MS Mississippi DOT · Bid Tabulation

Contract 109064301

Roundabout on US 51 at Green T Road

County
DeSoto
District
2
Letting
June 23, 2026
Bidders
6
Apparent low bid Talbot Brothers Contracting Co., Inc. $4,340,877.23
Other bidders Phillips Contracting Co., Inc. $4,894,331.05 Cook & Son, LLC $4,978,347.18 Ste-Bil Grading Inc. $5,038,731.00 Century Construction Group, Inc. $5,638,644.39 Xcavators, Inc. $5,866,014.55

Bid Items - unit price and extension by bidder

Item Description Qty UOM Talbot Brothers Contracting Co., Inc. $4,340,877.23 Phillips Contracting Co., Inc. $4,894,331.05 Cook & Son, LLC $4,978,347.18 Ste-Bil Grading Inc. $5,038,731.00 Century Construction Group, Inc. $5,638,644.39 Xcavators, Inc. $5,866,014.55
Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension
201-B001 Clearing and Grubbing 1 ACRE $15,000.0000 $15,000.00 $20,000.0000 $20,000.00 $10,000.0000 $10,000.00 $20,000.0000 $20,000.00 $1,500.0000 $1,500.00 $3,500.0000 $3,500.00
202-B007 Removal of Asphalt Pavement, All Depths 1,156 SY $20.0000 $23,120.00 $21.0000 $24,276.00 $12.0000 $13,872.00 $25.0000 $28,900.00 $20.0000 $23,120.00 $18.5000 $21,386.00
202-B052 Removal of Concrete Driveways, All Depths 318 SY $20.0000 $6,360.00 $25.0000 $7,950.00 $20.0000 $6,360.00 $25.0000 $7,950.00 $35.0000 $11,130.00 $27.0000 $8,586.00
202-B059 Removal of Concrete Median & Island Pavement, All Depths 262 SY $20.0000 $5,240.00 $25.0000 $6,550.00 $20.0000 $5,240.00 $25.0000 $6,550.00 $30.0000 $7,860.00 $30.0000 $7,860.00
202-B063 Removal of Concrete Paved Ditch 751 SY $20.0000 $15,020.00 $25.0000 $18,775.00 $15.0000 $11,265.00 $25.0000 $18,775.00 $18.0000 $13,518.00 $17.0000 $12,767.00
202-B089 Removal of Curb &/or Curb and Gutter, All Types 1,138 LF $15.0000 $17,070.00 $15.0000 $17,070.00 $20.0000 $22,760.00 $25.0000 $28,450.00 $11.7500 $13,371.50 $11.2500 $12,802.50
202-B126 Removal of Fence, All Types 973 LF $5.0000 $4,865.00 $9.0000 $8,757.00 $10.0000 $9,730.00 $10.0000 $9,730.00 $10.0000 $9,730.00 $8.5000 $8,270.50
202-B129 Removal of Flared End Section, All Sizes 7 EA $500.0000 $3,500.00 $885.0000 $6,195.00 $1,500.0000 $10,500.00 $1,000.0000 $7,000.00 $1,300.0000 $9,100.00 $1,225.0000 $8,575.00
202-B163 Removal of Inlet Tops 4 EA $1,000.0000 $4,000.00 $2,500.0000 $10,000.00 $1,500.0000 $6,000.00 $2,500.0000 $10,000.00 $3,000.0000 $12,000.00 $500.0000 $2,000.00
202-B191 Removal of Pipe, 8" And Above 357 LF $20.0000 $7,140.00 $50.0000 $17,850.00 $10.0000 $3,570.00 $25.0000 $8,925.00 $30.0000 $10,710.00 $36.0000 $12,852.00
202-B215 Removal of Sign Including Post & Footing 13 EA $100.0000 $1,300.00 $118.0000 $1,534.00 $100.0000 $1,300.00 $100.0000 $1,300.00 $100.0000 $1,300.00 $130.0000 $1,690.00
