MN Minnesota DOT · Bid Tabulation

Contract 260096

LOCATED ON T.H. 22 FROM 2575 FT NORTH OF CSAH 12 TO 340 FT SOUTH OF 210TH ST NEAR NEW AUBURN.

County
SIBLEY
Letting
June 10, 2026
Bidders
6
Apparent low bid The Mathiowetz Construction Co. $432,733.37
Other bidders B.H. Aggregate Services, Inc. $458,818.85 Holtmeier Construction, Inc. $461,140.55 Landwehr Construction, Inc. $509,855.41 Midwest Contracting, LLC $521,645.65 Minger Construction Companies, Inc. $525,186.00

Bid Items - unit price and extension by bidder

Item Description Qty UOM The Mathiowetz Construction Co. $432,733.37 B.H. Aggregate Services, Inc. $458,818.85 Holtmeier Construction, Inc. $461,140.55 Landwehr Construction, Inc. $509,855.41 Midwest Contracting, LLC $521,645.65 Minger Construction Companies, Inc. $525,186.00
Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension
2011601/01000 AS BUILT 1 LS $2,000.0000 $2,000.00 $2,000.0000 $2,000.00 $2,000.0000 $2,000.00 $2,300.0000 $2,300.00 $2,000.0000 $2,000.00 $2,300.0000 $2,300.00
2021501/00010 MOBILIZATION 1 LS $48,027.0000 $48,027.00 $24,500.0000 $24,500.00 $32,537.0000 $32,537.00 $27,575.9600 $27,575.96 $39,500.0000 $39,500.00 $29,000.0000 $29,000.00
2104502/00360 REMOVE ANCHORAGE ASSEMBLY-CABLE 2 EACH $200.0000 $400.00 $1,000.0000 $2,000.00 $200.0000 $400.00 $222.0000 $444.00 $1,000.0000 $2,000.00 $1,115.0000 $2,230.00
2104503/00450 REMOVE CABLE GUARDRAIL 1,000 L F $4.0000 $4,000.00 $7.0000 $7,000.00 $4.0000 $4,000.00 $4.4000 $4,400.00 $7.0000 $7,000.00 $7.7500 $7,750.00
2118509/00030 AGGREGATE SURFACING CLASS 2 85 TON $75.6200 $6,427.70 $100.0000 $8,500.00 $61.0500 $5,189.25 $51.5000 $4,377.50 $68.0000 $5,780.00 $54.5000 $4,632.50
2451507/00250 FINE AGGREGATE BEDDING (CV) 3 C Y $176.7200 $530.16 $200.0000 $600.00 $104.5000 $313.50 $66.8000 $200.40 $125.0000 $375.00 $57.5000 $172.50
2501502/05030 30'' RC PIPE APRON 1 EACH $2,643.4000 $2,643.40 $1,500.0000 $1,500.00 $3,395.3000 $3,395.30 $3,200.0000 $3,200.00 $4,850.0000 $4,850.00 $4,500.0000 $4,500.00
2503602/00320 CONNECT TO EXISTING STORM SEWER 1 EACH $1,030.3600 $1,030.36 $1,500.0000 $1,500.00 $1,550.0000 $1,550.00 $380.0000 $380.00 $1,250.0000 $1,250.00 $1,650.0000 $1,650.00
2511504/00017 GEOTEXTILE FILTER TYPE 7 1,128 S Y $5.6700 $6,395.76 $3.0000 $3,384.00 $4.4500 $5,019.60 $4.8000 $5,414.40 $6.9500 $7,839.60 $3.7500 $4,230.00
2511509/00013 RANDOM RIPRAP CLASS III 3,685 TON $53.9900 $198,953.15 $66.7000 $245,789.50 $63.7000 $234,734.50 $74.0000 $272,690.00 $74.8500 $275,822.25 $78.2500 $288,351.25
2511509/00020 GRANULAR FILTER MATERIAL 754 TON $46.9900 $35,430.46 $40.0000 $30,160.00 $39.1500 $29,519.10 $49.0000 $36,946.00 $58.6500 $44,222.10 $63.5000 $47,879.00
2554502/00024 END TREATMENT-TANGENT TERMINAL 2 EACH $4,000.0000 $8,000.00 $3,900.0000 $7,800.00 $4,000.0000 $8,000.00 $4,445.0000 $8,890.00 $3,900.0000 $7,800.00 $4,350.0000 $8,700.00
2554503/00131 TRAFFIC BARRIER DESIGN TYPE 31 900 L F $48.0000 $43,200.00 $45.0000 $40,500.00 $48.0000 $43,200.00 $53.3000 $47,970.00 $45.0000 $40,500.00 $50.0000 $45,000.00
