BR NO - 2 | 1 | LS | $5,120.0000 | $5,120.00 | $100,000.0000 | $100,000.00 | $20,000.0000 | $20,000.00 | $5,628.0000 | $5,628.00 | $15,000.0000 | $15,000.00 | $3.5600 | $3.56 |
| 504-0600 | TWENTY-FOUR HOUR ACCELERATED STRENGTH CONC | 19 | CY | $4,410.0000 | $83,790.00 | $1,100.0000 | $20,900.00 | $4,000.0000 | $76,000.00 | $1,509.0000 | $28,671.00 | $12,500.0000 | $237,500.00 | $1,957.5300 | $37,193.07 |
| 511-3000 | SUPERSTR REINF STEEL, BR NO - 3 | 1 | LS | $15,800.0000 | $15,800.00 | $30,000.0000 | $30,000.00 | $38,000.0000 | $38,000.00 | $10,310.0000 | $10,310.00 | $35,000.0000 | $35,000.00 | $1.7100 | $1.71 |
| 518-1000 | RAISE EXISTING BRIDGE, STA - 66+57.83 | 1 | LS | $196,445.0000 | $196,445.00 | $225,000.0000 | $225,000.00 | $150,000.0000 | $150,000.00 | $244,515.0000 | $244,515.00 | $80,000.0000 | $80,000.00 | $236,533.3300 | $236,533.33 |
| 519-0225 | CONCRETE OVERLAY, LATEX MODIFIED, THICKNESS - 1 IN | 811 | SY | $413.0000 | $334,943.00 | $345.0000 | $279,795.00 | $450.0000 | $364,950.00 | $375.0000 | $304,125.00 | $900.0000 | $729,900.00 | $272.7600 | $221,208.36 |
| 519-0515 | SURFACE PREPARATION | 3,269 | SY | $11.0000 | $35,959.00 | $9.0000 | $29,421.00 | $7.0000 | $22,883.00 | $6.0000 | $19,614.00 | $30.0000 | $98,070.00 | $6.7800 | $22,163.82 |
| 519-0530 | POLYMER OVERLAY | 3,269 | SY | $39.0000 | $127,491.00 | $30.0000 | $98,070.00 | $35.0000 | $114,415.00 | $33.0000 | $107,877.00 | $70.0000 | $228,830.00 | $41.4700 | $135,565.43 |
| 521-3000 | PATCHING CONCRETE BRIDGE | 86 | SF | $500.0000 | $43,000.00 | $400.0000 | $34,400.00 | $300.0000 | $25,800.00 | $543.0000 | $46,698.00 | $1,100.0000 | $94,600.00 | $304.7400 | $26,207.64 |
| 528-0501 | EPOXY PRESSURE INJECTION OF CONCRETE CRACKS | 178 | LF | $142.0000 | $25,276.00 | $150.0000 | $26,700.00 | $175.0000 | $31,150.00 | $344.0000 | $61,232.00 | $300.0000 | $53,400.00 | $136.3200 | $24,264.96 |
| 535-1107 | PAINT EXIST STEEL SUPERSTRUCTURE, BR ID - 063-09096M-001.81E | 1 | LS | $49,000.0000 | $49,000.00 | $40,000.0000 | $40,000.00 | $110,000.0000 | $110,000.00 | $65,000.0000 | $65,000.00 | $40,000.0000 | $40,000.00 | $1,155,000.0000 | $1,155,000.00 |
| 535-1109 | PAINT EXIST STEEL SUBSTRUCTURE, BR ID - 063-00139D-003.80N | 1 | LS | $49,000.0000 | $49,000.00 | $175,000.0000 | $175,000.00 | $110,000.0000 | $110,000.00 | $200,000.0000 | $200,000.00 | $40,000.0000 | $40,000.00 | $140,000.0000 | $140,000.00 |
| 540-1202 | REMOVAL OF PARTS OF EXISTING BRIDGE, BR NO - 3 | 1 | LS | $39,700.0000 | $39,700.00 | $225,000.0000 | $225,000.00 | $165,000.0000 | $165,000.00 | $55,451.0000 | $55,451.00 | $125,000.0000 | $125,000.00 | $160,922.4000 | $160,922.40 |
| 590-1000 | FIBER REINFORCED POLYMER (CARBON) BR NO- 3 | 18 | SY | $1,330.0000 | $23,940.00 | $1,280.0000 | $23,040.00 | $500.0000 | $9,000.00 | $2,293.0000 | $41,274.00 | $1,200.0000 | $21,600.00 | $560.0000 | $10,080.00 |
| 600-0001 | FLOWABLE FILL | 14 | CY | $1,505.0000 | $21,070.00 | $1,350.0000 | $18,900.00 | $2,000.0000 | $28,000.00 | $1,506.0000 | $21,084.00 | $3,500.0000 | $49,000.00 | $549.8100 | $7,697.34 |
| 620-0100 | TEMPORARY BARRIER, METHOD NO. 1 | 747 | LF | $33.0000 | $24,651.00 | $65.0000 | $48,555.00 | $75.0000 | $56,025.00 | $74.0000 | $55,278.00 | $100.0000 | $74,700.00 | $45.6900 | $34,130.43 |
| 632-0003 | CHANGEABLE MESSAGE SIGN, PORTABLE, TYPE 3 | 4 | EA | $6,800.0000 | $27,200.00 | $100.0000 | $400.00 | $7,500.0000 | $30,000.00 | $8,000.0000 | $32,000.00 | $20,000.0000 | $80,000.00 | $11,630.0400 | $46,520.16 |
| 653-1906 | THERMOPLASTIC SOLID TRAF STRIPE, 6 IN, WHITE | 583 | LF | $1.1000 | $641.30 | $1.0000 | $583.00 | $2.1000 | $1,224.30 | $1.0000 | $583.00 | $3.0000 | $1,749.00 | $0.9900 | $577.17 |
| 653-2602 | THERMOPLASTIC SOLID TRAF STRIPE, 6 IN, YELLOW | 583 | LF | $1.1000 | $641.30 | $1.0000 | $583.00 | $2.1000 | $1,224.30 | $1.0000 | $583.00 | $3.0000 | $1,749.00 | $0.9900 | $577.17 |
| 653-2611 | THERMOPLASTIC SKIP TRAF STRIPE, 6 IN, WHITE | 1,166 | GLF | $1.1000 | $1,282.60 | $1.0000 | $1,166.00 | $1.6000 | $1,865.60 | $1.0000 | $1,166.00 | $10.0000 | $11,660.00 | $0.8000 | $932.80 |
| 654-1003 | RAISED PVMT MARKERS TP 3 | 33 | EA | $6.5000 | $214.50 | $6.0000 | $198.00 | $8.0000 | $264.00 | $6.0000 | $198.00 | $10.0000 | $330.00 | $4.6400 | $153.12 |
| 657-9243 | WET REFLECTIVE PREFORMED SOLID PAVEMENT MARKINGS, 9 IN, CONTRAST (BLACK-YELLOW) | 174 | LF | $19.0000 | $3,306.00 | $18.0000 | $3,132.00 | $11.0000 | $1,914.00 | $18.0000 | $3,132.00 | $15.0000 | $2,610.00 | $9.0800 | $1,579.92 |
| 657-9245 | WET REFLECTIVE PREFORMED SOLID PAVEMENT MARKINGS, 9 IN, CONTRAST (BLACK-WHITE) | 174 | LF | $19.0000 | $3,306.00 | $18.0000 | $3,132.00 | $11.0000 | $1,914.00 | $18.0000 | $3,132.00 | $15.0000 | $2,610.00 | $9.0500 | $1,574.70 |
| 657-9316 | WET REFLECTIVE PREFORMED SKIP PAVEMENT MARKINGS, 6 INCH WIDE, WHITE | 174 | GLF | $9.5000 | $1,653.00 | $9.0000 | $1,566.00 | $4.2000 | $730.80 | $8.5000 | $1,479.00 | $5.0000 | $870.00 | $3.0300 | $527.22 |
| 657-9320 | WET REFLECTIVE PREFORMED SKIP PAVEMENT MARKINGS, 6 INCH WIDE, BLACK | 174 | GLF | $9.5000 | $1,653.00 | $9.0000 | $1,566.00 | $4.2000 | $730.80 | $8.5000 | $1,479.00 | $5.0000 | $870.00 | $3.0300 | $527.22 |
Source: public Georgia DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.