MI
Michigan DOT · Bid Tabulation
Contract 34000-218313
1.50 mi of hot mix asphalt base crushing and shaping, hot mix asphalt paving, and pavement markings on Nash Highway from M-50 to north of Kein Road, Ionia County. This is a Local Agency project. ** 995 Cb or 995 Ea **In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications of Cb and Ea. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.
- County
- Ionia County
- Letting
- June 5, 2026
- Bidders
- 6
Apparent low bid
Nashville Construction Company
$954,835.76
Other bidders
Lakeland Asphalt Corporation
$996,456.33
Rieth-Riley Construction Co., Inc.
$1,052,414.41
J & N Construction, LLC
$1,057,772.13
Michigan Paving and Materials Company
$1,092,255.00
Hoffman Bros., Inc.
$1,130,775.00
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | Nashville Construction Company $954,835.76 | Lakeland Asphalt Corporation $996,456.33 | Rieth-Riley Construction Co., Inc. $1,052,414.41 | J & N Construction, LLC $1,057,772.13 | Michigan Paving and Materials Company $1,092,255.00 | Hoffman Bros., Inc. $1,130,775.00 | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 1100001 | Mobilization, Max $90,500.00 | 1 | LS | $90,500.0000 | $90,500.00 | $53,600.0000 | $53,600.00 | $49,650.0000 | $49,650.00 | $90,500.0000 | $90,500.00 | $55,382.2500 | $55,382.25 | $90,500.0000 | $90,500.00 |
| 2020006 | Stump, Rem, 19 inch to 36 inch | 17 | Ea | $500.0000 | $8,500.00 | $425.0000 | $7,225.00 | $475.0000 | $8,075.00 | $425.0000 | $7,225.00 | $475.0000 | $8,075.00 | $225.0000 | $3,825.00 |
| 2020007 | Stump, Rem, 37 inch or Larger | 24 | Ea | $600.0000 | $14,400.00 | $510.0000 | $12,240.00 | $600.0000 | $14,400.00 | $650.0000 | $15,600.00 | $600.0000 | $14,400.00 | $450.0000 | $10,800.00 |
| 2020008 | Stump, Rem, 6 inch to 18 inch | 13 | Ea | $200.0000 | $2,600.00 | $300.0000 | $3,900.00 | $300.0000 | $3,900.00 | $275.0000 | $3,575.00 | $300.0000 | $3,900.00 | $75.0000 | $975.00 |
| 2040045 | Masonry and Conc Structure, Rem | 2 | Cyd | $50.0000 | $100.00 | $245.0000 | $490.00 | $245.0000 | $490.00 | $200.0000 | $400.00 | $245.0000 | $490.00 | $243.7000 | $487.40 |
| 2040050 | Pavt, Rem | 56 | Syd | $20.0000 | $1,120.00 | $31.7500 | $1,778.00 | $31.7500 | $1,778.00 | $12.0000 | $672.00 | $31.7500 | $1,778.00 | $31.7500 | $1,778.00 |
| 2050031 | Non Haz Contaminated Material Handling and Disposal, LM | 50 | Cyd | $100.0000 | $5,000.00 | $57.5000 | $2,875.00 | $57.5000 | $2,875.00 | $0.0100 | $0.50 | $57.5000 | $2,875.00 | $57.5000 | $2,875.00 |
| 2050041 | Subgrade Undercutting, Type II | 100 | Cyd | $40.0000 | $4,000.00 | $76.2000 | $7,620.00 | $76.2000 | $7,620.00 | $0.0100 | $1.00 | $76.2000 | $7,620.00 | $76.2000 | $7,620.00 |
