Mississippi DOT · Bid Tabulation
Contract 108954301
Thin Lift Overlay approximately 8.5 miles of SR 514 from SR 513 to SR 145, approximately 0.5 miles of the SR 513 Spur (SR952) from US 11 to US 11, approximately 12.5 miles of SR 513 from SR 145 to the SR 513 Spur, and approximately 5.8 miles of SR 513 fro
- County
- Clarke & Jasper
- District
- 6
- Letting
- June 23, 2026
- Bidders
- 3
Apparent low bid
Dunn Roadbuilders, LLC
$7,234,154.95
Other bidders
Walters Construction Co., Inc.
$7,486,346.95
APAC - Mississippi, Inc.
$8,054,272.26
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | Dunn Roadbuilders, LLC $7,234,154.95 | Walters Construction Co., Inc. $7,486,346.95 | APAC - Mississippi, Inc. $8,054,272.26 | |||
|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 201-D001 | Random Clearing | 1,283 | STA | $537.0000 | $688,971.00 | $489.0000 | $627,387.00 | $455.9600 | $584,996.68 |
| 202-B006 | Removal of Asphalt Paved Shoulders, All Depths | 3,331 | SY | $19.0000 | $63,289.00 | $38.0000 | $126,578.00 | $34.2000 | $113,920.20 |
| 202-B136 | Removal of Guard Rail | 2,595 | LF | $11.0000 | $28,545.00 | $8.0000 | $20,760.00 | $7.2500 | $18,813.75 |
| 202-B158 | Removal of Guard Rail, Including Rails, Posts and Terminal Ends | 915 | LF | $13.6000 | $12,444.00 | $11.0000 | $10,065.00 | $9.3300 | $8,536.95 |
| 202-B188 | Removal of Pavement, All Types and Depths | 6,140 | SY | $12.4000 | $76,136.00 | $8.0000 | $49,120.00 | $45.0000 | $276,300.00 |
| 202-B240 | Removal of Traffic Stripe | 10,960 | LF | $2.5000 | $27,400.00 | $2.3000 | $25,208.00 | $4.0000 | $43,840.00 |
| 304-F002 | Size 610 Crushed Stone Base | 10,620 | TON | - | - | - | - | $95.2900 | $1,011,979.80 |
| 304-F003 | Size 825B Crushed Stone Base | 10,620 | TON | $76.0000 | $807,120.00 | $82.0000 | $870,840.00 | - | - |
| 406-D001 | Fine Milling of Bituminous Pavement, All Depths | 20,409 | SY | $4.0000 | $81,636.00 | $1.7500 | $35,715.75 | $3.5600 | $72,656.04 |
| 423-A001 | Rumble Strips, Ground In | 57 | MI | $347.0000 | $19,779.00 | $322.5000 | $18,382.50 | $300.0000 | $17,100.00 |
| 503-C010 | Saw Cut, Full Depth | 3,255 | LF | $7.0000 | $22,785.00 | $9.0000 | $29,295.00 | $8.2900 | $26,983.95 |
| 606-B003 | Guard Rail, Class A, Type 1, 'W' Beam, Metal Post | 3,510 | LF | $37.0000 | $129,870.00 | $32.0000 | $112,320.00 | $30.5700 | $107,300.70 |
| 606-D001 | Guard Rail, Bridge End Section | 24 | EA | $3,707.0000 | $88,968.00 | $3,300.0000 | $79,200.00 | $3,103.6300 | $74,487.12 |
| 606-E001 | Guard Rail, Terminal End Section | 16 | EA | $4,641.0000 | $74,256.00 | $4,200.0000 | $67,200.00 | $3,886.0100 | $62,176.16 |
| 606-E007 | Guard Rail, Terminal End Section, Non-Flared | 12 | EA | $4,765.0000 | $57,180.00 | $4,200.0000 | $50,400.00 | $3,989.6400 | $47,875.68 |
| 618-B001 | Additional Construction Signs | 4 | SF | $10.0000 | $40.00 | $10.0000 | $40.00 | $10.0000 | $40.00 |
| 619-A1001 | Temporary Traffic Stripe, Continuous White | 54 | MI | $1,238.0000 | $66,852.00 | $1,100.0000 | $59,400.00 | $1,000.0000 | $54,000.00 |
| 619-A2001 | Temporary Traffic Stripe, Continuous Yellow | 53 | MI | $1,238.0000 | $65,614.00 | $1,100.0000 | $58,300.00 | $1,000.0000 | $53,000.00 |
| 619-A4002 | Temporary Traffic Stripe, Skip Yellow | 16 | MI | $1,238.0000 | $19,808.00 | $1,100.0000 | $17,600.00 | $1,000.0000 | $16,000.00 |
| 619-A5001 | Temporary Traffic Stripe, Detail | 12,499 | LF | $0.0500 | $624.95 | $0.0500 | $624.95 | $0.0500 | $624.95 |
| 619-A6002 | Temporary Traffic Stripe, Legend | 2,047 | LF | $1.0000 | $2,047.00 | $1.1500 | $2,354.05 | $1.0000 | $2,047.00 |
| 620-A001 | Mobilization | 1 | LS | $140,000.0000 | $140,000.00 | $261,340.0000 | $261,340.00 | $399,817.1800 | $399,817.18 |
| 630-F006 | Delineators, Guard Rail, White | 105 | EA | $35.0000 | $3,675.00 | $30.0000 | $3,150.00 | $29.0200 | $3,047.10 |
| 630-G005 | Type 3 Object Markers, OM-3R or OM-3L, Post Mounted | 76 | EA | $105.0000 | $7,980.00 | $95.0000 | $7,220.00 | $88.0800 | $6,694.08 |
| 630-G006 | Type 3 Object Markers, OM-3R or OM-3L, 2 Markers Per Post, Post Mounted | 130 | EA | $161.0000 | $20,930.00 | $140.0000 | $18,200.00 | $134.7200 | $17,513.60 |
| 907-403-A006 | 19-mm, ST, Asphalt Pavement | 3,372 | TON | $148.0000 | $499,056.00 | $152.0000 | $512,544.00 | $171.1500 | $577,117.80 |
| 907-407-A001 | Asphalt for Tack Coat | 40,450 | GAL | $4.0000 | $161,800.00 | $5.0000 | $202,250.00 | $4.0400 | $163,418.00 |
| 907-411-A001 | Ultra Thin Asphalt Pavement | 20,120 | TON | $138.5000 | $2,786,620.00 | $146.0000 | $2,937,520.00 | $141.4400 | $2,845,772.80 |
| 907-618-A001 | Maintenance of Traffic | 1 | LS | $125,000.0000 | $125,000.00 | $205,000.0000 | $205,000.00 | $218,434.5600 | $218,434.56 |
| 907-626-C014 | 6" Thermoplastic Edge Stripe, Continuous White | 54 | MI | $8,045.0000 | $434,430.00 | $7,500.0000 | $405,000.00 | $8,400.0000 | $453,600.00 |
| 907-626-D005 | 6" Thermoplastic Traffic Stripe, Skip Yellow | 16 | MI | $4,332.0000 | $69,312.00 | $3,800.0000 | $60,800.00 | $4,000.0000 | $64,000.00 |
| 907-626-E005 | 6" Thermoplastic Traffic Stripe, Continuous Yellow | 53 | MI | $8,045.0000 | $426,385.00 | $7,200.0000 | $381,600.00 | $8,200.0000 | $434,600.00 |
| 907-626-G004 | Thermoplastic Detail Stripe, White | 4,727 | LF | $4.0000 | $18,908.00 | $3.3000 | $15,599.10 | $4.0000 | $18,908.00 |
| 907-626-G005 | Thermoplastic Detail Stripe, Yellow | 3,784 | LF | $4.0000 | $15,136.00 | $3.3000 | $12,487.20 | $3.9500 | $14,946.80 |
| 907-626-H009 | Thermoplastic Legend, White | 260 | SF | $13.0000 | $3,380.00 | $11.0000 | $2,860.00 | $43.0000 | $11,180.00 |
| 907-626-H010 | Thermoplastic Legend, White | 4,858 | LF | $5.0000 | $24,290.00 | $4.3000 | $20,889.40 | $8.0000 | $38,864.00 |
| 907-627-J001 | Two-Way Clear Reflective High Performance Raised Markers | 2,174 | EA | $9.0000 | $19,566.00 | $7.7500 | $16,848.50 | $10.0000 | $21,740.00 |
| 907-627-L001 | Two-Way Yellow Reflective High Performance Raised Markers | 3,860 | EA | $9.0000 | $34,740.00 | $7.7500 | $29,915.00 | $10.0000 | $38,600.00 |
| 907-627-M001 | One-Way Clear Reflective High Performance Raised Markers | 3,591 | EA | $8.0000 | $28,728.00 | $7.7500 | $27,830.25 | $10.0000 | $35,910.00 |
| 907-628-H005 | 6" High Performance Cold Plastic Traffic Stripe, Continuous White | 4,270 | LF | $9.0000 | $38,430.00 | $7.7500 | $33,092.50 | $8.0000 | $34,160.00 |
| 907-628-I004 | 6" High Performance Cold Plastic Traffic Stripe, Skip Yellow | 1,474 | LF | $8.0000 | $11,792.00 | $7.7500 | $11,423.50 | $8.0000 | $11,792.00 |
| 907-628-J003 | 6" High Performance Cold Plastic Traffic Stripe, Continuous Yellow | 2,579 | LF | $8.0000 | $20,632.00 | $7.7500 | $19,987.25 | $8.0000 | $20,632.00 |
| 907-899-A001 | Railway-Highway Provisions | 1 | LS | $10,000.0000 | $10,000.00 | $40,000.0000 | $40,000.00 | $30,845.3600 | $30,845.36 |
Source: public Mississippi DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.