Mississippi DOT · Bid Tabulation
Contract 110153301
Emergency Slide Repair on SR 178 approximately 0.66 miles south of CR 121
- County
- Union
- District
- 1
- Letting
- June 12, 2026
- Bidders
- 4
Apparent low bid
GeoStabilization International, LLC
$1,809,401.69
Other bidders
Phillips Contracting Co., Inc.
$2,037,885.00
Hope Enterprises, LLC
$2,495,258.16
Century Construction Group, Inc.
$2,525,306.00
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | GeoStabilization International, LLC $1,809,401.69 | Phillips Contracting Co., Inc. $2,037,885.00 | Hope Enterprises, LLC $2,495,258.16 | Century Construction Group, Inc. $2,525,306.00 | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 202-B007 | Removal of Asphalt Pavement, All Depths | 75 | SY | $80.0000 | $6,000.00 | $25.0000 | $1,875.00 | $126.8400 | $9,513.00 | $80.0000 | $6,000.00 |
| 203-EX023 | Borrow Excavation, AH, LVM, Class B10 | 500 | CY | $25.0000 | $12,500.00 | $61.2500 | $30,625.00 | $52.0500 | $26,025.00 | $45.0000 | $22,500.00 |
| 203-G002 | Excess Excavation, LVM, AH | 700 | CY | $58.5500 | $40,985.00 | $50.0000 | $35,000.00 | $128.8800 | $90,216.00 | $65.0000 | $45,500.00 |
| 225-C001 | Mulch, Vegetative Mulch | 1 | TON | $209.4100 | $209.41 | $2,000.0000 | $2,000.00 | $691.9500 | $691.95 | $1,900.0000 | $1,900.00 |
| 304-H003 | Size 825B Crushed Stone Base, LVM | 25 | CY | $53.3500 | $1,333.75 | $275.0000 | $6,875.00 | $388.6600 | $9,716.50 | $275.0000 | $6,875.00 |
| 406-D001 | Fine Milling of Bituminous Pavement, All Depths | 470 | SY | $60.5000 | $28,435.00 | $40.0000 | $18,800.00 | $34.1400 | $16,045.80 | $25.0000 | $11,750.00 |
| 606-B001 | Guard Rail, Class A, Type 1 | 320 | LF | $30.3600 | $9,715.20 | $35.0000 | $11,200.00 | $38.2000 | $12,224.00 | $35.0000 | $11,200.00 |
| 606-E007 | Guard Rail, Terminal End Section, Non-Flared | 2 | EA | $5,500.0000 | $11,000.00 | $6,250.0000 | $12,500.00 | $6,919.4700 | $13,838.94 | $6,300.0000 | $12,600.00 |
| 612-A001 | Flowable Fill, Excavatable | 100 | CY | $171.4900 | $17,149.00 | $400.0000 | $40,000.00 | $237.3300 | $23,733.00 | $300.0000 | $30,000.00 |
| 618-B001 | Additional Construction Signs | 1 | SF | $10.0000 | $10.00 | $10.0000 | $10.00 | $10.0000 | $10.00 | $10.0000 | $10.00 |
| 620-A001 | Mobilization | 1 | LS | $106,597.8500 | $106,597.85 | $200,000.0000 | $200,000.00 | $206,394.2400 | $206,394.24 | $250,000.0000 | $250,000.00 |
| 907-225-A001 | Grassing | 1,500 | SY | $18.5100 | $27,765.00 | $5.0000 | $7,500.00 | $0.5800 | $870.00 | $3.5000 | $5,250.00 |
| 907-403-A005 | 19-mm, MT, Asphalt Pavement | 50 | TON | $599.5000 | $29,975.00 | $600.0000 | $30,000.00 | $394.4100 | $19,720.50 | $410.0000 | $20,500.00 |
| 907-403-A014 | 9.5-mm, MT, Asphalt Pavement | 40 | TON | $577.5000 | $23,100.00 | $600.0000 | $24,000.00 | $394.4100 | $15,776.40 | $410.0000 | $16,400.00 |
| 907-618-A001 | Maintenance of Traffic | 1 | LS | $17,820.0000 | $17,820.00 | $50,000.0000 | $50,000.00 | $8,580.1400 | $8,580.14 | $220,000.0000 | $220,000.00 |
| 907-626-C013 | 6" Thermoplastic Edge Stripe, Continuous White | 300 | LF | $16.5000 | $4,950.00 | $20.0000 | $6,000.00 | $20.7600 | $6,228.00 | $18.7500 | $5,625.00 |
| 907-626-E006 | 6" Thermoplastic Traffic Stripe, Continuous Yellow | 600 | LF | $16.5000 | $9,900.00 | $20.0000 | $12,000.00 | $20.7600 | $12,456.00 | $18.7500 | $11,250.00 |
| 907-825-A001 | Soil Nail Retaining Walls | 4,600 | SF | $314.8900 | $1,448,494.00 | $325.0000 | $1,495,000.00 | $435.7800 | $2,004,588.00 | $397.7600 | $1,829,696.00 |
| 907-825-B001 | Soil Nail Verification Tests | 1 | EA | $5,347.0000 | $5,347.00 | $32,000.0000 | $32,000.00 | $7,399.6800 | $7,399.68 | $7,000.0000 | $7,000.00 |
| 907-825-C001 | Soil Nail Proof Tests | 9 | EA | $901.7200 | $8,115.48 | $2,500.0000 | $22,500.00 | $1,247.8900 | $11,231.01 | $1,250.0000 | $11,250.00 |
Source: public Mississippi DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.