| 2080036 | Erosion Control, Silt Fence | 100 | Ft | $3.0000 | $300.00 | $5.5500 | $555.00 | $5.5500 | $555.00 | $3.5000 | $350.00 | $5.5500 | $555.00 | $5.5500 | $555.00 |
| 3020020 | Aggregate Base, 8 inch | 7,907 | Syd | $10.7500 | $85,000.25 | $16.0000 | $126,512.00 | $16.0000 | $126,512.00 | $18.0000 | $142,326.00 | $16.0000 | $126,512.00 | $17.3500 | $137,186.45 |
| 3050002 | HMA Base Crushing and Shaping | 19,818 | Syd | $2.0000 | $39,636.00 | $2.1600 | $42,806.88 | $2.1600 | $42,806.88 | $2.2500 | $44,590.50 | $2.1600 | $42,806.88 | $2.8500 | $56,481.30 |
| 3050010 | Material, Surplus and Unsuitable, Rem, LM | 178 | Cyd | $12.0000 | $2,136.00 | $21.0000 | $3,738.00 | $21.0000 | $3,738.00 | $25.0000 | $4,450.00 | $21.0000 | $3,738.00 | $20.9000 | $3,720.20 |
| 3050015 | Salv Crushed Material, LM | 50 | Cyd | $20.0000 | $1,000.00 | $8.4000 | $420.00 | $8.4000 | $420.00 | $20.0000 | $1,000.00 | $8.4000 | $420.00 | $8.3000 | $415.00 |
| 3060020 | Maintenance Gravel | 200 | Ton | $1.0000 | $200.00 | $0.0100 | $2.00 | $0.0100 | $2.00 | $0.0100 | $2.00 | $0.0100 | $2.00 | $0.0100 | $2.00 |
| 3070001 | Approach, Cl I | 85 | Ton | $30.0000 | $2,550.00 | $48.0000 | $4,080.00 | $48.0000 | $4,080.00 | $43.0000 | $3,655.00 | $48.0000 | $4,080.00 | $48.1000 | $4,088.50 |
| 3070021 | Approach, Cl II | 319 | Ton | $30.0000 | $9,570.00 | $42.0000 | $13,398.00 | $42.0000 | $13,398.00 | $43.0000 | $13,717.00 | $42.0000 | $13,398.00 | $41.8500 | $13,350.15 |
| 3077002 | _ Trenching, Modified | 159 | Sta | $500.0000 | $79,500.00 | $512.0000 | $81,408.00 | $512.0000 | $81,408.00 | $400.0000 | $63,600.00 | $512.0000 | $81,408.00 | $568.9000 | $90,455.10 |
| 3077031 | _ Shld, Cl II, Modified | 366 | Ton | $27.5000 | $10,065.00 | $43.0000 | $15,738.00 | $43.0000 | $15,738.00 | $51.0000 | $18,666.00 | $43.0000 | $15,738.00 | $43.1500 | $15,792.90 |
| 4030005 | Dr Structure Cover, Adj, Case 1 | 1 | Ea | $600.0000 | $600.00 | $1,177.0000 | $1,177.00 | $1,177.0000 | $1,177.00 | $800.0000 | $800.00 | $1,177.0000 | $1,177.00 | $1,177.0000 | $1,177.00 |
| 4030006 | Dr Structure Cover, Adj, Case 2 | 1 | Ea | $600.0000 | $600.00 | $951.0000 | $951.00 | $951.0000 | $951.00 | $600.0000 | $600.00 | $951.0000 | $951.00 | $951.2000 | $951.20 |
| 4040073 | Underdrain, Subgrade, 6 inch | 200 | Ft | $8.0000 | $1,600.00 | $11.7500 | $2,350.00 | $11.7500 | $2,350.00 | $10.0000 | $2,000.00 | $11.7500 | $2,350.00 | $11.7500 | $2,350.00 |
| 4040093 | Underdrain Outlet, 6 inch | 50 | Ft | $20.0000 | $1,000.00 | $30.0000 | $1,500.00 | $30.0000 | $1,500.00 | $65.0000 | $3,250.00 | $30.0000 | $1,500.00 | $29.6500 | $1,482.50 |
| 4040113 | Underdrain, Outlet Ending, 6 inch | 2 | Ea | $250.0000 | $500.00 | $420.0000 | $840.00 | $420.0000 | $840.00 | $200.0000 | $400.00 | $420.0000 | $840.00 | $415.3000 | $830.60 |
