IL
Illinois DOT · Bid Tabulation
Contract 62Y30
(60B&C-NRM)BDR,BJR 25
- County
- COOK
- District
- 1
- Letting
- April 24, 2026
- Section
- (60B&C-NRM)BDR,BJR 25
- Bidders
- 4
Apparent low bid
MARTAM CONSTRUCTION INCORPORATED
$786,723.00
Other bidders
MYS, INCORPORATED
$798,954.04
LORIG CONSTRUCTION COMPANY
$869,366.55
AREATHA CONSTRUCTION CO., INC.
$892,382.71
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | MARTAM CONSTRUCTION INCORPORATED $786,723.00 | MYS, INCORPORATED $798,954.04 | LORIG CONSTRUCTION COMPANY $869,366.55 | AREATHA CONSTRUCTION CO., INC. $892,382.71 | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 20200100 | EARTH EXCAVATION | 5 | CU YD | $220.0000 | $1,100.00 | $212.5300 | $1,062.65 | $110.0000 | $550.00 | $137.9500 | $689.75 |
| 21101505 | TOPSOIL EXC & PLAC | 6 | CU YD | $180.0000 | $1,080.00 | $388.3600 | $2,330.16 | $225.0000 | $1,350.00 | $140.6500 | $843.90 |
| 25200110 | SODDING SALT TOLERANT | 18 | SQ YD | $145.0000 | $2,610.00 | $16.3400 | $294.12 | $300.0000 | $5,400.00 | $270.0000 | $4,860.00 |
| 28000510 | INLET FILTERS | 11 | EACH | $250.0000 | $2,750.00 | $332.8800 | $3,661.68 | $350.0000 | $3,850.00 | $300.0000 | $3,300.00 |
| 35101600 | AGG BASE CSE B 4 | 144 | SQ YD | $15.0000 | $2,160.00 | $13.7500 | $1,980.00 | $41.0000 | $5,904.00 | $36.1500 | $5,205.60 |
| 40600290 | BIT MATLS TACK CT | 151 | POUND | $1.0000 | $151.00 | $0.0600 | $9.06 | $4.0000 | $604.00 | $4.0000 | $604.00 |
| 40600370 | LONG JOINT SEALANT | 300 | FOOT | $58.0000 | $17,400.00 | $59.4700 | $17,841.00 | $45.0000 | $13,500.00 | $44.0000 | $13,200.00 |
| 40600982 | HMA SURF REM BUTT JT | 67 | SQ YD | $34.0000 | $2,278.00 | $35.4300 | $2,373.81 | $41.0000 | $2,747.00 | $2.9500 | $197.65 |
| 40604172 | P HMA SC IL-9.5 E N70 | 76 | TON | $600.0000 | $45,600.00 | $607.7900 | $46,192.04 | $600.0000 | $45,600.00 | $550.0000 | $41,800.00 |
| 42001300 | PROTECTIVE COAT | 192 | SQ YD | $1.0000 | $192.00 | $2.2200 | $426.24 | $4.0000 | $768.00 | $2.8000 | $537.60 |
| 42400200 | PC CONC SIDEWALK 5 | 1,084 | SQ FT | $18.0000 | $19,512.00 | $13.0100 | $14,102.84 | $17.0000 | $18,428.00 | $22.6500 | $24,552.60 |
| 44000500 | COMB CURB GUTTER REM | 96 | FOOT | $15.0000 | $1,440.00 | $24.4700 | $2,349.12 | $32.0000 | $3,072.00 | $27.4000 | $2,630.40 |
| 44000600 | SIDEWALK REM | 535 | SQ FT | $3.0000 | $1,605.00 | $6.1100 | $3,268.85 | $6.0000 | $3,210.00 | $6.1000 | $3,263.50 |
| 50102400 | CONC REM | 10.1 | CU YD | $2,300.0000 | $23,230.00 | $2,407.9000 | $24,319.79 | $3,500.0000 | $35,350.00 | $3,179.4000 | $32,111.94 |