202-B240 Removal of Traffic Stripe 2,000 LF $5.0000 $10,000.00 $5.6000 $11,200.00 $5.0000 $10,000.00 $5.0000 $10,000.00 $5.0000 $10,000.00 $6.5000 $13,000.00
203-A001 Unclassified Excavation, FM, AH 5,225 CY $15.0000 $78,375.00 $18.0000 $94,050.00 $35.0000 $182,875.00 $20.0000 $104,500.00 $15.0000 $78,375.00 $22.5000 $117,562.50
203-EX020 Borrow Excavation, AH, FME, Class B9 10,245 CY $22.0000 $225,390.00 $27.1000 $277,639.50 $30.0000 $307,350.00 $25.0000 $256,125.00 $25.0000 $256,125.00 $22.5000 $230,512.50
203-G001 Excess Excavation, FM, AH 1,000 CY $15.0000 $15,000.00 $25.0000 $25,000.00 $30.0000 $30,000.00 $20.0000 $20,000.00 $17.7500 $17,750.00 $22.5000 $22,500.00
206-A001 Structure Excavation 543 CY $25.0000 $13,575.00 $25.0000 $13,575.00 $50.0000 $27,150.00 $25.0000 $13,575.00 $30.0000 $16,290.00 $40.0000 $21,720.00
206-B001 Select Material for Undercuts, Contractor Furnished, FM 26 CY $100.0000 $2,600.00 $30.0000 $780.00 $50.0000 $1,300.00 $150.0000 $3,900.00 $50.0000 $1,300.00 $125.0000 $3,250.00
209-A005 Geotextile Stabilization, Type V, Non-Woven 13,010 SY $5.0000 $65,050.00 $3.0000 $39,030.00 $2.5000 $32,525.00 $3.0000 $39,030.00 $3.2700 $42,542.70 $3.8500 $50,088.50
213-C001 Superphosphate 3 TON $800.0000 $2,400.00 $950.0000 $2,850.00 $800.0000 $2,400.00 $1,000.0000 $3,000.00 $800.0000 $2,400.00 $860.0000 $2,580.00
216-A001 Solid Sodding 330 SY $8.0000 $2,640.00 $9.5000 $3,135.00 $8.0000 $2,640.00 $10.0000 $3,300.00 $10.0000 $3,300.00 $10.0000 $3,300.00
217-A001 Ditch Liner 163 SY $5.0000 $815.00 $6.0000 $978.00 $5.0000 $815.00 $4.0000 $652.00 $5.8900 $960.07 $10.0000 $1,630.00
219-A001 Watering 7 KGAL $20.0000 $140.00 $20.0000 $140.00 $20.0000 $140.00 $20.0000 $140.00 $20.0000 $140.00 $20.0000 $140.00
220-A001 Insect Pest Control 3 ACRE $30.0000 $90.00 $30.0000 $90.00 $30.0000 $90.00 $30.0000 $90.00 $30.0000 $90.00 $30.0000 $90.00
221-A001 Concrete Paved Ditch 73 CY $900.0000 $65,700.00 $800.0000 $58,400.00 $800.0000 $58,400.00 $850.0000 $62,050.00 $1,130.0000 $82,490.00 $1,300.0000 $94,900.00
223-A001 Mowing 18 ACRE $70.0000 $1,260.00 $70.0000 $1,260.00 $70.0000 $1,260.00 $70.0000 $1,260.00 $70.0000 $1,260.00 $70.0000 $1,260.00
224-A001 Soil Reinforcing Mat 201 SY $8.0000 $1,608.00 $9.5000 $1,909.50 $8.0000 $1,608.00 $4.0000 $804.00 $9.4100 $1,891.41 $19.7500 $3,969.75
225-A001 Grassing 6 ACRE $2,800.0000 $16,800.00 $3,300.0000 $19,800.00 $2,800.0000 $16,800.00 $2,000.0000 $12,000.00 $3,293.8100 $19,762.86 $1,550.0000 $9,300.00
225-B001 Agricultural Limestone 12 TON $250.0000 $3,000.00 $295.0000 $3,540.00 $250.0000 $3,000.00 $200.0000 $2,400.00 $250.0000 $3,000.00 $160.0000 $1,920.00
225-C001 Mulch, Vegetative Mulch 12 TON $250.0000 $3,000.00 $295.0000 $3,540.00 $250.0000 $3,000.00 $200.0000 $2,400.00 $294.1000 $3,529.20 $580.0000 $6,960.00
226-A001 Temporary Grassing 6 ACRE $1,750.0000 $10,500.00 $2,060.0000 $12,360.00 $1,750.0000 $10,500.00 $2,000.0000 $12,000.00 $1,750.0000 $10,500.00 $1,150.0000 $6,900.00
237-A002 Wattles, 20" 800 LF $8.0000 $6,400.00 $9.5000 $7,600.00 $8.0000 $6,400.00 $10.0000 $8,000.00 $8.0000 $6,400.00 $6.2500 $5,000.00
239-A001 Temporary Slope Drains 60 LF $12.0000 $720.00 $25.0000 $1,500.00 $50.0000 $3,000.00 $1.0000 $60.00 $15.0000 $900.00 $50.0000 $3,000.00
245-A001 Silt Dike 400 LF $12.0000 $4,800.00 $14.2500 $5,700.00 $12.0000 $4,800.00 $1.0000 $400.00 $12.0000 $4,800.00 $21.2500 $8,500.00
246-B001 Rockbags 600 EA $15.0000 $9,000.00 $17.7500 $10,650.00 $15.0000 $9,000.00 $1.0000 $600.00 $15.0000 $9,000.00 $8.3000 $4,980.00
247-A001 Temporary Stream Diversion 1 EA $1,500.0000 $1,500.00 $15,000.0000 $15,000.00 $35,000.0000 $35,000.00 $5,000.0000 $5,000.00 $5,000.0000 $5,000.00 $32,500.0000 $32,500.00
304-B004 Granular Material, Class 5, Group D 900 TON $54.0000 $48,600.00 $66.0000 $59,400.00 $61.3200 $55,188.00 $60.0000 $54,000.00 $65.0000 $58,500.00 $60.0000 $54,000.00
304-F001 3/4" and Down Crushed Stone Base 6,400 TON - - - - $75.0000 $480,000.00 - - - - $70.2500 $449,600.00
304-F002 Size 610 Crushed Stone Base 6,400 TON $66.9400 $428,416.00 $67.0000 $428,800.00 - - $65.0000 $416,000.00 $80.0000 $512,000.00 - -
406-D001 Fine Milling of Bituminous Pavement, All Depths 1,990 SY $20.0000 $39,800.00 $10.1000 $20,099.00 $5.7500 $11,442.50 $10.0000 $19,900.00 $20.0000 $39,800.00 $10.5000 $20,895.00
503-C010 Saw Cut, Full Depth 855 LF $10.0000 $8,550.00 $15.0000 $12,825.00 $12.0000 $10,260.00 $25.0000 $21,375.00 $9.0000 $7,695.00 $32.5000 $27,787.50
602-A001 Reinforcing Steel 17,572 LBS $2.0000 $35,144.00 $1.5000 $26,358.00 $1.5000 $26,358.00 $3.0000 $52,716.00 $1.9000 $33,386.80 $4.5000 $79,074.00
603-ALT003 18" Type A Alternate Pipe 80 LF $50.0000 $4,000.00 $124.5000 $9,960.00 $50.0000 $4,000.00 $75.0000 $6,000.00 $90.0000 $7,200.00 $90.0000 $7,200.00
603-ALT006 24" Type A Alternate Pipe 64 LF $70.0000 $4,480.00 $140.0000 $8,960.00 $75.0000 $4,800.00 $85.0000 $5,440.00 $105.2500 $6,736.00 $120.0000 $7,680.00
603-CA011 18" Reinforced Concrete Pipe, Class III 712 LF $55.0000 $39,160.00 $124.5000 $88,644.00 $75.0000 $53,400.00 $100.0000 $71,200.00 $75.2500 $53,578.00 $87.2500 $62,122.00
603-CA026 24" Reinforced Concrete Pipe, Class III 216 LF $72.0000 $15,552.00 $140.0000 $30,240.00 $100.0000 $21,600.00 $100.0000 $21,600.00 $105.0000 $22,680.00 $90.0000 $19,440.00
603-CA038 24" Reinforced Concrete Pipe, Class V, Jacked or Bored 64 LF $772.7700 $49,457.28 $950.0000 $60,800.00 $1,145.0000 $73,280.00 $800.0000 $51,200.00 $1,005.0000 $64,320.00 $1,600.0000 $102,400.00
603-CA055 36" Reinforced Concrete Pipe, Class III 24 LF $139.0000 $3,336.00 $182.5000 $4,380.00 $160.0000 $3,840.00 $200.0000 $4,800.00 $150.0000 $3,600.00 $355.0000 $8,520.00
603-CA065 36" Reinforced Concrete Pipe, Class V, Jacked or Bored 64 LF $1,013.6100 $64,871.04 $1,250.0000 $80,000.00 $1,412.0000 $90,368.00 $1,050.0000 $67,200.00 $1,300.0000 $83,200.00 $1,925.0000 $123,200.00
603-CA076 48" Reinforced Concrete Pipe, Class III 168 LF $220.0000 $36,960.00 $260.0000 $43,680.00 $225.0000 $37,800.00 $400.0000 $67,200.00 $190.0000 $31,920.00 $192.0000 $32,256.00
603-CB003 18" Reinforced Concrete End Section 5 EA $950.0000 $4,750.00 $1,500.0000 $7,500.00 $1,100.0000 $5,500.00 $2,000.0000 $10,000.00 $2,300.0000 $11,500.00 $1,350.0000 $6,750.00
603-CB004 24" Reinforced Concrete End Section 4 EA $1,200.0000 $4,800.00 $1,700.0000 $6,800.00 $1,500.0000 $6,000.00 $2,500.0000 $10,000.00 $2,350.0000 $9,400.00 $2,350.0000 $9,400.00
603-CB006 36" Reinforced Concrete End Section 1 EA $2,000.0000 $2,000.00 $2,200.0000 $2,200.00 $2,050.0000 $2,050.00 $3,000.0000 $3,000.00 $3,000.0000 $3,000.00 $2,700.0000 $2,700.00
603-CB008 48" Reinforced Concrete End Section 3 EA $3,500.0000 $10,500.00 $3,300.0000 $9,900.00 $4,000.0000 $12,000.00 $5,000.0000 $15,000.00 $3,500.0000 $10,500.00 $4,000.0000 $12,000.00
603-CE002 22" x 13" Concrete Arch Pipe, Class A III 24 LF $82.0000 $1,968.00 $141.5000 $3,396.00 $85.0000 $2,040.00 $120.0000 $2,880.00 $110.0000 $2,640.00 $330.0000 $7,920.00
604-A001 Castings 1,343 LBS $8.0000 $10,744.00 $5.0000 $6,715.00 $5.0000 $6,715.00 $8.0000 $10,744.00 $10.0000 $13,430.00 $13.0000 $17,459.00
604-B001 Gratings 391 LBS $8.0000 $3,128.00 $5.0000 $1,955.00 $5.0000 $1,955.00 $8.0000 $3,128.00 $10.0000 $3,910.00 $13.0000 $5,083.00
609-B002 Concrete Curb, Header 174 LF $52.0000 $9,048.00 $72.0000 $12,528.00 $40.0000 $6,960.00 $75.0000 $13,050.00 $50.0000 $8,700.00 $67.6000 $11,762.40
609-B003 Concrete Curb, Special Design 377 LF $71.0000 $26,767.00 $63.0000 $23,751.00 $40.0000 $15,080.00 $75.0000 $28,275.00 $50.0000 $18,850.00 $92.3000 $34,797.10
609-C001 Concrete Integral Curb, Type 1 274 LF $32.0000 $8,768.00 $63.0000 $17,262.00 $40.0000 $10,960.00 $50.0000 $13,700.00 $50.0000 $13,700.00 $41.6000 $11,398.40
609-D004 Combination Concrete Curb and Gutter Type 2 Modified 69 LF $54.5000 $3,760.50 $63.0000 $4,347.00 $40.0000 $2,760.00 $75.0000 $5,175.00 $50.0000 $3,450.00 $70.8500 $4,888.65
609-D007 Combination Concrete Curb and Gutter Type 3 Modified 5,108 LF $37.5000 $191,550.00 $49.0000 $250,292.00 $40.0000 $204,320.00 $40.0000 $204,320.00 $50.0000 $255,400.00 $48.7500 $249,015.00
612-B001 Flowable Fill, Non-Excavatable 15 CY $550.0000 $8,250.00 $750.0000 $11,250.00 $600.0000 $9,000.00 $400.0000 $6,000.00 $325.0000 $4,875.00 $685.0000 $10,275.00
614-B001 Concrete Driveway, With Reinforcement 1,126 SY $103.5000 $116,541.00 $112.7500 $126,956.50 $90.0000 $101,340.00 $120.0000 $135,120.00 $140.0000 $157,640.00 $134.5000 $151,447.00
616-A003 Concrete Median and/or Island Pavement, 12-inch 497 SY $170.5000 $84,738.50 $149.0000 $74,053.00 $110.0000 $54,670.00 $200.0000 $99,400.00 $175.0000 $86,975.00 $220.0000 $109,340.00
617-A001 Right-of-Way Marker 15 EA $400.0000 $6,000.00 $500.0000 $7,500.00 $250.0000 $3,750.00 $400.0000 $6,000.00 $500.0000 $7,500.00 $390.0000 $5,850.00
619-A1001 Temporary Traffic Stripe, Continuous White 5 MI $3,000.0000 $15,000.00 $3,350.0000 $16,750.00 $3,000.0000 $15,000.00 $3,000.0000 $15,000.00 $3,000.0000 $15,000.00 $3,900.0000 $19,500.00
619-A2001 Temporary Traffic Stripe, Continuous Yellow 4 MI $3,000.0000 $12,000.00 $3,350.0000 $13,400.00 $3,000.0000 $12,000.00 $3,000.0000 $12,000.00 $3,000.0000 $12,000.00 $3,900.0000 $15,600.00
619-A5001 Temporary Traffic Stripe, Detail 13,577 LF $0.7500 $10,182.75 $0.8500 $11,540.45 $0.7500 $10,182.75 $1.0000 $13,577.00 $0.7500 $10,182.75 $1.0000 $13,577.00
619-A6001 Temporary Traffic Stripe, Legend 699 SF $2.0000 $1,398.00 $2.2500 $1,572.75 $2.0000 $1,398.00 $3.0000 $2,097.00 $2.0000 $1,398.00 $2.6000 $1,817.40
619-A6002 Temporary Traffic Stripe, Legend 645 LF $1.0000 $645.00 $1.1000 $709.50 $1.0000 $645.00 $1.0000 $645.00 $1.0000 $645.00 $1.3000 $838.50
619-D1001 Standard Roadside Construction Signs, Less than 10 Square Feet 235 SF $7.0000 $1,645.00 $7.8000 $1,833.00 $7.0000 $1,645.00 $10.0000 $2,350.00 $8.2500 $1,938.75 $9.1000 $2,138.50
619-D2001 Standard Roadside Construction Signs, 10 Square Feet or More 596 SF $7.0000 $4,172.00 $7.8000 $4,648.80 $7.0000 $4,172.00 $7.0000 $4,172.00 $8.2500 $4,917.00 $9.1000 $5,423.60
619-G4001 Barricades, Type III, Double Faced 36 LF $16.0000 $576.00 $17.8000 $640.80 $16.0000 $576.00 $16.0000 $576.00 $20.0000 $720.00 $20.8000 $748.80
619-G4005 Barricades, Type III, Single Faced 192 LF $14.0000 $2,688.00 $15.6000 $2,995.20 $14.0000 $2,688.00 $15.0000 $2,880.00 $16.5000 $3,168.00 $18.2000 $3,494.40
619-G5001 Free Standing Plastic Drums 155 EA $40.0000 $6,200.00 $45.0000 $6,975.00 $40.0000 $6,200.00 $80.0000 $12,400.00 $47.0000 $7,285.00 $52.0000 $8,060.00
619-G7001 Warning Lights, Type "B" 8 EA $100.0000 $800.00 $112.0000 $896.00 $100.0000 $800.00 $200.0000 $1,600.00 $115.0000 $920.00 $130.0000 $1,040.00
620-A001 Mobilization 1 LS $325,000.0000 $325,000.00 $480,000.0000 $480,000.00 $284,363.1700 $284,363.17 $400,000.0000 $400,000.00 $560,000.0000 $560,000.00 $530,000.0000 $530,000.00
630-A001 Standard Roadside Signs, Sheet Aluminum, 0.080" Thickness 178 SF $20.0000 $3,560.00 $22.2500 $3,960.50 $20.0000 $3,560.00 $20.0000 $3,560.00 $23.5000 $4,183.00 $26.0000 $4,628.00
630-A003 Standard Roadside Signs, Sheet Aluminum, 0.125" Thickness 36 SF $22.0000 $792.00 $24.5000 $882.00 $22.0000 $792.00 $22.0000 $792.00 $26.0000 $936.00 $28.6000 $1,029.60
630-C001 Square Tube Posts, 4.0 lb/ft 170 LF $50.0000 $8,500.00 $55.6000 $9,452.00 $50.0000 $8,500.00 $50.0000 $8,500.00 $59.0000 $10,030.00 $65.0000 $11,050.00
630-C005 Square Tube Posts, 2.0 lb/ft 293 LF $25.0000 $7,325.00 $27.8000 $8,145.40 $25.0000 $7,325.00 $25.0000 $7,325.00 $29.5000 $8,643.50 $32.5000 $9,522.50
682-A018 Underground Branch Circuit, AWG 2, 3 Conductor 50 LF $27.2300 $1,361.50 $32.5000 $1,625.00 $26.0000 $1,300.00 $30.0000 $1,500.00 $30.5000 $1,525.00 $33.8000 $1,690.00
682-A039 Underground Branch Circuit, AWG 8, 3 Conductor 1,644 LF $12.5700 $20,665.08 $15.0000 $24,660.00 $12.0000 $19,728.00 $15.0000 $24,660.00 $14.0000 $23,016.00 $15.6000 $25,646.40
682-B037 Underground Branch Circuit, Jacked or Bored, AWG 8, 3 Conductor 496 LF $29.3200 $14,542.72 $35.0000 $17,360.00 $28.0000 $13,888.00 $30.0000 $14,880.00 $33.0000 $16,368.00 $36.4000 $18,054.40
682-D003 Underground Pull Box 1 EA $1,047.1200 $1,047.12 $1,250.0000 $1,250.00 $1,000.0000 $1,000.00 $1,500.0000 $1,500.00 $2,000.0000 $2,000.00 $1,300.0000 $1,300.00
682-E003 Underground Junction Box With Concrete Pad 12 EA $2,329.8400 $27,958.08 $2,785.0000 $33,420.00 $2,225.0000 $26,700.00 $2,800.0000 $33,600.00 $2,600.0000 $31,200.00 $2,900.0000 $34,800.00
682-F001 Secondary Power Controller 1 EA $13,612.5700 $13,612.57 $16,250.0000 $16,250.00 $13,000.0000 $13,000.00 $16,000.0000 $16,000.00 $20,000.0000 $20,000.00 $16,900.0000 $16,900.00
683-B208 Lighting Assembly, Low Mast, LED, Type 35-1-10-263 10 EA $6,911.0000 $69,110.00 $8,250.0000 $82,500.00 $6,600.0000 $66,000.00 $7,500.0000 $75,000.00 $8,000.0000 $80,000.00 $8,580.0000 $85,800.00
683-B209 Lighting Assembly, Low Mast, LED, Type 35-2-10-263 2 EA $8,481.6800 $16,963.36 $10,125.0000 $20,250.00 $8,100.0000 $16,200.00 $9,500.0000 $19,000.00 $10,000.0000 $20,000.00 $10,530.0000 $21,060.00
684-A004 Pole Foundation, 30" Diameter 16 CY $1,361.2600 $21,780.16 $1,625.0000 $26,000.00 $1,300.0000 $20,800.00 $1,500.0000 $24,000.00 $1,500.0000 $24,000.00 $1,690.0000 $27,040.00
684-B004 Slip Casing, 30" Diameter 7 LF $5.2400 $36.68 $6.2500 $43.75 $5.0000 $35.00 $5.0000 $35.00 $75.0000 $525.00 $6.5000 $45.50
685-B004 Aerially Supported Electrical Cable, XLP, AWG 4, 3 Conductor 1,545 LF $4.1900 $6,473.55 $5.0000 $7,725.00 $4.0000 $6,180.00 $5.0000 $7,725.00 $4.7000 $7,261.50 $5.2000 $8,034.00
685-C001 Temporary Lighting Assemblies 11 EA $3,246.0700 $35,706.77 $3,875.0000 $42,625.00 $3,100.0000 $34,100.00 $3,800.0000 $41,800.00 $3,650.0000 $40,150.00 $4,030.0000 $44,330.00
685-D001 Service Pole 1 EA $3,979.0600 $3,979.06 $4,750.0000 $4,750.00 $3,800.0000 $3,800.00 $5,000.0000 $5,000.00 $4,500.0000 $4,500.00 $4,940.0000 $4,940.00
699-A001 Roadway Construction Stakes 1 LS $100,000.0000 $100,000.00 $40,000.0000 $40,000.00 $1.0000 $1.00 $100,000.0000 $100,000.00 $345,000.0000 $345,000.00 $175,000.0000 $175,000.00
815-A007 Loose Riprap, Size 300 100 TON $100.0000 $10,000.00 $110.0000 $11,000.00 $120.0000 $12,000.00 $100.0000 $10,000.00 $95.0000 $9,500.00 $82.5000 $8,250.00
815-E001 Geotextile under Riprap 113 SY $5.0000 $565.00 $3.0000 $339.00 $5.0000 $565.00 $3.0000 $339.00 $10.0000 $1,130.00 $8.8500 $1,000.05
907-234-A001 Temporary Silt Fence 2,000 LF $5.0000 $10,000.00 $5.9000 $11,800.00 $5.0000 $10,000.00 $8.0000 $16,000.00 $5.7500 $11,500.00 $5.5000 $11,000.00
907-234-D001 Inlet Siltation Guard 5 EA $650.0000 $3,250.00 $765.0000 $3,825.00 $650.0000 $3,250.00 $750.0000 $3,750.00 $650.0000 $3,250.00 $600.0000 $3,000.00
907-234-E001 Reset Inlet Siltation Guard 5 EA $650.0000 $3,250.00 $765.0000 $3,825.00 $650.0000 $3,250.00 $750.0000 $3,750.00 $650.0000 $3,250.00 $590.0000 $2,950.00
907-403-A002 12.5-mm, MT, Asphalt Pavement 984 TON $172.7700 $170,005.68 $204.0000 $200,736.00 $213.7300 $210,310.32 $200.0000 $196,800.00 $194.0000 $190,896.00 $225.0000 $221,400.00
907-403-A005 19-mm, MT, Asphalt Pavement 1,340 TON $157.0600 $210,460.40 $180.0000 $241,200.00 $184.9300 $247,806.20 $170.0000 $227,800.00 $176.5000 $236,510.00 $198.0000 $265,320.00
907-403-A014 9.5-mm, MT, Asphalt Pavement 1,201 TON $178.0100 $213,790.01 $215.0000 $258,215.00 $208.7400 $250,696.74 $200.0000 $240,200.00 $200.0000 $240,200.00 $240.0000 $288,240.00
907-403-B002 12.5-mm, MT, Asphalt Pavement, Leveling 1,000 TON $172.7700 $172,770.00 $204.0000 $204,000.00 $242.4300 $242,430.00 $200.0000 $200,000.00 $194.0000 $194,000.00 $225.0000 $225,000.00
907-407-A001 Asphalt for Tack Coat 2,618 GAL $4.1900 $10,969.42 $5.3000 $13,875.40 $5.0000 $13,090.00 $6.0000 $15,708.00 $4.7000 $12,304.60 $5.8500 $15,315.30
907-413-E001 Sawing and Sealing Transverse Joints in Asphalt Pavement 1,330 LF $5.0000 $6,650.00 $5.5000 $7,315.00 $4.2500 $5,652.50 $12.0000 $15,960.00 $5.0000 $6,650.00 $6.5000 $8,645.00
907-601-A001 Class "B" Structural Concrete 88 CY $1,500.0000 $132,000.00 $250.0000 $22,000.00 $1,350.0000 $118,800.00 $1,500.0000 $132,000.00 $1,500.0000 $132,000.00 $2,600.0000 $228,800.00
907-601-B001 Class "B" Structural Concrete, Minor Structures 77 CY $3,800.0000 $292,600.00 $2,940.0000 $226,380.00 $2,500.0000 $192,500.00 $3,800.0000 $292,600.00 $2,000.0000 $154,000.00 $4,550.0000 $350,350.00
907-609-F002 Prefabricated Curb 2,410 LF $62.0000 $149,420.00 $84.7500 $204,247.50 $72.0000 $173,520.00 $75.0000 $180,750.00 $85.0000 $204,850.00 $93.6000 $225,576.00
907-616-C003 Colored and Imprinted Concrete Median and Island Pavement, 4-inch Thickness 13,716 SF $11.7500 $161,163.00 $15.0000 $205,740.00 $30.0000 $411,480.00 $20.0000 $274,320.00 $23.2500 $318,897.00 $15.2500 $209,169.00
907-618-A001 Maintenance of Traffic 1 LS $27,355.0000 $27,355.00 $75,000.0000 $75,000.00 $214,040.0000 $214,040.00 $125,000.0000 $125,000.00 $300,000.0000 $300,000.00 $165,000.0000 $165,000.00
907-626-B005 6" Thermoplastic Traffic Stripe, Continuous White 4,814 LF $2.5000 $12,035.00 $2.8000 $13,479.20 $2.5000 $12,035.00 $2.5000 $12,035.00 $2.7500 $13,238.50 $3.2500 $15,645.50
907-626-E006 6" Thermoplastic Traffic Stripe, Continuous Yellow 2,808 LF $2.5000 $7,020.00 $2.8000 $7,862.40 $2.5000 $7,020.00 $2.5000 $7,020.00 $2.7500 $7,722.00 $3.2500 $9,126.00
907-626-G004 Thermoplastic Detail Stripe, White 3,650 LF $5.0000 $18,250.00 $5.6000 $20,440.00 $5.0000 $18,250.00 $5.0000 $18,250.00 $5.7500 $20,987.50 $6.5000 $23,725.00
907-626-G005 Thermoplastic Detail Stripe, Yellow 6,550 LF $5.0000 $32,750.00 $5.6000 $36,680.00 $5.0000 $32,750.00 $5.0000 $32,750.00 $5.7500 $37,662.50 $6.5000 $42,575.00
907-626-H009 Thermoplastic Legend, White 443 SF $40.0000 $17,720.00 $44.5000 $19,713.50 $40.0000 $17,720.00 $40.0000 $17,720.00 $45.7500 $20,267.25 $52.0000 $23,036.00
907-626-H010 Thermoplastic Legend, White 168 LF $7.0000 $1,176.00 $7.8000 $1,310.40 $7.0000 $1,176.00 $7.0000 $1,176.00 $8.0000 $1,344.00 $9.1000 $1,528.80
907-627-K001 Red-Clear Reflective High Performance Raised Markers 145 EA $15.0000 $2,175.00 $17.0000 $2,465.00 $15.0000 $2,175.00 $15.0000 $2,175.00 $17.2500 $2,501.25 $19.5000 $2,827.50
907-627-L001 Two-Way Yellow Reflective High Performance Raised Markers 1,811 EA $15.0000 $27,165.00 $17.0000 $30,787.00 $15.0000 $27,165.00 $15.0000 $27,165.00 $17.2500 $31,239.75 $19.5000 $35,314.50

Source: public Mississippi DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.