Missouri DOT · Bid Tabulation
Contract 260618-C02
****(1): Job JKU0140 Route 150 JACKSON County. 2 Bridge rehabilitations over the Blue River in Grandview, the total length of improvement being 1.098 miles.
- County
- JACKSON
- Letting
- June 18, 2026
- Bidders
- 4
Apparent low bid
Louis-Company, LLC
$4,191,737.23
Other bidders
Concrete Strategies, LLC
$5,156,536.48
Comanche Construction, Inc.
$5,167,847.83
Iowa Civil Contracting, Inc.
$5,364,061.90
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | Louis-Company, LLC $4,191,737.23 | Concrete Strategies, LLC $5,156,536.48 | Comanche Construction, Inc. $5,167,847.83 | Iowa Civil Contracting, Inc. $5,364,061.90 | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 2019919 | MISC. TREE CLEARING | 2 | ACRE | $9,289.6900 | $18,579.38 | $19,100.0000 | $38,200.00 | $18,002.4400 | $36,004.88 | $11,700.0000 | $23,400.00 |
| 2022010 | REMOVAL OF IMPROVEMENTS | 1 | LS | $31,690.8000 | $31,690.80 | $205,000.0000 | $205,000.00 | $222,923.0700 | $222,923.07 | $178,000.0000 | $178,000.00 |
| 2031000 | CLASS A EXCAVATION | 4,391 | CUYD | $14.6100 | $64,152.51 | $36.5000 | $160,271.50 | $34.1800 | $150,084.38 | $19.2100 | $84,351.11 |
| 2035500 | EMBANKMENT IN PLACE | 2,106 | CUYD | $24.1900 | $50,944.14 | $39.0000 | $82,134.00 | $36.8000 | $77,500.80 | $37.5700 | $79,122.42 |
| 2036000 | COMPACTING EMBANKMENT | 2,258 | CUYD | $11.5400 | $26,057.32 | $11.5000 | $25,967.00 | $10.5200 | $23,754.16 | $24.4500 | $55,208.10 |
| 2037075 | COMPACTING IN CUT | 35.7 | STA | $799.3900 | $28,538.22 | $1,060.0000 | $37,842.00 | $998.9700 | $35,663.23 | $775.6800 | $27,691.78 |
| 2063000 | CLASS 3 EXCAVATION | 276 | CUYD | $49.9700 | $13,791.72 | $22.5000 | $6,210.00 | $21.0300 | $5,804.28 | $52.5700 | $14,509.32 |
| 2069902 | MISC. DRAINAGE SYSTEM CLEANOUT | 2 | EA | $862.0600 | $1,724.12 | $3,910.0000 | $7,820.00 | $3,680.4100 | $7,360.82 | $1,710.7900 | $3,421.58 |
| 2153000 | SHAPING SLOPES, CLASS III | 6 | 100F | $1,914.6300 | $11,487.78 | $1,115.0000 | $6,690.00 | $1,051.5500 | $6,309.30 | $1,720.0000 | $10,320.00 |
| 2161000 | SCARIFICATION OF BRIDGE DECK | 13,808 | SQYD | $6.7300 | $92,925.60 | $5.5000 | $75,944.00 | $11.2400 | $155,196.32 | $6.1500 | $84,919.20 |
| 2164500 | REMOVAL OF EXISTING EXPANSION JOINT & ADJACENT CONCRETE | 234 | LF | $364.0800 | $85,194.72 | $350.0000 | $81,900.00 | $506.5700 | $118,537.38 | $731.1200 | $171,082.08 |
| 3040504 | TYPE 5 AGGREGATE FOR BASE (4 IN. THICK) | 6,502 | SQYD | $13.5300 | $87,972.06 | $20.0000 | $130,040.00 | $18.9300 | $123,082.86 | $14.3500 | $93,303.70 |
| 4019905 | MISC. TEMPORARY OPTIONAL PAVEMENT | 5,931.1 | SQYD | $99.6200 | $590,856.18 | $56.5000 | $335,107.15 | $53.1000 | $314,941.41 | $57.6000 | $341,631.36 |
| 5021312 | CONCRETE PAVEMENT (12 IN. NON-REINFORCED 15 FT. JOINTS) | 569.9 | SQYD | $131.2100 | $74,776.58 | $140.0000 | $79,786.00 | $115.3000 | $65,709.47 | $171.8600 | $97,943.01 |
| 5031010A | BRIDGE APPROACH SLAB (MAJOR) | 440 | SQYD | $359.9500 | $158,378.00 | $435.0000 | $191,400.00 | $323.4300 | $142,309.20 | $590.1500 | $259,666.00 |
| 5041000 | CONCRETE APPROACH PAVEMENT | 263.9 | SQYD | $175.7900 | $46,390.98 | $175.0000 | $46,182.50 | $159.5700 | $42,110.52 | $290.6500 | $76,702.54 |
| 5057000 | POLYESTER POLYMER CONCRETE WEARING SURFACE | 13,808 | SQYD | $81.9100 | $1,130,616.80 | $111.0000 | $1,532,688.00 | $107.0350 | $1,477,937.60 | $138.1000 | $1,906,884.80 |
| 6044011 | PIPE COLLAR, TYPE A | 1 | EA | $3,187.0300 | $3,187.03 | $1,955.0000 | $1,955.00 | $1,840.2000 | $1,840.20 | $1,047.5200 | $1,047.52 |
| 6046018A | 18 IN. SLOTTED DRAIN | 165 | LF | $262.2600 | $43,272.90 | $340.0000 | $56,100.00 | $320.7200 | $52,918.80 | $205.8600 | $33,966.90 |
| 6061060 | MGS GUARDRAIL | 838 | LF | $37.6900 | $31,584.22 | $29.0000 | $24,302.00 | $27.3400 | $22,910.92 | $33.8700 | $28,383.06 |
| 6061061 | MGS GUARDRAIL, 8 FT. POSTS, 6 FT. - 3 IN. SPACING | 1,638 | LF | $41.8800 | $68,599.44 | $35.0000 | $57,330.00 | $32.6000 | $53,398.80 | $37.6300 | $61,637.94 |
| 6061069 | MGS BRIDGE APPROACH TRANSITION SECTION (REGULAR/NO CURB) | 6 | EA | $4,786.5600 | $28,719.36 | $4,200.0000 | $25,200.00 | $3,953.8100 | $23,722.86 | $4,300.0000 | $25,800.00 |
| 6063014 | TYPE A CRASHWORTHY END TERMINAL (MASH) | 6 | EA | $4,188.2400 | $25,129.44 | $3,400.0000 | $20,400.00 | $3,180.9200 | $19,085.52 | $3,762.5000 | $22,575.00 |
| 6069903 | MISC. REMOVE AND REPLACE BARRIER CURB | 48 | LF | $474.1600 | $22,759.68 | $715.0000 | $34,320.00 | $928.1900 | $44,553.12 | $64.9600 | $3,118.08 |
| 6097000 | ROCK LINING | 2 | CUYD | $254.9000 | $509.80 | $670.0000 | $1,340.00 | $630.9300 | $1,261.86 | $455.3000 | $910.60 |
| 6113010 | FURNISHING TYPE 1 ROCK BLANKET | 20 | CUYD | $80.7700 | $1,615.40 | $106.0000 | $2,120.00 | $99.9000 | $1,998.00 | $97.1300 | $1,942.60 |
| 6113030 | PLACING TYPE 1 ROCK BLANKET | 20 | CUYD | $120.5700 | $2,411.40 | $62.0000 | $1,240.00 | $57.8400 | $1,156.80 | $167.6400 | $3,352.80 |
| 6122009 | IMPACT ATTENUATOR 45 MPH (SAND BARREL ARRAY) | 1 | EA | $4,188.2500 | $4,188.25 | $2,230.0000 | $2,230.00 | $1,735.0400 | $1,735.04 | $2,150.0000 | $2,150.00 |
| 6122014 | IMPACT ATTENUATOR 60 MPH (SAND BARREL ARRAY) | 2 | EA | $5,983.2000 | $11,966.40 | $3,122.0000 | $6,244.00 | $1,945.3600 | $3,890.72 | $3,010.0000 | $6,020.00 |
| 6122020 | REPLACEMENT SAND BARREL | 5 | EA | $478.6600 | $2,393.30 | $446.0000 | $2,230.00 | $341.7500 | $1,708.75 | $430.0000 | $2,150.00 |
| 6122040 | WORK ZONE CRASH CUSHION (NARROW) | 2 | EA | $9,333.7900 | $18,667.58 | $10,816.0000 | $21,632.00 | $7,446.4000 | $14,892.80 | $10,427.5000 | $20,855.00 |
| 6122041 | WORK ZONE CRASH CUSHION (NARROW) (RELOCATION) | 1 | EA | $2,153.9500 | $2,153.95 | $2,230.0000 | $2,230.00 | $1,085.5800 | $1,085.58 | $2,150.0000 | $2,150.00 |
| 6123001 | TRUCK MOUNTED ATTENUATOR (TMA) | 1 | LS | $25,129.4300 | $25,129.43 | $15,000.0000 | $15,000.00 | $20,000.0000 | $20,000.00 | $12,919.8200 | $12,919.82 |
| 6161005 | CONSTRUCTION SIGNS | 1,074 | SQFT | $5.9800 | $6,422.52 | $7.8000 | $8,377.20 | $5.2600 | $5,649.24 | $7.5300 | $8,087.22 |
| 6161025 | CHANNELIZER (TRIM-LINE) | 191 | EA | $19.1500 | $3,657.65 | $43.5000 | $8,308.50 | $16.8200 | $3,212.62 | $41.9300 | $8,008.63 |
| 6161030 | TYPE 3 MOVEABLE BARRICADE | 55 | EA | $113.6800 | $6,252.40 | $240.0000 | $13,200.00 | $99.9000 | $5,494.50 | $231.1300 | $12,712.15 |
| 6161033 | DIRECTION INDICATOR BARRICADE | 29 | EA | $77.7800 | $2,255.62 | $168.0000 | $4,872.00 | $68.3500 | $1,982.15 | $161.2500 | $4,676.25 |
| 6161040 | FLASHING ARROW PANEL | 2 | EA | $3,530.0900 | $7,060.18 | $5,020.0000 | $10,040.00 | $3,102.0600 | $6,204.12 | $4,837.5000 | $9,675.00 |
| 6161055 | SEQUENTIAL FLASHING WARNING LIGHT | 29 | EA | $65.8200 | $1,908.78 | $167.5000 | $4,857.50 | $57.8400 | $1,677.36 | $161.2500 | $4,676.25 |
| 6161070 | TUBULAR MARKER | 71 | EA | $101.7100 | $7,221.41 | $78.0000 | $5,538.00 | $89.3800 | $6,345.98 | $75.2500 | $5,342.75 |
| 6161098A | CHANGEABLE MESSAGE SIGN WITHOUT COMMUNICATION INTERFACE, CONTRACTOR FURNISHED / RETAINED | 4 | EA | $5,803.7100 | $23,214.84 | $12,850.0000 | $51,400.00 | $5,099.9900 | $20,399.96 | $12,362.5000 | $49,450.00 |
| 6173600D | TEMPORARY TRAFFIC BARRIER, CONTRACTOR FURNISHED / RETAINED | 1,546 | LF | $53.8500 | $83,252.10 | $30.2500 | $46,766.50 | $35.4700 | $54,836.62 | $29.0300 | $44,880.38 |
| 6173700B | TEMPORARY TRAFFIC BARRIER ANCHORED, CONTRACTOR FURNISHED / RETAINED | 1,740 | LF | $65.8200 | $114,526.80 | $33.5000 | $58,290.00 | $49.0000 | $85,260.00 | $32.2500 | $56,115.00 |
| 6181000 | MOBILIZATION | 1 | LS | $317,370.3400 | $317,370.34 | $692,000.0000 | $692,000.00 | $510,000.0000 | $510,000.00 | $331,000.0000 | $331,000.00 |
| 6181020 | ADDITIONAL MOBILIZATION FOR SEEDING | 1 | EA | $600.0000 | $600.00 | $600.0000 | $600.00 | $600.0000 | $600.00 | $600.0000 | $600.00 |
| 6200015 | PREFORMED THERMOPLASTIC PAVEMENT MARKING, 24 IN. WHITE | 112 | LF | $21.5400 | $2,412.48 | $36.0000 | $4,032.00 | $18.9300 | $2,120.16 | $34.4000 | $3,852.80 |
| 6200042A | PREFORMED THERMOPLASTIC PAVEMENT MARKING, 24 IN. X 36 IN., YIELD LINE TRIANGLE | 24 | EA | $41.8800 | $1,005.12 | $39.0000 | $936.00 | $36.8000 | $883.20 | $37.6300 | $903.12 |
| 6205902B | 6 IN. WHITE CLASS 2 PAVEMENT MARKING PAINT (25-MIL, TYPE L BEADS) | 23,593 | LF | $0.2800 | $6,606.04 | $0.3500 | $8,257.55 | $0.2400 | $5,662.32 | $0.3400 | $8,021.62 |
| 6205903B | 6 IN. YELLOW CLASS 2 PAVEMENT MARKING PAINT (25-MIL, TYPE L BEADS) | 16,303 | LF | $0.2800 | $4,564.84 | $0.3600 | $5,869.08 | $0.2400 | $3,912.72 | $0.3500 | $5,706.05 |
| 6205906B | 12 IN. WHITE CLASS 2 PAVEMENT MARKING PAINT (25-MIL, TYPE L BEADS) | 757 | LF | $0.5900 | $446.63 | $1.1700 | $885.69 | $0.5200 | $393.64 | $1.1300 | $855.41 |
| 6206124B | 24 IN. WHITE CLASS 1 PAVEMENT MARKING PAINT (18-MIL, TYPE P BEADS) | 128 | LF | $0.3000 | $38.40 | $13.3800 | $1,712.64 | $0.2600 | $33.28 | $12.9000 | $1,651.20 |
| 6207001 | PAVEMENT MARKING REMOVAL | 46,118 | LF | $0.5900 | $27,209.62 | $0.3300 | $15,218.94 | $0.5200 | $23,981.36 | $0.3300 | $15,218.94 |
| 6208076 | 4 IN TEMPORARY PAVEMENT MARKING PAINT | 42,406 | LF | $0.1700 | $7,209.02 | $0.3300 | $13,993.98 | $0.1500 | $6,360.90 | $0.3300 | $13,993.98 |
| 6214600A | FLOWABLE BACKFILL | 10 | CUYD | $590.3700 | $5,903.70 | $1,200.0000 | $12,000.00 | $910.9200 | $9,109.20 | $836.1500 | $8,361.50 |
| 6240103A | PERMANENT EROSION CONTROL GEOTEXTILE | 30 | SQYD | $2.9900 | $89.70 | $33.5000 | $1,005.00 | $31.5500 | $946.50 | $10.0000 | $300.00 |
| 6274000 | CONTRACTOR FURNISHED SURVEYING AND STAKING | 1 | LS | $14,359.6800 | $14,359.68 | $13,380.0000 | $13,380.00 | $12,618.5300 | $12,618.53 | $13,750.0000 | $13,750.00 |
| 7033013 | PENETRATING CONCRETE SEALER | 2,496 | SY | $7.3800 | $18,420.48 | $40.0000 | $99,840.00 | $12.0000 | $29,952.00 | $27.1300 | $67,716.48 |
| 7034214 | CLASS B-2 CONCRETE | 23.2 | CUYD | $2,852.3500 | $66,174.52 | $2,440.0000 | $56,608.00 | $8,019.5600 | $186,053.80 | $5,800.0000 | $134,560.00 |
| 7039903 | MISC. BRIDGE BARRIER REPAIR | 10 | LF | $352.5700 | $3,525.70 | $280.0000 | $2,800.00 | $1,406.4800 | $14,064.80 | $2,252.9400 | $22,529.40 |
| 7040102 | SUBSTRUCTURE REPAIR (UNFORMED) | 10 | SQFT | $156.3000 | $1,563.00 | $335.0000 | $3,350.00 | $656.3100 | $6,563.10 | $336.3900 | $3,363.90 |
| 7040103 | SUPERSTRUCTURE REPAIR (UNFORMED) | 310 | SQFT | $156.6300 | $48,555.30 | $150.0000 | $46,500.00 | $220.4800 | $68,348.80 | $336.3700 | $104,274.70 |
| 7040104 | HALF-SOLE REPAIR | 350 | SQFT | $40.9500 | $14,332.50 | $110.0000 | $38,500.00 | $116.4200 | $40,747.00 | $170.2800 | $59,598.00 |
| 7040164 | FIBER REINFORCED POLYMER WRAP | 310 | SF | $101.3000 | $31,403.00 | $52.0000 | $16,120.00 | $278.9500 | $86,474.50 | $174.6200 | $54,132.20 |
| 7101000 | REINFORCING STEEL (EPOXY COATED) | 2,820 | LB | $2.3900 | $6,739.80 | $2.0000 | $5,640.00 | $3.3900 | $9,559.80 | $6.9200 | $19,514.40 |
| 7110100 | PROTECTIVE COATING - CONCRETE BENTS AND PIERS (URETHANE) | 2 | LS | $23,932.7900 | $47,865.58 | $22,250.0000 | $44,500.00 | $21,030.8800 | $42,061.76 | $22,000.0000 | $44,000.00 |
| 7120900 | EXPANSION DEVICE (FINGER PLATE) | 156 | LF | $1,937.7200 | $302,284.32 | $1,950.0000 | $304,200.00 | $2,495.7300 | $389,333.88 | $2,000.0000 | $312,000.00 |
| 7125102 | SURFACE PREPARATION FOR APPLYING EPOXY-MASTIC PRIMER | 1 | LS | $4,786.5600 | $4,786.56 | $4,500.0000 | $4,500.00 | $4,206.1800 | $4,206.18 | $4,400.0000 | $4,400.00 |
| 7125960 | ALUMINUM EPOXY-MASTIC PRIMER | 1 | LS | $1,196.6400 | $1,196.64 | $1,150.0000 | $1,150.00 | $1,051.5400 | $1,051.54 | $1,100.0000 | $1,100.00 |
| 7172001 | STRIP SEAL EXPANSION JOINT SYSTEM | 78 | LF | $587.3500 | $45,813.30 | $705.0000 | $54,990.00 | $750.3400 | $58,526.52 | $745.2700 | $58,131.06 |
| 7261018 | 18 IN. PIPE GROUP A | 314 | LF | $92.0300 | $28,897.42 | $123.0000 | $38,622.00 | $115.6700 | $36,320.38 | $104.0700 | $32,677.98 |
| 7311032 | PRECAST CONCRETE DROP INLET 3 FT X 2 FT | 10 | FT | $1,196.6400 | $11,966.40 | $1,785.0000 | $17,850.00 | $1,682.4700 | $16,824.70 | $2,384.6900 | $23,846.90 |
| 7320618A | 18 IN. OR ALLOWED SUBSTITUTE GROUP A FLARED END SECTION | 1 | EA | $677.7800 | $677.78 | $2,800.0000 | $2,800.00 | $2,628.8700 | $2,628.87 | $1,202.3900 | $1,202.39 |
| 8025006 | MULCHING | 5.5 | ACRE | $1,675.3000 | $9,214.15 | $1,784.0000 | $9,812.00 | $1,314.4300 | $7,229.37 | $1,375.0000 | $7,562.50 |
| 8051000A | SEEDING - COOL SEASON GRASSES | 3.9 | ACRE | $3,230.9300 | $12,600.63 | $2,490.0000 | $9,711.00 | $2,260.8200 | $8,817.20 | $2,365.0000 | $9,223.50 |
| 8061006 | ALTERNATE DITCH CHECK | 5,664 | LF | $8.3800 | $47,464.32 | $10.0000 | $56,640.00 | $15.3500 | $86,942.40 | $6.1600 | $34,890.24 |
| 8061016 | SEDIMENT REMOVAL | 219 | CUYD | $18.7800 | $4,112.82 | $22.5000 | $4,927.50 | $21.0300 | $4,605.57 | $5.0000 | $1,095.00 |
| 8061017 | TEMPORARY SEEDING | 1.6 | ACRE | $1,794.9600 | $2,871.94 | $2,152.0000 | $3,443.20 | $1,493.1900 | $2,389.10 | $1,562.0000 | $2,499.20 |
| 8061019 | SILT FENCE | 6,143 | LF | $3.3500 | $20,579.05 | $4.3500 | $26,722.05 | $2.9100 | $17,876.13 | $1.8600 | $11,425.98 |
| 9029902 | MISC. OPTIONAL TRAFFIC SIGNAL DETECTORS | 1 | EA | $6,461.8600 | $6,461.86 | $5,600.0000 | $5,600.00 | $5,257.7200 | $5,257.72 | $5,500.0000 | $5,500.00 |
| 9031270A | 2 IN. PSST POST - 12 GA. | 70 | LF | $41.8800 | $2,931.60 | $19.5000 | $1,365.00 | $18.4000 | $1,288.00 | $37.6300 | $2,634.10 |
| 9031274 | CONCRETE POST ANCHOR FOR 2 IN. PSST. - 7 GA. | 5 | EA | $269.2400 | $1,346.20 | $350.0000 | $1,750.00 | $330.1800 | $1,650.90 | $241.8800 | $1,209.40 |
Source: public Missouri DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.