GA
Georgia DOT · Bid Tabulation
Contract B1CBA2602108-0
0.218 MILE OF CONSTRUCTION OF A BRIDGE AND APPROACHES ON SATILLA RD (CR 181) OVER WILLACOOCHEE RIVER OVERFLOW. (E)
- County
- Irwin
- Letting
- June 12, 2026
- Bidders
- 1
Apparent low bid
SOUTHERN CONCRETE CONSTRUC N A
$1,869,513.21
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | SOUTHERN CONCRETE CONSTRUC N A $1,869,513.21 | |
|---|---|---|---|---|---|
| Unit Price | Extension | ||||
| 150-1000 | TRAFFIC CONTROL - 0016588 | 1 | LS | $35,000.0000 | $35,000.00 |
| 163-0232 | TEMPORARY GRASSING | 1 | AC | $100.0000 | $100.00 |
| 163-0240 | MULCH | 29 | TN | $25.0000 | $725.00 |
| 163-0301 | CONSTRUCT AND REMOVE CONSTRUCTION EXITS | 2 | EA | $500.0000 | $1,000.00 |
| 163-0501 | CONSTRUCT AND REMOVE SILT CONTROL GATE, TP 1 | 3 | EA | $50.0000 | $150.00 |
| 163-0520 | CONSTRUCT AND REMOVE TEMPORARY PIPE SLOPE DRAIN | 133 | LF | $1.0000 | $133.00 |
| 163-0528 | CONSTRUCT AND REMOVE FABRIC CHECK DAM - TYPE C SILT FENCE | 40 | LF | $0.1000 | $4.00 |
| 163-0550 | CONSTRUCT AND REMOVE INLET SEDIMENT TRAP | 4 | EA | $1.0000 | $4.00 |
| 165-0030 | MAINTENANCE OF TEMPORARY SILT FENCE, TP C | 1,700 | LF | $0.0100 | $17.00 |
| 165-0041 | MAINTENANCE OF CHECK DAMS - ALL TYPES | 20 | LF | $0.0100 | $0.20 |
| 165-0101 | MAINTENANCE OF CONSTRUCTION EXIT | 1 | EA | $50.0000 | $50.00 |
| 165-0105 | MAINTENANCE OF INLET SEDIMENT TRAP | 4 | EA | $1.0000 | $4.00 |
| 165-0310 | MAINTENANCE OF CONSTRUCTION EXIT TIRE WASH AREA (PER EACH) | 1 | EA | $50.0000 | $50.00 |
| 167-1000 | WATER QUALITY MONITORING AND SAMPLING | 2 | EA | $500.0000 | $1,000.00 |
| 167-1500 | WATER QUALITY INSPECTIONS | 12 | MO | $1,500.0000 | $18,000.00 |
| 171-0030 | TEMPORARY SILT FENCE, TYPE C | 3,400 | LF | $3.6700 | $12,478.00 |
| 210-0100 | GRADING COMPLETE - 0016588 | 1 | LS | $150,000.0000 | $150,000.00 |
| 310-5060 | GR AGGR BASE CRS, 6 INCH, INCL MATL | 168 | SY | $35.8500 | $6,022.80 |
| 310-5080 | GR AGGR BASE CRS, 8 INCH, INCL MATL | 1,375 | SY | $35.8500 | $49,293.75 |
| 318-3000 | AGGR SURF CRS | 45 | TN | $51.7300 | $2,327.85 |
| 402-1812 | RECYCLED ASPH CONC LEVELING, INCL BITUM MATL & H LIME | 65 | TN | $161.7900 | $10,516.35 |
| 402-3102 | RECYCLED ASPH CONC 9.5 MM SUPERPAVE, TYPE II, BLEND 1, INCL BITUM MATL & H LIME | 157 | TN | $156.0100 | $24,493.57 |
| 402-3121 | RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM MATL & H LIME | 230 | TN | $111.8800 | $25,732.40 |
| 402-3190 | RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2,INCL BITUM MATL & H LIME | 236 | TN | $114.6100 | $27,047.96 |
| 413-0750 | TACK COAT | 201 | GL | $3.4700 | $697.47 |
| 433-1200 | REINF CONC APPROACH SLAB, INCL SLOPED EDGE | 213.88 | SY | $290.0600 | $62,038.03 |
| 441-0301 | CONC SPILLWAY, TP 1 | 4 | EA | $3,034.5000 | $12,138.00 |
| 456-2082 | SINUSOIDAL EDGELINE RUMBLE STRIPS - GROUND IN PLACE CONTINUOUS, 6 IN (150 MM) | 1 | GLM | $18,073.1200 | $18,073.12 |
| 500-2100 | CONCRETE BARRIER | 207 | LF | $200.0000 | $41,400.00 |
| 500-3101 | CLASS A CONCRETE | 45.68 | CY | $1,588.1700 | $112,959.91 |
| 507-1021 | PSC CORED SLAB BEAMS, 21 IN, BR NO - 1 | 1,133 | LF | $475.0000 | $538,175.00 |
| 511-1000 | BAR REINF STEEL | 6,878 | LB | $2.0000 | $13,756.00 |
| 511-3000 | SUPERSTR REINF STEEL, BR NO - 1 | 1 | LS | $10,000.0000 | $10,000.00 |
| 520-2216 | PILING, PSC, 16 IN SQ | 1,190 | LF | $135.0000 | $160,650.00 |
| 520-3216 | TEST PILE, PSC, 16 IN SQ | 2 | EA | $10,000.0000 | $20,000.00 |
| 520-4216 | LOAD TEST, PSC, 16 IN SQ | 1 | EA | $0.0100 | $0.01 |
| 520-5000 | PILOT HOLES | 527 | LF | $275.0000 | $144,925.00 |
| 523-1100 | DYNAMIC PILE TEST | 2 | EA | $16,000.0000 | $32,000.00 |
| 533-0010 | BRIDGE DECK WATERPROOFING MEMBRANE, METHOD A | 359 | SY | $54.0000 | $19,386.00 |
| 540-1101 | REMOVAL OF EXISTING BR, STA NO - 14+17 | 1 | LS | $150,000.0000 | $150,000.00 |
| 550-2180 | SIDE DRAIN PIPE, 18 IN, H 1-10 | 27 | LF | $73.9200 | $1,995.84 |
| 550-4118 | FLARED END SECTION 18 IN, SIDE DRAIN | 2 | EA | $693.5000 | $1,387.00 |
| 576-1015 | SLOPE DRAIN PIPE, 15 IN | 70 | LF | $52.8800 | $3,701.60 |
| 603-2024 | STN DUMPED RIP RAP, TP 1, 24 IN | 641 | SY | $125.0000 | $80,125.00 |
| 603-2181 | STN DUMPED RIP RAP, TP 3, 18 IN | 25 | SY | $132.4100 | $3,310.25 |
| 603-7000 | PLASTIC FILTER FABRIC | 666 | SY | $5.4150 | $3,966.75 |
| 634-1200 | RIGHT OF WAY MARKERS | 10 | EA | $267.7500 | $2,677.50 |
| 636-1033 | HIGHWAY SIGNS, TP 1 MATL, REFL SHEETING, TP 9 | 33 | SF | $32.1300 | $1,060.29 |
| 636-1036 | HIGHWAY SIGNS, TP 1 MATL, REFL SHEETING, TP 11 | 12 | SF | $32.1300 | $385.56 |
| 636-2070 | GALV STEEL POSTS, TP 7 | 92 | LF | $16.0600 | $1,477.52 |
| 636-2090 | GALV STEEL POSTS, TP 9 | 31 | LF | $17.8500 | $553.35 |
| 636-5030 | DELINEATOR, TP 3 | 8 | EA | $133.8700 | $1,070.96 |
| 641-1100 | GUARDRAIL, TP T | 84 | LF | $75.8600 | $6,372.24 |
| 641-1200 | GUARDRAIL, TP W | 638 | LF | $23.2000 | $14,801.60 |
| 641-5001 | GUARDRAIL ANCHORAGE, TP 1 | 2 | EA | $1,740.3700 | $3,480.74 |
| 641-5015 | GUARDRAIL TERMINAL, TP 12A, 31 IN, TANGENT, ENERGY-ABSORBING | 2 | EA | $3,123.7500 | $6,247.50 |
| 643-8200 | BARRIER FENCE (ORANGE), 4 FT | 2,290 | LF | $2.3700 | $5,427.30 |
| 653-1906 | THERMOPLASTIC SOLID TRAF STRIPE, 6 IN, WHITE | 1,270 | LF | $2.0100 | $2,552.70 |
| 653-3602 | THERMOPLASTIC SKIP TRAF STRIPE, 6 IN, YELLOW | 635 | GLF | $1.5600 | $990.60 |
| 654-1001 | RAISED PVMT MARKERS TP 1 | 16 | EA | $6.6900 | $107.04 |
| 700-6910 | PERMANENT GRASSING | 1 | AC | $25,672.9200 | $25,672.92 |
| 700-7000 | AGRICULTURAL LIME | 2 | TN | $0.0100 | $0.02 |
| 700-8000 | FERTILIZER MIXED GRADE | 1 | TN | $0.0100 | $0.01 |
| 700-8100 | FERTILIZER NITROGEN CONTENT | 50 | LB | $0.0100 | $0.50 |
| 716-2000 | EROSION CONTROL MATS, SLOPES | 900 | SY | $2.0000 | $1,800.00 |
Source: public Georgia DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →