Illinois DOT · Bid Tabulation
Contract 64T42
177(-4HB(-1,-2,-3,-4)(2VB)BRR
- County
- STEPHENSON
- District
- 2
- Letting
- April 24, 2026
- Section
- 177(-4HB(-1,-2,-3,-4)(2VB)BRR
- Bidders
- 2
Apparent low bid
MARTIN & COMPANY EXCAVATING
$4,082,943.00
Other bidders
CIVIL CONSTRUCTORS, INC. D/B/A/ HELM CIVIL
$4,367,658.23
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | MARTIN & COMPANY EXCAVATING $4,082,943.00 | CIVIL CONSTRUCTORS, INC. D/B/A/ HELM CIVIL $4,367,658.23 | ||
|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | ||||
| 20200600 | EXC & GR EX SHOULDER | 9.2 | UNIT | $950.0000 | $8,740.00 | $1,050.0000 | $9,660.00 |
| 28100203 | STONE RIPRAP CL A2 | 40 | TON | $65.0000 | $2,600.00 | $160.0000 | $6,400.00 |
| 31102000 | SUB GRAN MAT C | 137 | CU YD | $40.0000 | $5,480.00 | $56.0000 | $7,672.00 |
| 40600985 | PCC SURF REM BUTT JT | 1,250 | SQ YD | $10.0000 | $12,500.00 | $25.0000 | $31,250.00 |
| 40603085 | HMA BC IL-19.0 N70 | 55 | TON | $200.0000 | $11,000.00 | $308.0000 | $16,940.00 |
| 40604060 | HMA SC IL-9.5 D N50 | 134 | TON | $200.0000 | $26,800.00 | $166.0000 | $22,244.00 |
| 40604062 | HMA SC IL-9.5 D N70 | 56 | TON | $200.0000 | $11,200.00 | $260.0000 | $14,560.00 |
| 40800031 | P BIT MATLS TACK CT | 1,510 | POUND | $0.1000 | $151.00 | $1.0000 | $1,510.00 |
| 42000080 | PVT CON PCC BR APP SL | 194 | SQ YD | $275.0000 | $53,350.00 | $358.0000 | $69,452.00 |
| 42001300 | PROTECTIVE COAT | 990 | SQ YD | $1.0000 | $990.00 | $2.4000 | $2,376.00 |
| 44000100 | PAVEMENT REM | 1,218 | SQ YD | $12.0000 | $14,616.00 | $9.0000 | $10,962.00 |
| 44000155 | HMA SURF REM 1 1/2 | 919 | SQ YD | $12.0000 | $11,028.00 | $14.0000 | $12,866.00 |
| 44000500 | COMB CURB GUTTER REM | 1,205 | FOOT | $10.0000 | $12,050.00 | $9.0000 | $10,845.00 |
| 44003100 | MEDIAN REMOVAL | 5,337 | SQ FT | $7.0000 | $37,359.00 | $1.2000 | $6,404.40 |
| 44004250 | PAVED SHLD REMOVAL | 178 | SQ YD | $18.0000 | $3,204.00 | $21.0000 | $3,738.00 |
| 48101500 | AGGREGATE SHLDS B 6 | 476 | SQ YD | $15.0000 | $7,140.00 | $20.5000 | $9,758.00 |
| 50102400 | CONC REM | 75.6 | CU YD | $2,000.0000 | $151,200.00 | $3,998.0000 | $302,248.80 |
| 50157300 | PROTECTIVE SHIELD | 2,651 | SQ YD | $80.0000 | $212,080.00 | $68.0000 | $180,268.00 |
| 50200100 | STRUCTURE EXCAVATION | 42 | CU YD | $50.0000 | $2,100.00 | $81.0000 | $3,402.00 |
| 50300225 | CONC STRUCT | 29 | CU YD | $2,000.0000 | $58,000.00 | $875.0000 | $25,375.00 |
| 50300255 | CONC SUP-STR | 97.4 | CU YD | $2,000.0000 | $194,800.00 | $2,200.0000 | $214,280.00 |
| 50300300 | PROTECTIVE COAT | 5,072 | SQ YD | $1.0000 | $5,072.00 | $2.0000 | $10,144.00 |
| 50301350 | CONC SUPSTR APP SLAB | 137.4 | CU YD | $660.0000 | $90,684.00 | $790.0000 | $108,546.00 |
| 50500405 | F & E STRUCT STEEL | 460 | POUND | $54.0000 | $24,840.00 | $9.5000 | $4,370.00 |
| 50800205 | REINF BARS, EPOXY CTD | 66,690 | POUND | $2.2200 | $148,051.80 | $2.7500 | $183,397.50 |
| 50800515 | BAR SPLICERS | 404 | EACH | $50.0000 | $20,200.00 | $58.0000 | $23,432.00 |
| 52000110 | PREF JT STRIP SEAL | 434 | FOOT | $300.0000 | $130,200.00 | $293.0000 | $127,162.00 |
| 52100010 | ELAST BEARING ASSY T1 | 8 | EACH | $2,200.0000 | $17,600.00 | $3,000.0000 | $24,000.00 |
| 52100020 | ELAST BEARING ASSY T2 | 7 | EACH | $6,000.0000 | $42,000.00 | $3,200.0000 | $22,400.00 |
| 52100520 | ANCHOR BOLTS 1 | 44 | EACH | $180.0000 | $7,920.00 | $170.0000 | $7,480.00 |
| 53016001 ★ | DECK SLAB REP (FD-T1) | 16 | SQ YD | $1,000.0000 | $16,000.00 | $2,375.0000 | $38,000.00 |
| 53016002 ★ | DECK SLAB REP (FD-T2) | 22 | SQ YD | $1,000.0000 | $22,000.00 | $1,730.0000 | $38,060.00 |
| 53101002 ★ | BR DECK SCAR 3/4 | 5,121 | SQ YD | $53.5000 | $273,973.50 | $98.0000 | $501,858.00 |
| 53101409 ★ | BR DK LTX C OLY 2 1/2 | 5,121 | SQ YD | $138.0000 | $706,698.00 | $170.0000 | $870,570.00 |
| 53212754 ★ | STR REP CON DP = < 5 | 767 | SQ FT | $225.0000 | $172,575.00 | $205.0000 | $157,235.00 |
| 53212755 ★ | STR REP CON DP OVER 5 | 29 | SQ FT | $250.0000 | $7,250.00 | $280.0000 | $8,120.00 |
| 54210182 | PIPE ELBOW 12 | 3 | EACH | $750.0000 | $2,250.00 | $195.4200 | $586.26 |
| 54213447 | END SECTIONS 12 | 3 | EACH | $750.0000 | $2,250.00 | $1,050.0000 | $3,150.00 |
| 58600101 | GRANULAR BACKFILL STR | 28 | CU YD | $50.0000 | $1,400.00 | $120.0000 | $3,360.00 |
| 58700300 | CONCRETE SEALER | 462 | SQ FT | $4.0000 | $1,848.00 | $3.4000 | $1,570.80 |
| 59000200 | EPOXY CRACK INJECTION | 110 | FOOT | $85.0000 | $9,350.00 | $72.0000 | $7,920.00 |
| 59300100 | CONTR LOW-STRENG MATL | 24 | CU YD | $400.0000 | $9,600.00 | $210.0000 | $5,040.00 |
| 60100945 | PIPE DRAINS 12 | 198 | FOOT | $110.0000 | $21,780.00 | $88.0000 | $17,424.00 |
| 60300105 | FR & GRATES ADJUST | 14 | EACH | $2,800.0000 | $39,200.00 | $800.0000 | $11,200.00 |
| 60500060 | REMOV INLETS | 5 | EACH | $750.0000 | $3,750.00 | $780.0000 | $3,900.00 |
| 60600605 | CONC CURB TB | 39 | FOOT | $100.0000 | $3,900.00 | $75.0000 | $2,925.00 |
| 60603500 | COMB CC&G TB6.06 | 806 | FOOT | $65.0000 | $52,390.00 | $40.0000 | $32,240.00 |
| 60618300 | CONC MEDIAN SURF 4 | 4,625 | SQ FT | $12.0000 | $55,500.00 | $5.7000 | $26,362.50 |
| 60619200 | CONC MED TSB6.06 | 1,138 | SQ FT | $25.0000 | $28,450.00 | $22.0000 | $25,036.00 |
| 61000050 | CONC THRUST BLOCKS | 3 | EACH | $750.0000 | $2,250.00 | $960.0000 | $2,880.00 |
| 61000225 | TY F INLET BOX 610001 | 5 | EACH | $7,500.0000 | $37,500.00 | $6,000.0000 | $30,000.00 |
| 63100045 | TRAF BAR TERM T2 | 1 | EACH | $2,200.0000 | $2,200.00 | $1,788.0000 | $1,788.00 |
| 63100070 | TRAF BAR TERM T5 | 2 | EACH | $2,000.0000 | $4,000.00 | $1,598.0000 | $3,196.00 |
| 63100085 | TRAF BAR TERM T6 | 4 | EACH | $6,800.0000 | $27,200.00 | $5,994.0000 | $23,976.00 |
| 63200310 | GUARDRAIL REMOV | 262.5 | FOOT | $10.0000 | $2,625.00 | $9.8600 | $2,588.25 |
| 63301210 | REM RE-E SPBGR TY A | 1,726 | FOOT | $20.0000 | $34,520.00 | $17.7700 | $30,671.02 |
| 67000500 | ENGR FIELD OFFICE B | 4 | CAL MO | $3,800.0000 | $15,200.00 | $4,500.0000 | $18,000.00 |
| 67100100 | MOBILIZATION | 1 | L SUM | $231,000.0000 | $231,000.00 | $262,059.4900 | $262,059.49 |
| 70100200 | TRAF CONT-PROT 701331 | 2 | EACH | $8,700.0000 | $17,400.00 | $7,250.0000 | $14,500.00 |
| 70100205 | TRAF CONT-PROT 701401 | 4 | EACH | $1.0000 | $4.00 | $0.0100 | $0.04 |
| 70100207 | TRAF CONT-PROT 701402 | 4 | EACH | $11,100.0000 | $44,400.00 | $7,500.0000 | $30,000.00 |
| 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $36,000.0000 | $36,000.00 | $27,000.0000 | $27,000.00 |
| 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $1,100.0000 | $1,100.00 | $1,000.0000 | $1,000.00 |
| 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1,100.0000 | $1,100.00 | $1,000.0000 | $1,000.00 |
| 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $1,100.0000 | $1,100.00 | $1,000.0000 | $1,000.00 |
| 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $30,000.0000 | $30,000.00 | $35,000.0000 | $35,000.00 |
| 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $1,100.0000 | $1,100.00 | $1,000.0000 | $1,000.00 |
| 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $600.0000 | $6,000.00 | $500.0000 | $5,000.00 |
| 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $12,000.0000 | $12,000.00 | $10,000.0000 | $10,000.00 |
| 70106700 | TEMP RUMBLE STRIPS | 12 | EACH | $1.0000 | $12.00 | $0.0100 | $0.12 |
| 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $60.0000 | $2,520.00 | $50.0000 | $2,100.00 |
| 70300150 | SHRT TRM PAVT MK REM | 9,844 | SQ FT | $0.5000 | $4,922.00 | $0.3000 | $2,953.20 |
| 70307120 | TMP PVT MK L4 T4 TAPE | 25,627 | FOOT | $1.5000 | $38,440.50 | $1.2500 | $32,033.75 |
| 70307210 | TMP PVT MK L24 T4 TAP | 44 | FOOT | $10.0000 | $440.00 | $7.5000 | $330.00 |
| 70400100 | TEMP CONC BARRIER | 2,525 | FOOT | $30.0000 | $75,750.00 | $45.0000 | $113,625.00 |
| 70400125 | PIN TEMP CONC BARRIER | 216 | EACH | $30.0000 | $6,480.00 | $39.0000 | $8,424.00 |
| 70400200 | REL TEMP CONC BARRIER | 2,525 | FOOT | $10.0000 | $25,250.00 | $8.0000 | $20,200.00 |
| 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $2,700.0000 | $5,400.00 | $2,250.0000 | $4,500.00 |
| 70600251 | IMP ATTN TEMP NRN TL3 | 4 | EACH | $2,700.0000 | $10,800.00 | $2,250.0000 | $9,000.00 |
| 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $600.0000 | $1,200.00 | $400.0000 | $800.00 |
| 70600352 | IMP ATTN REL NRN TL3 | 4 | EACH | $600.0000 | $2,400.00 | $400.0000 | $1,600.00 |
| 78004630 | PREF PL PM TD STD L 6 | 770 | FOOT | $12.0000 | $9,240.00 | $10.0000 | $7,700.00 |
| 78004645 | PREF PL PM TD STD L 9 | 820 | FOOT | $18.0000 | $14,760.00 | $15.0000 | $12,300.00 |
| 78009000 | MOD URETH PM LTR-SYM | 47 | SQ FT | $8.0000 | $376.00 | $6.6000 | $310.20 |
| 78009004 | MOD URETH PM LINE 4 | 6,427 | FOOT | $1.4000 | $8,997.80 | $1.1000 | $7,069.70 |
| 78009006 | MOD URETH PM LINE 6 | 12,811 | FOOT | $2.0000 | $25,622.00 | $1.6500 | $21,138.15 |
| 78009008 | MOD URETH PM LINE 8 | 806 | FOOT | $2.6000 | $2,095.60 | $2.2000 | $1,773.20 |
| 78011025 | GRV RCSD PVT MRKG 5 | 6,427 | FOOT | $1.4000 | $8,997.80 | $1.1000 | $7,069.70 |
| 78011035 | GRV RCSD PVT MRKG 7 | 13,581 | FOOT | $2.0000 | $27,162.00 | $1.6500 | $22,408.65 |
| 78011045 | GRV RCSD PVT MRKG 9 | 806 | FOOT | $2.5000 | $2,015.00 | $2.1000 | $1,692.60 |
| 78011050 | GRV RCSD PVT MRKG 10 | 820 | FOOT | $2.6000 | $2,132.00 | $2.2000 | $1,804.00 |
| 78100100 | RAISED REFL PAVT MKR | 7 | EACH | $300.0000 | $2,100.00 | $250.0000 | $1,750.00 |
| 78200006 | GRDRAIL REF TYPE B | 72 | EACH | $12.0000 | $864.00 | $10.0000 | $720.00 |
| 78300202 | PVT MKG REM WTR BLAST | 2,027 | SQ FT | $2.0000 | $4,054.00 | $1.5000 | $3,040.50 |
| X0325748 ★ | ACRYLIC COATING | 20 | SQ YD | $200.0000 | $4,000.00 | $160.0000 | $3,200.00 |
| X0325749 ★ | FIBER WRAP | 211 | SQ FT | $150.0000 | $31,650.00 | $95.0000 | $20,045.00 |
| X2600022 ★ | REM ST RE SNPLASSY SP | 5 | EACH | $1,000.0000 | $5,000.00 | $900.0000 | $4,500.00 |
| X4201510 ★ | PCC BR APPR SH PVT SP | 102 | SQ YD | $215.0000 | $21,930.00 | $165.0000 | $16,830.00 |
| X5030250 ★ | BR DECK GROOVING LONG | 3,318 | SQ YD | $20.0000 | $66,360.00 | $12.0000 | $39,816.00 |
| X5030539 ★ | FLOOR DRAINS CLEANED | 28 | EACH | $250.0000 | $7,000.00 | $120.0000 | $3,360.00 |
| X5060700 ★ | CLEAN/PAINT BEARINGS | 7 | EACH | $6,500.0000 | $45,500.00 | $6,075.0000 | $42,525.00 |
| X5060704 ★ | CLN & PT EXP RE-BAR | 22 | SQ FT | $1,000.0000 | $22,000.00 | $119.0000 | $2,618.00 |
| X5230154 ★ | CLN BRDG SCUPS/DNSPTS | 12 | EACH | $500.0000 | $6,000.00 | $120.0000 | $1,440.00 |
| X6010003 ★ | PIPE DRAIN REMOVAL | 198 | FOOT | $30.0000 | $5,940.00 | $26.0000 | $5,148.00 |
| X7010216 ★ | TRAF CONT & PROT SPL | 1 | L SUM | $8,100.0000 | $8,100.00 | $6,750.0000 | $6,750.00 |
| X7820007 ★ | GRDRAIL REFL TY C SPL | 6 | EACH | $30.0000 | $180.00 | $23.4000 | $140.40 |
| X7820008 ★ | BARRIER WALL REFL SPL | 56 | EACH | $30.0000 | $1,680.00 | $25.0000 | $1,400.00 |
| Z0001495 ★ | BR APPROACH SHLD REM | 94 | SQ YD | $50.0000 | $4,700.00 | $99.0000 | $9,306.00 |
| Z0001899 ★ | JACK & REM EX BEARING | 15 | EACH | $3,100.0000 | $46,500.00 | $2,700.0000 | $40,500.00 |
| Z0004552 ★ | APPROACH SLAB REM | 255 | SQ YD | $25.0000 | $6,375.00 | $98.0000 | $24,990.00 |
| Z0029090 ★ | DIAMOND GRIND BR SEC | 4,996 | SQ YD | $18.0000 | $89,928.00 | $14.0000 | $69,944.00 |
| Z0041895 ★ | POLYMER CONCRETE | 3 | CU FT | $2,000.0000 | $6,000.00 | $1,920.0000 | $5,760.00 |
| Z0043800 ★ | P P CONC I-BM REPAIR | 2 | SQ FT | $1,000.0000 | $2,000.00 | $580.0000 | $1,160.00 |
| Z0062456 ★ | TEMP PAVEMENT | 1,218 | SQ YD | $125.0000 | $152,250.00 | $43.0000 | $52,374.00 |
| Z0073200 ★ | TEMP SHORING & CRIB | 1 | EACH | $8,000.0000 | $8,000.00 | $3,150.0000 | $3,150.00 |
Source: public Illinois DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.