| 50157300 | PROTECTIVE SHIELD | 312 | SQ YD | $40.0000 | $12,480.00 | $65.8900 | $20,557.68 | $20.0000 | $6,240.00 | $126.5500 | $39,483.60 |
| 50300255 | CONC SUP-STR | 10.1 | CU YD | $3,500.0000 | $35,350.00 | $3,293.8100 | $33,267.48 | $3,500.0000 | $35,350.00 | $4,892.1500 | $49,410.72 |
| 50300300 | PROTECTIVE COAT | 1,308 | SQ YD | $1.0000 | $1,308.00 | $2.4900 | $3,256.92 | $2.0000 | $2,616.00 | $2.8000 | $3,662.40 |
| 50800205 | REINF BARS, EPOXY CTD | 1,440 | POUND | $5.0000 | $7,200.00 | $6.8200 | $9,820.80 | $5.0000 | $7,200.00 | $7.2500 | $10,440.00 |
| 50800515 | BAR SPLICERS | 24 | EACH | $65.0000 | $1,560.00 | $70.5200 | $1,692.48 | $70.0000 | $1,680.00 | $56.2500 | $1,350.00 |
| 52000110 | PREF JT STRIP SEAL | 152 | FOOT | $315.0000 | $47,880.00 | $269.6600 | $40,988.32 | $294.0000 | $44,688.00 | $560.7500 | $85,234.00 |
| 59000200 | EPOXY CRACK INJECTION | 1 | FOOT | $980.0000 | $980.00 | $177.5400 | $177.54 | $400.0000 | $400.00 | $603.3500 | $603.35 |
| 60603800 | COMB CC&G TB6.12 | 215 | FOOT | $56.0000 | $12,040.00 | $48.5700 | $10,442.55 | $94.0000 | $20,210.00 | $83.9000 | $18,038.50 |
| 66900200 | NON SPL WASTE DISPOSL | 5 | CU YD | $310.0000 | $1,550.00 | $150.6700 | $753.35 | $100.0000 | $500.00 | $268.6000 | $1,343.00 |
| 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,200.0000 | $1,200.00 | $2,219.2300 | $2,219.23 | $1,650.0000 | $1,650.00 | $1,760.0000 | $1,760.00 |
| 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $4,400.0000 | $4,400.00 | $2,330.1900 | $2,330.19 | $2,800.0000 | $2,800.00 | $3,400.0000 | $3,400.00 |
| 66901003 | REG SUB F CON REPORT | 1 | L SUM | $600.0000 | $600.00 | $2,108.2700 | $2,108.27 | $1,000.0000 | $1,000.00 | $500.0000 | $500.00 |
| 66901006 | REG SUB MON | 2 | CAL DA | $800.0000 | $1,600.00 | $1,331.5300 | $2,663.06 | $1,250.0000 | $2,500.00 | $715.0000 | $1,430.00 |
| 67100100 | MOBILIZATION | 1 | L SUM | $46,000.0000 | $46,000.00 | $33,284.1100 | $33,284.11 | $50,000.0000 | $50,000.00 | $53,500.0000 | $53,500.00 |
| 70107025 | CHANGEABLE MESSAGE SN | 204 | CAL DA | $12.0000 | $2,448.00 | $32.1800 | $6,564.72 | $10.0000 | $2,040.00 | $10.0000 | $2,040.00 |
| 70300150 | SHRT TRM PAVT MK REM | 1,132 | SQ FT | $0.7000 | $792.40 | $1.1100 | $1,256.52 | $0.7000 | $792.40 | $0.6500 | $735.80 |
| 70307100 | TMP PVT MK L&S T4 TAP | 33 | SQ FT | $20.0000 | $660.00 | $4.9900 | $164.67 | $20.0000 | $660.00 | $18.0000 | $594.00 |
| 70307120 | TMP PVT MK L4 T4 TAPE | 3,315 | FOOT | $1.5000 | $4,972.50 | $1.5000 | $4,972.50 | $1.4000 | $4,641.00 | $1.3500 | $4,475.25 |
| 70307130 | TMP PVT MK L6 T4 TAPE | 10 | FOOT | $1.8000 | $18.00 | $2.2200 | $22.20 | $1.7500 | $17.50 | $1.6000 | $16.00 |
| 70400100 | TEMP CONC BARRIER | 410 | FOOT | $35.0000 | $14,350.00 | $46.5900 | $19,101.90 | $50.0000 | $20,500.00 | $50.0000 | $20,500.00 |
| 70400200 | REL TEMP CONC BARRIER | 410 | FOOT | $12.0000 | $4,920.00 | $12.8300 | $5,260.30 | $15.0000 | $6,150.00 | $14.0000 | $5,740.00 |
| 70600255 | IMP ATTN TEMP FRN TL2 | 2 | EACH | $4,800.0000 | $9,600.00 | $4,792.4200 | $9,584.84 | $4,500.0000 | $9,000.00 | $4,319.0000 | $8,638.00 |
| 70600322 | IMP ATTN REL FRN TL2 | 2 | EACH | $2,300.0000 | $4,600.00 | $2,292.4600 | $4,584.92 | $2,200.0000 | $4,400.00 | $2,066.0000 | $4,132.00 |
| 78000100 | THPL PVT MK LTR & SYM | 33 | SQ FT | $12.0000 | $396.00 | $11.1000 | $366.30 | $10.0000 | $330.00 | $10.0000 | $330.00 |
| 78000200 | THPL PVT MK LINE 4 | 5,381 | FOOT | $0.9000 | $4,842.90 | $0.9400 | $5,058.14 | $0.8500 | $4,573.85 | $0.8500 | $4,573.85 |
| 78000400 | THPL PVT MK LINE 6 | 45 | FOOT | $5.0000 | $225.00 | $4.4400 | $199.80 | $4.0000 | $180.00 | $4.0000 | $180.00 |
| 78000600 | THPL PVT MK LINE 12 | 325 | FOOT | $6.0000 | $1,950.00 | $5.5500 | $1,803.75 | $5.0000 | $1,625.00 | $5.0000 | $1,625.00 |
| 78004620 | PREF PL PM TD STD L4 | 568 | FOOT | $6.0000 | $3,408.00 | $6.1000 | $3,464.80 | $5.5000 | $3,124.00 | $5.5000 | $3,124.00 |
| 78004635 | PREF PL PM TD STD L 7 | 36 | FOOT | $12.0000 | $432.00 | $11.1000 | $399.60 | $10.0000 | $360.00 | $10.0000 | $360.00 |
| 78004660 | PREF PL PM TD STD L12 | 42 | FOOT | $18.0000 | $756.00 | $16.6400 | $698.88 | $15.0000 | $630.00 | $15.0000 | $630.00 |
| 78009012 | MOD URETH PM LINE 12 | 42 | FOOT | $33.0000 | $1,386.00 | $33.2900 | $1,398.18 | $30.0000 | $1,260.00 | $30.0000 | $1,260.00 |
| 78011025 | GRV RCSD PVT MRKG 5 | 568 | FOOT | $4.4000 | $2,499.20 | $4.4400 | $2,521.92 | $4.0000 | $2,272.00 | $4.0000 | $2,272.00 |
| 78011040 | GRV RCSD PVT MRKG 8 | 36 | FOOT | $15.0000 | $540.00 | $13.3100 | $479.16 | $12.0000 | $432.00 | $12.0000 | $432.00 |
| 78011065 | GRV RCSD PVT MRKG 13 | 42 | FOOT | $25.0000 | $1,050.00 | $22.1900 | $931.98 | $20.0000 | $840.00 | $20.0000 | $840.00 |
| 78300202 | PVT MKG REM WTR BLAST | 2,288 | SQ FT | $2.0000 | $4,576.00 | $4.9900 | $11,417.12 | $1.8500 | $4,232.80 | $1.8500 | $4,232.80 |
| X0300062 ★ | GRAFFITI REMOVAL | 271 | SQ YD | $92.0000 | $24,932.00 | $80.8400 | $21,907.64 | $108.0000 | $29,268.00 | $83.9000 | $22,736.90 |
| X0325839 ★ | SIGNAL TIMING | 1 | L SUM | $6,000.0000 | $6,000.00 | $5,548.0600 | $5,548.06 | $3,900.0000 | $3,900.00 | $3,900.0000 | $3,900.00 |
| X0326766 ★ | CLEAN RESEAL RLF JNT | 312 | FOOT | $26.0000 | $8,112.00 | $105.4100 | $32,887.92 | $52.0000 | $16,224.00 | $1.0000 | $312.00 |
| X0326806 ★ | WASHOUT BASIN | 1 | L SUM | $1,500.0000 | $1,500.00 | $2,161.6300 | $2,161.63 | $250.0000 | $250.00 | $1,123.8500 | $1,123.85 |
| X4400100 ★ | PCC SURF REM VAR DP | 47 | SQ YD | $48.0000 | $2,256.00 | $25.4300 | $1,195.21 | $50.0000 | $2,350.00 | $13.9500 | $655.65 |
| X4401198 ★ | HMA SURF REM VAR DP | 373 | SQ YD | $36.0000 | $13,428.00 | $38.4100 | $14,326.93 | $40.0000 | $14,920.00 | $2.9500 | $1,100.35 |
| X5030250 ★ | BR DECK GROOVING LONG | 976 | SQ YD | $11.0000 | $10,736.00 | $8.1900 | $7,993.44 | $12.0000 | $11,712.00 | $9.8000 | $9,564.80 |
| X6700410 ★ | ENGR FLD OFF A SPL | 6 | CAL MO | $4,200.0000 | $25,200.00 | $3,585.0000 | $21,510.00 | $4,000.0000 | $24,000.00 | $2,500.0000 | $15,000.00 |
| X7010216 ★ | TRAF CONT & PROT SPL | 1 | L SUM | $96,000.0000 | $96,000.00 | $18,259.3200 | $18,259.32 | $85,000.0000 | $85,000.00 | $29,250.0000 | $29,250.00 |
| X7200061 ★ | TEMP INFO SIGNING | 250 | SQ FT | $17.0000 | $4,250.00 | $16.6400 | $4,160.00 | $17.0000 | $4,250.00 | $16.0000 | $4,000.00 |
| Z0001700 ★ | APPR SLAB REPAIR (FD) | 9 | SQ YD | $3,500.0000 | $31,500.00 | $1,528.8600 | $13,759.74 | $1,600.0000 | $14,400.00 | $1,735.9000 | $15,623.10 |
| Z0001800 ★ | APPR SLAB REPAIR (PD) | 1 | SQ YD | $3,200.0000 | $3,200.00 | $2,066.5800 | $2,066.58 | $1,500.0000 | $1,500.00 | $1,859.9000 | $1,859.90 |
| Z0006014 | BR DK LTX C OLY 2 1/2 | 1,008 | SQ YD | $118.0000 | $118,944.00 | $176.8600 | $178,274.88 | $158.0000 | $159,264.00 | $175.4000 | $176,803.20 |
| Z0012130 | BR DECK SCAR 3/4 | 1,008 | SQ YD | $48.0000 | $48,384.00 | $75.9400 | $76,547.52 | $76.0000 | $76,608.00 | $105.8000 | $106,646.40 |
| Z0012754 | STR REP CON DP = < 5 | 20 | SQ FT | $300.0000 | $6,000.00 | $703.0000 | $14,060.00 | $750.0000 | $15,000.00 | $641.7000 | $12,834.00 |
| Z0012800 ★ | CONC PAVT SCAR | 285 | SQ YD | $39.0000 | $11,115.00 | $8.2700 | $2,356.95 | $33.0000 | $9,405.00 | $13.9500 | $3,975.75 |
| Z0015550 ★ | DEBRIS REMOVAL | 20 | CU YD | $220.0000 | $4,400.00 | $224.8100 | $4,496.20 | $250.0000 | $5,000.00 | $100.0000 | $2,000.00 |
| Z0029090 ★ | DIAMOND GRIND BR SEC | 1,008 | SQ YD | $11.0000 | $11,088.00 | $13.3100 | $13,416.48 | $11.0000 | $11,088.00 | $14.2000 | $14,313.60 |
Source: public Illinois DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →