GRADE & DRAIN WITH ASPHALT SURFACE MUD CREEK ROAD (KY 979)
- County
- FLOYD
- Letting
- May 21, 2026
- Bidders
- 2
Apparent low bid
BUSH & BURCHETT INC
$4,826,984.62
Other bidders
STANDAFER BUILDERS INC
$4,930,208.15
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | BUSH & BURCHETT INC $4,826,984.62 | STANDAFER BUILDERS INC $4,930,208.15 | ||
|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | ||||
| 00003 | CRUSHED STONE BASE | 4,030 | TON | $58.9000 | $237,367.00 | $58.9000 | $237,367.00 |
| 00020 | TRAFFIC BOUND BASE | 182 | TON | $75.0000 | $13,650.00 | $58.9000 | $10,719.80 |
| 00078 | CRUSHED AGGREGATE SIZE NO 2 | 706 | TON | $69.0000 | $48,714.00 | $42.0000 | $29,652.00 |
| 00100 | ASPHALT SEAL AGGREGATE | 107 | TON | $225.0000 | $24,075.00 | $225.0000 | $24,075.00 |
| 00103 | ASPHALT SEAL COAT | 32 | TON | $890.0000 | $28,480.00 | $890.0000 | $28,480.00 |
| 00212 | CL2 ASPH BASE 1.00D PG64-22 | 3,995 | TON | $162.1000 | $647,589.50 | $162.1000 | $647,589.50 |
| 00301 | CL2 ASPH SURF 0.38D PG64-22 | 1,070 | TON | $189.6000 | $202,872.00 | $189.6000 | $202,872.00 |
| 00441 | ENTRANCE PIPE-18 IN | 36 | LF | $86.0000 | $3,096.00 | $32.0000 | $1,152.00 |
| 00443 | ENTRANCE PIPE-24 IN | 60 | LF | $94.0000 | $5,640.00 | $44.0000 | $2,640.00 |
| 00450 | ENTRANCE PIPE-15 IN EQUIV | 134 | LF | $82.0000 | $10,988.00 | $37.0000 | $4,958.00 |
| 00468 | CULVERT PIPE-36 IN | 170 | LF | $161.0000 | $27,370.00 | $200.0000 | $34,000.00 |
| 00521 | STORM SEWER PIPE-15 IN | 272 | LF | $103.0000 | $28,016.00 | $33.0000 | $8,976.00 |
| 00522 | STORM SEWER PIPE-18 IN | 60 | LF | $110.0000 | $6,600.00 | $37.0000 | $2,220.00 |
| 00554 | STORM SEWER PIPE-24 IN EQUIV | 157 | LF | $118.0000 | $18,526.00 | $48.0000 | $7,536.00 |
| 00556 | STORM SEWER PIPE-30 IN EQUIV | 174 | LF | $136.0000 | $23,664.00 | $68.0000 | $11,832.00 |
| 01000 | PERFORATED PIPE-4 IN | 530 | LF | $9.0000 | $4,770.00 | $15.0000 | $7,950.00 |
| 01010 | NON-PERFORATED PIPE-4 IN | 109 | LF | $10.0000 | $1,090.00 | $15.0000 | $1,635.00 |
| 01024 | PERF PIPE HEADWALL TY 2-4 IN | 1 | EACH | $1,100.0000 | $1,100.00 | $1,200.0000 | $1,200.00 |
| 01028 | PERF PIPE HEADWALL TY 3-4 IN | 5 | EACH | $1,350.0000 | $6,750.00 | $1,200.0000 | $6,000.00 |
| 01211 | PIPE CULVERT HEADWALL-30 IN EQUIV | 1 | EACH | $5,000.0000 | $5,000.00 | $200.0000 | $200.00 |
| 01212 | PIPE CULVERT HEADWALL-36 IN | 2 | EACH | $3,800.0000 | $7,600.00 | $6,500.0000 | $13,000.00 |
| 01453 | S & F BOX INLET-OUTLET-36 IN | 2 | EACH | $4,900.0000 | $9,800.00 | $6,500.0000 | $13,000.00 |
| 01496 | DROP BOX INLET TYPE 3 | 1 | EACH | $2,900.0000 | $2,900.00 | $3,000.0000 | $3,000.00 |
| 01529 | DROP BOX INLET TYPE 6D | 7 | EACH | $2,800.0000 | $19,600.00 | $4,000.0000 | $28,000.00 |
| 01538 | DROP BOX INLET TYPE 7 | 1 | EACH | $6,800.0000 | $6,800.00 | $2,700.0000 | $2,700.00 |
| 01740 | CORED HOLE DRAINAGE BOX CON-4 IN | 2 | EACH | $600.0000 | $1,200.00 | $350.0000 | $700.00 |
| 01890 | ISLAND HEADER CURB TYPE 1 | 972 | LF | $100.0000 | $97,200.00 | $41.2100 | $40,056.12 |
| 01987 | DELINEATOR FOR G/R BI DIRECTIONAL WHITE | 7 | EACH | $13.0000 | $91.00 | $15.4200 | $107.94 |
| 02003 | RELOCATE TEMP CONC BARRIER | 640 | LF | $44.0000 | $28,160.00 | $5.0000 | $3,200.00 |
| 02014 | BARRICADE-TYPE III | 4 | EACH | $200.0000 | $800.00 | $200.0000 | $800.00 |
| 02084 | JPC PAVEMENT-8 IN | 475 | SQYD | $150.0000 | $71,250.00 | $136.1100 | $64,652.25 |
| 02159 | TEMP DITCH | 1,550 | LF | $1.6500 | $2,557.50 | $1.0000 | $1,550.00 |
| 02160 | CLEAN TEMP DITCH | 775 | LF | $2.2500 | $1,743.75 | $0.1000 | $77.50 |
| 02191 | STRUCTURE DEMOLITION | 1 | EACH | $6,800.0000 | $6,800.00 | $3,500.0000 | $3,500.00 |
| 02200 | ROADWAY EXCAVATION | 48,269 | CUYD | $14.0000 | $675,766.00 | $20.0000 | $965,380.00 |
| 02203 | STRUCTURE EXCAV-UNCLASSIFIED | 215 | CUYD | $13.0000 | $2,795.00 | $25.0000 | $5,375.00 |
| 02223 | GRANULAR EMBANKMENT | 6,094 | CUYD | $50.0000 | $304,700.00 | $50.0000 | $304,700.00 |
| 02242 | WATER | 117 | MGAL | $1.0000 | $117.00 | $1.0000 | $117.00 |
| 02360 | G/R TERMINAL SECTION NO 1 | 8 | EACH | $65.0000 | $520.00 | $93.2500 | $746.00 |
| 02371 | G/R END TREATMENT TYPE 7 | 2 | EACH | $1,700.0000 | $3,400.00 | $2,133.5800 | $4,267.16 |
| 02381 | REMOVE G/R | 1,077 | LF | $3.8500 | $4,146.45 | $3.2000 | $3,446.40 |
| 02397 | TEMP G/R | 612.5 | LF | $18.7500 | $11,484.38 | $20.7900 | $12,733.88 |
| 02429 | RIGHT-OF-WAY MONUMENT TYPE 1 | 61 | EACH | $300.0000 | $18,300.00 | $191.4300 | $11,677.23 |
| 02430 | RIGHT-OF-WAY MONUMENT TYPE 1A | 3 | EACH | $300.0000 | $900.00 | $173.5500 | $520.65 |
| 02431 | WITNESS R/W MONUMENT TYPE 2 | 3 | EACH | $200.0000 | $600.00 | $178.9200 | $536.76 |
| 02432 | WITNESS POST | 3 | EACH | $200.0000 | $600.00 | $155.6700 | $467.01 |
| 02483 | CHANNEL LINING CLASS II | 115 | TON | $70.0000 | $8,050.00 | $45.0000 | $5,175.00 |
| 02484 | CHANNEL LINING CLASS III | 83 | TON | $71.0000 | $5,893.00 | $50.0000 | $4,150.00 |
| 02545 | CLEARING AND GRUBBING | 1 | LS | $46,500.0000 | $46,500.00 | $125,000.0000 | $125,000.00 |
| 02555 | CONCRETE-CLASS B | 100 | CUYD | $2,000.0000 | $200,000.00 | $745.0000 | $74,500.00 |
| 02562 | TEMPORARY SIGNS | 500 | SQFT | $15.0000 | $7,500.00 | $40.0000 | $20,000.00 |
| 02568 40178 | MOBILIZATION | 1 | LS | $200,000.0000 | $200,000.00 | $200,000.0000 | $200,000.00 |
| 02569 | DEMOBILIZATION | 1 | LS | $72,000.0000 | $72,000.00 | $75,000.0000 | $75,000.00 |
| 02585 | EDGE KEY | 68 | LF | $53.5000 | $3,638.00 | $53.5000 | $3,638.00 |
| 02602 40176 | FABRIC-GEOTEXTILE CLASS 1 | 12,056 | SQYD | $1.8500 | $22,303.60 | $1.8500 | $22,303.60 |
| 02603 | FABRIC-GEOTEXTILE CLASS 2 | 66 | SQYD | $6.5000 | $429.00 | $2.0000 | $132.00 |
| 02607 | FABRIC-GEOTEXTILE CLASS 2 FOR PIPE | 1,997 | SQYD | $2.0000 | $3,994.00 | $2.0000 | $3,994.00 |
| 02608 | FABRIC-GEOTEXTILE CLASS 4A | 13,433 | SQYD | $3.0000 | $40,299.00 | $3.7500 | $50,373.75 |
| 02650 | MAINTAIN & CONTROL TRAFFIC | 1 | LS | $100,000.0000 | $100,000.00 | $185,000.0000 | $185,000.00 |
| 02651 | DIVERSIONS (BY-PASS DETOURS) | 1 | LS | $14,000.0000 | $14,000.00 | $8,500.0000 | $8,500.00 |
| 02653 | LANE CLOSURE | 2 | EACH | $1,000.0000 | $2,000.00 | $3,200.0000 | $6,400.00 |
| 02671 | PORTABLE CHANGEABLE MESSAGE SIGN | 2 | EACH | $9,000.0000 | $18,000.00 | $11,000.0000 | $22,000.00 |
| 02690 | SAFELOADING | 4 | CUYD | $230.0000 | $920.00 | $350.0000 | $1,400.00 |
| 02697 | EDGELINE RUMBLE STRIPS | 5,705 | LF | $1.1000 | $6,275.50 | $0.3500 | $1,996.75 |
| 02701 | TEMP SILT FENCE | 1,550 | LF | $3.0000 | $4,650.00 | $3.5500 | $5,502.50 |
| 02703 | SILT TRAP TYPE A | 16 | EACH | $250.0000 | $4,000.00 | $45.0000 | $720.00 |
| 02704 40037 | SILT TRAP TYPE B | 16 | EACH | $250.0000 | $4,000.00 | $45.0000 | $720.00 |
| 02705 40031 | SILT TRAP TYPE C | 16 | EACH | $250.0000 | $4,000.00 | $45.0000 | $720.00 |
| 02706 | CLEAN SILT TRAP TYPE A | 16 | EACH | $240.0000 | $3,840.00 | $10.0000 | $160.00 |
| 02707 | CLEAN SILT TRAP TYPE B | 16 | EACH | $240.0000 | $3,840.00 | $10.0000 | $160.00 |
| 02708 | CLEAN SILT TRAP TYPE C | 16 | EACH | $240.0000 | $3,840.00 | $10.0000 | $160.00 |
| 02726 | STAKING | 1 | LS | $35,400.0000 | $35,400.00 | $36,000.0000 | $36,000.00 |
| 02731 | REMOVE STRUCTURE | 1 | LS | $200,000.0000 | $200,000.00 | $1,800.0000 | $1,800.00 |
| 03171 | CONC BARRIER WALL TYPE 9T | 640 | LF | $100.0000 | $64,000.00 | $80.0000 | $51,200.00 |
| 04933 | TEMP SIGNAL 2 PHASE | 2 | EACH | $5,000.0000 | $10,000.00 | $24,000.0000 | $48,000.00 |
| 05950 40032 | EROSION CONTROL BLANKET | 3,292 | SQYD | $2.5500 | $8,394.60 | $2.6600 | $8,756.72 |
| 05952 | TEMP MULCH | 49,713 | SQYD | $0.2500 | $12,428.25 | $0.4000 | $19,885.20 |
| 05953 | TEMP SEEDING AND PROTECTION | 37,285 | SQYD | $0.2700 | $10,066.95 | $0.4200 | $15,659.70 |
| 05963 | INITIAL FERTILIZER | 1.8 | TON | $1,700.0000 | $3,060.00 | $1,791.7200 | $3,225.10 |
| 05964 | MAINTENANCE FERTILIZER | 3 | TON | $1,700.0000 | $5,100.00 | $1,791.7200 | $5,375.16 |
| 05985 | SEEDING AND PROTECTION | 54,887 | SQYD | $0.5700 | $31,285.59 | $0.7700 | $42,262.99 |
| 05992 | AGRICULTURAL LIMESTONE | 34 | TON | $125.0000 | $4,250.00 | $82.3100 | $2,798.54 |
| 06510 | PAVE STRIPING-TEMP PAINT-4 IN | 3,700 | LF | $0.1800 | $666.00 | $0.1800 | $666.00 |
| 06514 | PAVE STRIPING-PERM PAINT-4 IN | 490 | LF | $0.2200 | $107.80 | $0.2200 | $107.80 |
| 06515 | PAVE STRIPING-PERM PAINT-6 IN | 14,376 | LF | $0.2500 | $3,594.00 | $0.2500 | $3,594.00 |
| 06568 | PAVE MARKING-THERMO STOP BAR-24IN | 36 | LF | $12.0000 | $432.00 | $12.0000 | $432.00 |
| 06574 | PAVE MARKING-THERMO CURV ARROW | 8 | EACH | $125.0000 | $1,000.00 | $125.0000 | $1,000.00 |
| 06576 | PAVE MARKING-THERMO ONLY | 1 | EACH | $300.0000 | $300.00 | $300.0000 | $300.00 |
| 08003 | FOUNDATION PREPARATION | 1 | LS | $235,000.0000 | $235,000.00 | $15,000.0000 | $15,000.00 |
| 08100 | CONCRETE-CLASS A | 125.9 | CUYD | $2,000.0000 | $251,800.00 | $1,492.0000 | $187,842.80 |
| 08150 | STEEL REINFORCEMENT | 17,681 | LB | $3.0000 | $53,043.00 | $2.0000 | $35,362.00 |
| 08410 | LOW FLOW DIVERSION CURB | 1 | LS | $20,000.0000 | $20,000.00 | $5,500.0000 | $5,500.00 |
| 08911 | CRASH CUSHION TY 6 CLASS T TL2 | 2 | EACH | $15,000.0000 | $30,000.00 | $5,598.2600 | $11,196.52 |
| 10020NS | FUEL ADJUSTMENT | 20,939 | DOLL | $1.0000 | $20,939.00 | $1.0000 | $20,939.00 |
| 10030NS | ASPHALT ADJUSTMENT | 21,284 | DOLL | $1.0000 | $21,284.00 | $1.0000 | $21,284.00 |
| 14007 | W ENCASEMENT STEEL BORED RANGE 2 | 110 | LF | $142.0000 | $15,620.00 | $520.0000 | $57,200.00 |
| 14009 | W ENCASEMENT STEEL BORED RANGE 4 | 115 | LF | $163.0000 | $18,745.00 | $560.0000 | $64,400.00 |
| 14022 | W FLUSH HYDRANT ASSEMBLY | 5 | EACH | $850.0000 | $4,250.00 | $16,500.0000 | $82,500.00 |
| 14035 | W PIPE DUCTILE IRON 04 INCH | 329 | LF | $46.0000 | $15,134.00 | $82.0000 | $26,978.00 |
| 14037 | W PIPE DUCTILE IRON 08 INCH | 1,465 | LF | $64.0000 | $93,760.00 | $85.0000 | $124,525.00 |
| 14058 | W PIPE PVC 04 INCH | 500 | LF | $48.0000 | $24,000.00 | $68.0000 | $34,000.00 |
| 14060 | W PIPE PVC 08 INCH | 2,600 | LF | $42.0000 | $109,200.00 | $78.0000 | $202,800.00 |
| 14080 | W SERV PE/PLST LONG SIDE 3/4 IN | 25 | EACH | $610.0000 | $15,250.00 | $3,200.0000 | $80,000.00 |
| 14095 | W TIE-IN 08 INCH | 3 | EACH | $2,310.0000 | $6,930.00 | $6,800.0000 | $20,400.00 |
| 14104 | W VALVE 04 INCH | 4 | EACH | $1,880.0000 | $7,520.00 | $2,400.0000 | $9,600.00 |
| 14106 | W VALVE 08 INCH | 11 | EACH | $1,820.0000 | $20,020.00 | $4,400.0000 | $48,400.00 |
| 20071EC | JOINT ADHESIVE | 9,300 | LF | $0.9500 | $8,835.00 | $0.9500 | $8,835.00 |
| 20099ES842 | PAVE MARK TEMP PAINT STOP BAR | 23 | LF | $10.0000 | $230.00 | $10.0000 | $230.00 |
| 21802EN | G/R STEEL W BEAM-S FACE (7 FT POST) | 812.5 | LF | $33.5000 | $27,218.75 | $33.8000 | $27,462.50 |
| 22664EN | WATER BLASTING EXISTING STRIPE | 1,000 | LF | $2.5000 | $2,500.00 | $2.5000 | $2,500.00 |
| 23274EN11F | TURF REINFORCEMENT MAT 1 | 1,094 | SQYD | $9.0000 | $9,846.00 | $11.2900 | $12,351.26 |
| 23791EC | PAVE STRIPING-CHEVRON MARKINGS | 644 | SQFT | $6.5000 | $4,186.00 | $6.5000 | $4,186.00 |
| 23952EC | DRAINAGE JUNCTION BOX TY B | 1 | EACH | $3,560.0000 | $3,560.00 | $1,700.0000 | $1,700.00 |
| 24814EC | PIPELINE INSPECTION | 561 | LF | $8.0000 | $4,488.00 | $4.4600 | $2,502.06 |
| 24970EC | ASPHALT MATERIAL FOR TACK NON-TRACKING | 8 | TON | $860.0000 | $6,880.00 | $860.0000 | $6,880.00 |
| 26248EC | ELECTRONIC DELIVERY MGMT SYSTEM - AGG | 1 | LS | $1,500.0000 | $1,500.00 | $1,500.0000 | $1,500.00 |
Source: public Kentucky DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →