LA
Louisiana DOT · Bid Tabulation
Contract H.015526.6
CHIPPEWA ST PUMP STATION IMP PHASE 1
- County
- East Baton Rouge
- District
- HQ
- Letting
- June 30, 2026
- Bidders
- 2
Apparent low bid
Grady Crawford Const. Co., Inc. of Baton Rouge
$1,409,540.42
Other bidders
Jack B. Harper Electrical LLC
$1,589,271.33
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | Grady Crawford Const. Co., Inc. of Baton Rouge $1,409,540.42 | Jack B. Harper Electrical LLC $1,589,271.33 | ||
|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | ||||
| 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | $58,169.2600 | $58,169.26 | $45,470.7700 | $45,470.77 |
| 727-01-00100 | Mobilization | 1 | LUMP | $159,275.0000 | $159,275.00 | $103,184.6200 | $103,184.62 |
| 729-01-00100 | Sign (Type A) | 96 | SQFT | $46.0000 | $4,416.00 | $59.8500 | $5,745.60 |
| 729-01-00200 | Mounting of Sign (Type A) | 6 | EACH | $377.1700 | $2,263.02 | $196.9200 | $1,181.52 |
| 729-08-00200 | Sign Support (3 1/2" Size Post) | 2 | EACH | $3,101.3000 | $6,202.60 | $4,290.7700 | $8,581.54 |
| 736-04-00001 | Signal Pole (Pedestal Pole) | 4 | EACH | $3,200.0000 | $12,800.00 | $1,838.4600 | $7,353.84 |
| 736-15-02400 | Signal Support (Foundation, 24 inch Minimum Diameter) | 4 | EACH | $8,625.0000 | $34,500.00 | $2,053.8500 | $8,215.40 |
| 740-01-00100 | Construction Layout | 1 | LUMP | $26,000.0000 | $26,000.00 | $12,830.7700 | $12,830.77 |
| 805-01-00500 | Class A1 Concrete (Footing) | 4.36 | CUYD | $4,059.8100 | $17,700.77 | $6,185.4900 | $26,968.74 |
| 806-01-00100 | Deformed Reinforcing Steel | 1,148 | LB | $9.1700 | $10,527.16 | $6.2200 | $7,140.56 |
| NS-ITS-01121 | CCTV Camera Assembly, Furnish and Install with PTZ, Digital | 2 | EACH | $5,991.8300 | $11,983.66 | $38,935.6600 | $77,871.32 |
| NS-ITS-04000 | Fiber Optic Marker | 8 | EACH | $180.0000 | $1,440.00 | $136.9200 | $1,095.36 |
| NS-ITS-04005 | Tracer Wire (THWN #10 AWG Green Copper Conductor) | 3,000 | LNFT | $1.9800 | $5,940.00 | $1.3400 | $4,020.00 |
| NS-ITS-04020 | Fiber Optic Cable, SM, Furnish & Install, 13-48 Fibers | 3,750 | LNFT | $3.8300 | $14,362.50 | $4.4000 | $16,500.00 |
| NS-ITS-04180 | Fiber Optic Connection, Install, Splice | 3 | EACH | $48.0000 | $144.00 | $45.3800 | $136.14 |
| NS-ITS-04200 | Fiber Optic Connection, Termination, Furnish & Install | 5 | EACH | $48.0000 | $240.00 | $68.4600 | $342.30 |
| NS-ITS-04420 | Fiber Optic Connection Patch Panel, Indoor, Furnish & Install | 1 | EACH | $27.9000 | $27.90 | $790.7700 | $790.77 |
| NS-ITS-06020 | Pullbox, In-ground, Furnish & Install | 7 | EACH | $2,339.2400 | $16,374.68 | $7,183.7500 | $50,286.25 |
| NS-ITS-09080 | Local Ethernet Switch, Furnish & Install | 1 | EACH | $1,955.0000 | $1,955.00 | $4,795.3800 | $4,795.38 |
| NS-ITS-13200 | As-Builts | 1 | LUMP | $10,500.0000 | $10,500.00 | $3,169.2300 | $3,169.23 |
| TS-729-00040 | Flashing Beacon Assembly on Pedestal Pole | 4 | EACH | $7,864.1600 | $31,456.64 | $8,261.5400 | $33,046.16 |
| TS-822-09100 | Electrical System (Pump Station) | 1 | LUMP | $983,262.2300 | $983,262.23 | $1,170,545.0600 | $1,170,545.06 |
Source: public Louisiana DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.