| 5010005 | HMA Surface, Rem | 195 | Syd | $6.0000 | $1,170.00 | $13.0000 | $2,535.00 | $13.0000 | $2,535.00 | $8.0000 | $1,560.00 | $13.0000 | $2,535.00 | $12.6500 | $2,466.75 |
| 5010061 | HMA Approach | 166 | Ton | $77.2700 | $12,826.82 | $76.5000 | $12,699.00 | $163.1900 | $27,089.54 | $144.1900 | $23,935.54 | $185.0000 | $30,710.00 | $95.1000 | $15,786.60 |
| 5012024 | HMA, 4EL | 3,093 | Ton | $77.2700 | $238,996.11 | $76.5000 | $236,614.50 | $80.9200 | $250,285.56 | $80.9200 | $250,285.56 | $87.0000 | $269,091.00 | $76.5000 | $236,614.50 |
| 5012036 | HMA, 5EL | 2,320 | Ton | $77.2700 | $179,266.40 | $76.5000 | $177,480.00 | $89.6400 | $207,964.80 | $89.6200 | $207,918.40 | $96.0000 | $222,720.00 | $76.5000 | $177,480.00 |
| 8070095 | Post, Mailbox | 24 | Ea | $100.0000 | $2,400.00 | $100.0000 | $2,400.00 | $80.0000 | $1,920.00 | $125.0000 | $3,000.00 | $80.0000 | $1,920.00 | $79.5000 | $1,908.00 |
| 8110231 | Pavt Mrkg, Waterborne, 4 inch, White | 15,806 | Ft | $0.0900 | $1,422.54 | $0.1400 | $2,212.84 | $0.0900 | $1,422.54 | $0.0900 | $1,422.54 | $0.0900 | $1,422.54 | $0.0900 | $1,422.54 |
| 8110232 | Pavt Mrkg, Waterborne, 4 inch, Yellow | 13,905 | Ft | $0.0900 | $1,251.45 | $0.1400 | $1,946.70 | $0.0900 | $1,251.45 | $0.0900 | $1,251.45 | $0.0900 | $1,251.45 | $0.0900 | $1,251.45 |
| 8110251 | Pavt Mrkg, Waterborne, 2nd Application, 4 inch, White | 15,806 | Ft | $0.0900 | $1,422.54 | $0.1100 | $1,738.66 | $0.0800 | $1,264.48 | $0.0800 | $1,264.48 | $0.0800 | $1,264.48 | $0.0800 | $1,264.48 |
| 8110252 | Pavt Mrkg, Waterborne, 2nd Application, 4 inch, Yellow | 13,905 | Ft | $0.0900 | $1,251.45 | $0.1100 | $1,529.55 | $0.0800 | $1,112.40 | $0.0800 | $1,112.40 | $0.0800 | $1,112.40 | $0.0800 | $1,112.40 |
| 8120012 | Barricade, Type III, High Intensity, Double Sided, Lighted, Furn | 21 | Ea | $66.6400 | $1,399.44 | $66.6400 | $1,399.44 | $45.0000 | $945.00 | $45.0000 | $945.00 | $45.0000 | $945.00 | $101.5000 | $2,131.50 |
| 8120013 | Barricade, Type III, High Intensity, Double Sided, Lighted, Oper | 21 | Ea | $3.4000 | $71.40 | $3.4000 | $71.40 | $5.0000 | $105.00 | $5.0000 | $105.00 | $5.0000 | $105.00 | $5.0000 | $105.00 |
| 8120140 | Lighted Arrow, Type C, Furn | 2 | Ea | $408.0000 | $816.00 | $408.0000 | $816.00 | $200.0000 | $400.00 | $200.0000 | $400.00 | $200.0000 | $400.00 | $395.0000 | $790.00 |
| 8120141 | Lighted Arrow, Type C, Oper | 2 | Ea | $68.0000 | $136.00 | $68.0000 | $136.00 | $100.0000 | $200.00 | $100.0000 | $200.00 | $100.0000 | $200.00 | $25.0000 | $50.00 |
| 8120170 | Minor Traf Devices | 1 | LS | $37,400.0000 | $37,400.00 | $94,858.0000 | $94,858.00 | $97,150.0000 | $97,150.00 | $94,921.0000 | $94,921.00 | $97,169.0000 | $97,169.00 | $168,200.0000 | $168,200.00 |
| 8120246 | Pavt Mrkg, Wet Reflective, Type R, Tape, 4 inch, Yellow, Temp | 1,264 | Ft | $1.7500 | $2,212.00 | $1.5000 | $1,896.00 | $1.9700 | $2,490.08 | $1.9700 | $2,490.08 | $1.7500 | $2,212.00 | $1.7500 | $2,212.00 |
| 8120252 | Plastic Drum, Fluorescent, Furn | 110 | Ea | $27.8800 | $3,066.80 | $27.8800 | $3,066.80 | $14.0000 | $1,540.00 | $14.0000 | $1,540.00 | $14.0000 | $1,540.00 | $13.0000 | $1,430.00 |
| 8120253 | Plastic Drum, Fluorescent, Oper | 110 | Ea | $1.3600 | $149.60 | $1.3600 | $149.60 | $1.0000 | $110.00 | $1.0000 | $110.00 | $1.0000 | $110.00 | $0.5000 | $55.00 |
| 8120264 | Pavt Mrkg, Wet Reflective, Type NR, Tape, 4 inch, Yellow, Temp | 1,264 | Ft | $1.7500 | $2,212.00 | $1.5000 | $1,896.00 | $2.8700 | $3,627.68 | $2.8700 | $3,627.68 | $1.0000 | $1,264.00 | $1.7500 | $2,212.00 |
| 8120310 | Sign Cover | 91 | Ea | $30.0000 | $2,730.00 | $30.0000 | $2,730.00 | $5.0000 | $455.00 | $5.0000 | $455.00 | $5.0000 | $455.00 | $35.0000 | $3,185.00 |
| 8120350 | Sign, Type B, Temp, Prismatic, Furn | 1,071 | Sft | $4.6600 | $4,990.86 | $4.6600 | $4,990.86 | $2.0000 | $2,142.00 | $2.0000 | $2,142.00 | $2.0000 | $2,142.00 | $4.1000 | $4,391.10 |
| 8120351 | Sign, Type B, Temp, Prismatic, Oper | 1,071 | Sft | $0.0500 | $53.55 | $0.0500 | $53.55 | $1.0000 | $1,071.00 | $1.0000 | $1,071.00 | $1.0000 | $1,071.00 | $0.5000 | $535.50 |
| 8120352 | Sign, Type B, Temp, Prismatic, Spec, Furn | 455 | Sft | $4.7600 | $2,165.80 | $4.7600 | $2,165.80 | $4.0000 | $1,820.00 | $4.0000 | $1,820.00 | $4.0000 | $1,820.00 | $4.1500 | $1,888.25 |
| 8120353 | Sign, Type B, Temp, Prismatic, Spec, Oper | 455 | Sft | $0.0500 | $22.75 | $0.0500 | $22.75 | $1.0000 | $455.00 | $1.0000 | $455.00 | $1.0000 | $455.00 | $0.3500 | $159.25 |
| 8120370 | Traf Regulator Control | 1 | LS | $5,025.0000 | $5,025.00 | $11,000.0000 | $11,000.00 | $13,950.0000 | $13,950.00 | $5,420.0000 | $5,420.00 | $13,500.0000 | $13,500.00 | $17,325.3800 | $17,325.38 |
| 8162007 | Slope Restoration, Non-Freeway, Type G | 17,600 | Syd | $5.0000 | $88,000.00 | $2.4400 | $42,944.00 | $2.4400 | $42,944.00 | $1.6500 | $29,040.00 | $2.4400 | $42,944.00 | $2.0000 | $35,200.00 |
| 8210001 | Monument Box | 3 | Ea | $800.0000 | $2,400.00 | $800.0000 | $2,400.00 | $800.0000 | $2,400.00 | $800.0000 | $2,400.00 | $800.0000 | $2,400.00 | $800.0000 | $2,400.00 |
| 8210010 | Monument Preservation | 3 | Ea | $500.0000 | $1,500.00 | $500.0000 | $1,500.00 | $500.0000 | $1,500.00 | $500.0000 | $1,500.00 | $500.0000 | $1,500.00 | $500.0000 | $1,500.00 |
Source: public Michigan DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →