Georgia DOT · Bid Tabulation
Contract B1CBA2602094-0
0.160 MILE OF CONSTRUCTION OF A BRIDGE AND APPROACHES ON GRACE CHAPEL RD (CR 95) OVER SPANISH CREEK. (E)
- County
- Charlton
- Letting
- June 12, 2026
- Bidders
- 3
Apparent low bid
UNDERGROUND EXCAVATING, INC.
$2,089,459.60
Other bidders
SOUTHEASTERN SITE DEVELOPME N A
$2,208,476.54
SOUTHERN CONCRETE CONSTRUC N A
$2,220,280.36
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | UNDERGROUND EXCAVATING, INC. $2,089,459.60 | SOUTHEASTERN SITE DEVELOPME N A $2,208,476.54 | SOUTHERN CONCRETE CONSTRUC N A $2,220,280.36 | |||
|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 150-1000 | TRAFFIC CONTROL - 0016568 | 1 | LS | $20,000.0000 | $20,000.00 | $26,191.9000 | $26,191.90 | $22,273.3300 | $22,273.33 |
| 163-0232 | TEMPORARY GRASSING | 2 | AC | $500.0000 | $1,000.00 | $995.0000 | $1,990.00 | $10.0000 | $20.00 |
| 163-0240 | MULCH | 22 | TN | $50.0000 | $1,100.00 | $795.0000 | $17,490.00 | $5.0000 | $110.00 |
| 163-0301 | CONSTRUCT AND REMOVE CONSTRUCTION EXITS | 2 | EA | $500.0000 | $1,000.00 | $4,270.4800 | $8,540.96 | $500.0000 | $1,000.00 |
| 163-0520 | CONSTRUCT AND REMOVE TEMPORARY PIPE SLOPE DRAIN | 125 | LF | $10.0000 | $1,250.00 | $26.7700 | $3,346.25 | $1.0000 | $125.00 |
| 163-0528 | CONSTRUCT AND REMOVE FABRIC CHECK DAM - TYPE C SILT FENCE | 80 | LF | $18.0000 | $1,440.00 | $9.5000 | $760.00 | $1.0000 | $80.00 |
| 163-0550 | CONSTRUCT AND REMOVE INLET SEDIMENT TRAP | 2 | EA | $450.0000 | $900.00 | $310.0000 | $620.00 | $10.0000 | $20.00 |
| 165-0030 | MAINTENANCE OF TEMPORARY SILT FENCE, TP C | 1,600 | LF | $1.0000 | $1,600.00 | $5.4500 | $8,720.00 | $0.0100 | $16.00 |
| 165-0041 | MAINTENANCE OF CHECK DAMS - ALL TYPES | 80 | LF | $1.0000 | $80.00 | $2.0500 | $164.00 | $0.0100 | $0.80 |
| 165-0101 | MAINTENANCE OF CONSTRUCTION EXIT | 1 | EA | $1.0000 | $1.00 | $1,395.2500 | $1,395.25 | $50.0000 | $50.00 |
| 165-0105 | MAINTENANCE OF INLET SEDIMENT TRAP | 2 | EA | $1.0000 | $2.00 | $150.0000 | $300.00 | $5.0000 | $10.00 |
| 165-0310 | MAINTENANCE OF CONSTRUCTION EXIT TIRE WASH AREA (PER EACH) | 1 | EA | $1.0000 | $1.00 | $3,805.5900 | $3,805.59 | $50.0000 | $50.00 |
| 167-1000 | WATER QUALITY MONITORING AND SAMPLING | 2 | EA | $250.0000 | $500.00 | $1,059.3300 | $2,118.66 | $500.0000 | $1,000.00 |
| 167-1500 | WATER QUALITY INSPECTIONS | 12 | MO | $500.0000 | $6,000.00 | $289.3600 | $3,472.32 | $1,500.0000 | $18,000.00 |
| 171-0030 | TEMPORARY SILT FENCE, TYPE C | 3,200 | LF | $4.5000 | $14,400.00 | $4.4500 | $14,240.00 | $4.8300 | $15,456.00 |
| 207-0203 | FOUND BKFILL MATL, TP II | 500 | CY | $120.0000 | $60,000.00 | $40.0000 | $20,000.00 | $165.0000 | $82,500.00 |
| 210-0100 | GRADING COMPLETE - 0016568 | 1 | LS | $205,000.0000 | $205,000.00 | $353,360.0000 | $353,360.00 | $120,000.0000 | $120,000.00 |
| 210-0250 | UNDERCUT EXCAVATION | 500 | CY | $20.0000 | $10,000.00 | $35.0000 | $17,500.00 | $22.0000 | $11,000.00 |
| 310-5080 | GR AGGR BASE CRS, 8 INCH, INCL MATL | 1,700 | SY | $33.0000 | $56,100.00 | $74.4200 | $126,514.00 | $35.0000 | $59,500.00 |
| 402-1812 | RECYCLED ASPH CONC LEVELING, INCL BITUM MATL & H LIME | 70 | TN | $200.0000 | $14,000.00 | $170.0000 | $11,900.00 | $160.3200 | $11,222.40 |
| 402-3102 | RECYCLED ASPH CONC 9.5 MM SUPERPAVE, TYPE II, BLEND 1, INCL BITUM MATL & H LIME | 180 | TN | $200.0000 | $36,000.00 | $163.0000 | $29,340.00 | $166.9700 | $30,054.60 |
| 402-3121 | RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM MATL & H LIME | 300 | TN | $180.0000 | $54,000.00 | $152.0000 | $45,600.00 | $147.4800 | $44,244.00 |
| 402-3190 | RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2,INCL BITUM MATL & H LIME | 300 | TN | $180.0000 | $54,000.00 | $152.0000 | $45,600.00 | $148.8400 | $44,652.00 |
| 413-0750 | TACK COAT | 275 | GL | $8.0000 | $2,200.00 | $6.0000 | $1,650.00 | $3.9500 | $1,086.25 |
| 433-1200 | REINF CONC APPROACH SLAB, INCL SLOPED EDGE | 213.9 | SY | $275.0000 | $58,822.50 | $278.0000 | $59,464.20 | $254.8400 | $54,510.28 |
| 441-0050 | CONC SLOPE DRAIN | 17 | SY | $280.0000 | $4,760.00 | $127.0000 | $2,159.00 | $263.6200 | $4,481.54 |
| 441-0303 | CONC SPILLWAY, TP 3 | 2 | EA | $3,000.0000 | $6,000.00 | $2,600.0000 | $5,200.00 | $3,075.6200 | $6,151.24 |
| 455-1000 | FILTER FABRIC FOR EMBANKMENT STABILIZATION | 500 | SY | $6.0000 | $3,000.00 | $3.5100 | $1,755.00 | $4.6300 | $2,315.00 |
| 500-2100 | CONCRETE BARRIER | 392 | LF | $168.0000 | $65,856.00 | $153.0000 | $59,976.00 | $112.9500 | $44,276.40 |
| 500-3101 | CLASS A CONCRETE | 45 | CY | $2,000.0000 | $90,000.00 | $2,025.0000 | $91,125.00 | $2,200.0000 | $99,000.00 |
| 507-0027 | PSC BOX BEAMS, 27 IN, BR NO - 1 | 2,156 | LF | $350.0000 | $754,600.00 | $306.3700 | $660,533.72 | $450.0000 | $970,200.00 |
| 511-1000 | BAR REINF STEEL | 6,984 | LB | $1.9000 | $13,269.60 | $2.1000 | $14,666.40 | $2.0000 | $13,968.00 |
| 511-3000 | SUPERSTR REINF STEEL, BR NO - 1 | 1 | LS | $14,788.0000 | $14,788.00 | $8,386.2000 | $8,386.20 | $20,000.0000 | $20,000.00 |
| 520-2214 | PILING, PSC, 14 IN SQ | 1,185 | LF | $125.0000 | $148,125.00 | $103.0000 | $122,055.00 | $115.0000 | $136,275.00 |
| 520-3214 | TEST PILE, PSC, 14 IN SQ | 2 | EA | $12,500.0000 | $25,000.00 | $14,551.9900 | $29,103.98 | $10,500.0000 | $21,000.00 |
| 520-4214 | LOAD TEST, PSC, 14 IN SQ | 1 | EA | $1.0000 | $1.00 | $1.0000 | $1.00 | $0.0100 | $0.01 |
| 523-1100 | DYNAMIC PILE TEST | 2 | EA | $7,500.0000 | $15,000.00 | $2,600.0000 | $5,200.00 | $15,500.0000 | $31,000.00 |
| 533-0010 | BRIDGE DECK WATERPROOFING MEMBRANE, METHOD A | 665 | SY | $40.0000 | $26,600.00 | $31.3400 | $20,841.10 | $50.0000 | $33,250.00 |
| 540-1101 | REMOVAL OF EXISTING BR, STA NO - 1 | 1 | LS | $200,000.0000 | $200,000.00 | $249,033.9400 | $249,033.94 | $190,000.0000 | $190,000.00 |
| 603-2018 | STN DUMPED RIP RAP, TP 1, 18 IN | 438 | SY | $150.0000 | $65,700.00 | $178.4100 | $78,143.58 | $150.0000 | $65,700.00 |
| 603-7000 | PLASTIC FILTER FABRIC | 438 | SY | $6.0000 | $2,628.00 | $6.2600 | $2,741.88 | $6.0000 | $2,628.00 |
| 634-1200 | RIGHT OF WAY MARKERS | 10 | EA | $330.0000 | $3,300.00 | $360.3800 | $3,603.80 | $263.6200 | $2,636.20 |
| 636-1033 | HIGHWAY SIGNS, TP 1 MATL, REFL SHEETING, TP 9 | 6 | SF | $42.0000 | $252.00 | $38.0000 | $228.00 | $33.3900 | $200.34 |
| 636-1036 | HIGHWAY SIGNS, TP 1 MATL, REFL SHEETING, TP 11 | 18 | SF | $44.0000 | $792.00 | $40.0000 | $720.00 | $35.1500 | $632.70 |
| 636-2070 | GALV STEEL POSTS, TP 7 | 26 | LF | $24.0000 | $624.00 | $22.0000 | $572.00 | $19.3300 | $502.58 |
| 636-2090 | GALV STEEL POSTS, TP 9 | 30 | LF | $27.0000 | $810.00 | $24.0000 | $720.00 | $21.0900 | $632.70 |
| 636-5020 | DELINEATOR, TP 2 | 12 | EA | $150.0000 | $1,800.00 | $125.0000 | $1,500.00 | $109.8400 | $1,318.08 |
| 641-1100 | GUARDRAIL, TP T | 82.6 | LF | $95.0000 | $7,847.00 | $119.4300 | $9,864.92 | $83.4800 | $6,895.45 |
| 641-1200 | GUARDRAIL, TP W | 457 | LF | $29.0000 | $13,253.00 | $30.6100 | $13,988.77 | $25.4800 | $11,644.36 |
| 641-5001 | GUARDRAIL ANCHORAGE, TP 1 | 2 | EA | $2,250.0000 | $4,500.00 | $1,771.6500 | $3,543.30 | $1,977.1800 | $3,954.36 |
| 641-5015 | GUARDRAIL TERMINAL, TP 12A, 31 IN, TANGENT, ENERGY-ABSORBING | 2 | EA | $3,750.0000 | $7,500.00 | $3,519.3600 | $7,038.72 | $3,295.3000 | $6,590.60 |
| 643-8200 | BARRIER FENCE (ORANGE), 4 FT | 755 | LF | $2.0000 | $1,510.00 | $3.7700 | $2,846.35 | $2.2000 | $1,661.00 |
| 653-1906 | THERMOPLASTIC SOLID TRAF STRIPE, 6 IN, WHITE | 1,650 | LF | $1.0000 | $1,650.00 | $0.7500 | $1,237.50 | $0.6600 | $1,089.00 |
| 653-2602 | THERMOPLASTIC SOLID TRAF STRIPE, 6 IN, YELLOW | 1,650 | LF | $1.0000 | $1,650.00 | $0.7500 | $1,237.50 | $0.6600 | $1,089.00 |
| 654-1001 | RAISED PVMT MARKERS TP 1 | 40 | EA | $8.2500 | $330.00 | $7.5000 | $300.00 | $6.5900 | $263.60 |
| 700-6910 | PERMANENT GRASSING | 1 | AC | $2,000.0000 | $2,000.00 | $1,795.0000 | $1,795.00 | $23,743.9600 | $23,743.96 |
| 700-7000 | AGRICULTURAL LIME | 2 | TN | $110.0000 | $220.00 | $595.0000 | $1,190.00 | $0.0100 | $0.02 |
| 700-8000 | FERTILIZER MIXED GRADE | 1 | TN | $1,650.0000 | $1,650.00 | $1,195.0000 | $1,195.00 | $0.0100 | $0.01 |
| 700-8100 | FERTILIZER NITROGEN CONTENT | 55 | LB | $4.5000 | $247.50 | $1.6500 | $90.75 | $0.0100 | $0.55 |
| 713-0400 | COCONUT FIBER BLANKET, SLOPES | 800 | SY | $6.0000 | $4,800.00 | $2.2500 | $1,800.00 | $0.2500 | $200.00 |
Source: public Georgia DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.