2554602/00073 GUIDE POST TYPE SPECIAL 1 EACH $200.0000 $200.00 $105.0000 $105.00 $200.0000 $200.00 $116.0000 $116.00 $200.0000 $200.00 $117.0000 $117.00
2563601/00010 TRAFFIC CONTROL 1 LS $7,000.0000 $7,000.00 $10,000.0000 $10,000.00 $17,000.0000 $17,000.00 $9,500.0000 $9,500.00 $7,000.0000 $7,000.00 $9,500.0000 $9,500.00
2563601/01100 PORTABLE SIGNAL SYSTEM 1 LS $6,000.0000 $6,000.00 $8,000.0000 $8,000.00 $6,000.0000 $6,000.00 $7,400.0000 $7,400.00 $6,000.0000 $6,000.00 $7,500.0000 $7,500.00
2563602/00650 TEMPORARY DRIVEWAY SIGNAL 2 EACH $3,000.0000 $6,000.00 $500.0000 $1,000.00 $3,000.0000 $6,000.00 $2,200.0000 $4,400.00 $6,000.0000 $12,000.00 $2,285.0000 $4,570.00
2564502/00780 RIGHT OF WAY MARKER 14 EACH $200.0000 $2,800.00 $215.0000 $3,010.00 $200.0000 $2,800.00 $238.0000 $3,332.00 $200.0000 $2,800.00 $239.5000 $3,353.00
2573502/00140 CULVERT END CONTROLS 2 EACH $281.5400 $563.08 $250.0000 $500.00 $75.0000 $150.00 $225.0000 $450.00 $75.0000 $150.00 $143.5000 $287.00
2573503/00031 FLOTATION SILT CURTAIN TYPE MOVING WATER 1,253 L F $25.0000 $31,325.00 $23.7500 $29,758.75 $25.0000 $31,325.00 $27.2000 $34,081.60 $26.0000 $32,578.00 $24.0000 $30,072.00
2573503/00064 SEDIMENT CONTROL LOG TYPE COMPOST 3,428 L F $3.1500 $10,798.20 $3.9500 $13,540.60 $3.1500 $10,798.20 $4.5500 $15,597.40 $3.2000 $10,969.60 $2.5000 $8,570.00
2574505/00020 SOIL BED PREPARATION 0.8 ACRE $1,250.0000 $1,000.00 $1,000.0000 $800.00 $3,750.0000 $3,000.00 $1,145.0000 $916.00 $1,250.0000 $1,000.00 $2,230.0000 $1,784.00
2574508/00014 FERTILIZER TYPE 4 92 LB $1.2500 $115.00 $2.0000 $184.00 $1.2500 $115.00 $2.2500 $207.00 $1.2500 $115.00 $3.7500 $345.00
2575504/00325 ROLLED EROSION PREVENTION CATEGORY 25 3,561 S Y $1.7000 $6,053.70 $3.0500 $10,861.05 $1.7000 $6,053.70 $3.5000 $12,463.50 $1.7000 $6,053.70 $2.2500 $8,012.25
2575505/00021 SEEDING 0.8 ACRE $1,250.0000 $1,000.00 $2,500.0000 $2,000.00 $3,750.0000 $3,000.00 $2,863.0000 $2,290.40 $1,250.0000 $1,000.00 $550.0000 $440.00
2575505/00040 WEED SPRAYING 0.8 ACRE $350.0000 $280.00 $1,750.0000 $1,400.00 $2,850.0000 $2,280.00 $2,004.0000 $1,603.20 $350.0000 $280.00 $2,000.0000 $1,600.00
2575506/00010 WEED SPRAY MIXTURE 0.1 GAL $250.0000 $25.00 $1,400.0000 $140.00 $250.0000 $25.00 $1,600.0000 $160.00 $250.0000 $25.00 $1,100.0000 $110.00
2575608/25100 SEED MESIC INSLOPE 49 LB $8.5000 $416.50 $10.0000 $490.00 $8.5000 $416.50 $11.4500 $561.05 $8.5000 $416.50 $11.2500 $551.25
2581503/00006 6'' REMOVABLE PREFORMED PAVEMENT MARKING TAPE 171 L F $2.2000 $376.20 $2.1000 $359.10 $2.2000 $376.20 $2.3000 $393.30 $2.2000 $376.20 $2.2500 $384.75
2581503/00024 24'' REMOVABLE PREFORMED PAVEMENT MARKING TAPE 24 L F $20.0000 $480.00 $8.4000 $201.60 $20.0000 $480.00 $9.3000 $223.20 $20.0000 $480.00 $9.2500 $222.00
2581603/00020 REMOVABLE PREFORMED PLASTIC MASK (BLACK) 549 L F $2.3000 $1,262.70 $2.2500 $1,235.25 $2.3000 $1,262.70 $2.5000 $1,372.50 $2.3000 $1,262.70 $2.5000 $1,372.50

Source: public Minnesota DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.