New York DOT · Bid Tabulation
Contract D265658
PAVEMENT PREVENTATIVE MAINTENANCE - Route 167 City of Little Falls, Town of Manheim
- County
- Herkimer
- Letting
- February 26, 2026
- Bidders
- 2
Apparent low bid
HEIDELBERG MATERIALS NORTHEAST LLC
$4,804,231.78
Other bidders
BARRETT PAVING MATERIALS INC
$4,992,613.98
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | HEIDELBERG MATERIALS NORTHEAST LLC $4,804,231.78 | BARRETT PAVING MATERIALS INC $4,992,613.98 | ||
|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | ||||
| 201.07010004 | CLEARING AND GRUBBING AND TREE TRIMMING | 14 | EACH | $1,800.0000 | $25,200.00 | $1,422.0000 | $19,908.00 |
| 203.02 | UNCLASSIFIED EXCAVATION AND DISPOSAL | 406 | CY | $40.0000 | $16,240.00 | $72.0000 | $29,232.00 |
| 203.24010017 | SHOULDER BACKUP MATERIAL | 50 | TON | $145.0000 | $7,250.00 | $102.0000 | $5,100.00 |
| 209.1901 | ROLLED EROS CNTR PROD,CL II TYPE A, INT | 545 | SY | $4.7500 | $2,588.75 | $6.8600 | $3,738.70 |
| 209.23010009 | Biodegradable Sediment Filter Log 12 | 694 | LF | $9.7500 | $6,766.50 | $10.7200 | $7,439.68 |
| 304.12 | SUBBASE COURSE, TYPE 2 | 573 | CY | $87.0000 | $49,851.00 | $141.0000 | $80,793.00 |
| 404.0682 | 6.3 F2 Top Cour Asph 80 Ser Comp | 7,843 | TON | $109.0000 | $854,887.00 | $112.0000 | $878,416.00 |
| 404.1289 | 12.5 F9 T&L Should Cour Asph 80 Ser Comp | 15,872 | TON | $102.0000 | $1,618,944.00 | $99.0000 | $1,571,328.00 |
| 404.2589 | 25 F9 Binder Cour Asph 80 Ser Comp | 164 | TON | $140.0000 | $22,960.00 | $139.0000 | $22,796.00 |
| 407.01040009 | NON-TRACKING TACK COAT | 15,753 | GAL | $3.0000 | $47,259.00 | $3.8300 | $60,333.99 |
| 418.7603 | ASPHALT PAVEMENT JOINT ADHESIVE | 33,227 | LF | $0.5700 | $18,939.39 | $0.4500 | $14,952.15 |
| 490.17011018 | PRODUCTION COLD MICROMILLING | 141,379 | SY | $3.3000 | $466,550.70 | $3.9000 | $551,378.10 |
| 555.0021 | Concrete for Structures, Performance | 6.6 | CY | $2,300.0000 | $15,180.00 | $3,910.0000 | $25,806.00 |
| 555.9902 | Performance Concrete Quality F Struct | 1 | QU | $25.0000 | $25.00 | $25.0000 | $25.00 |
| 556.0202 | EPOXY-COATED BAR REINFORCEMENT FOR STRUC | 789 | LB | $13.5000 | $10,651.50 | $12.0000 | $9,468.00 |
| 559.02 | Protective Sealing of New Struct Concret | 123 | SF | $6.5000 | $799.50 | $2.0500 | $252.15 |
| 568.54 | STEEL BRIDGE RAILING (THREE RAIL) | 48 | LF | $225.3700 | $10,817.76 | $225.3700 | $10,817.76 |
| 568.70 | TRANSITION BRIDGE RAILING | 64 | LF | $202.4800 | $12,958.72 | $202.4800 | $12,958.72 |
| 580.01 | REMOVAL OF STRUCTURAL CONCRETE | 4 | CY | $4,950.0000 | $19,800.00 | $4,790.0000 | $19,160.00 |
| 586.0201 | DRILL GROUT BOLTS OR REINFORMENT BARS | 111 | EACH | $60.7500 | $6,743.25 | $76.0000 | $8,436.00 |
| 587.01 | BRIDGE RAILING REMOVAL AND DISPOSAL | 44 | LF | $35.0000 | $1,540.00 | $30.4300 | $1,338.92 |
| 595.50000018 | SHEET-APPLIED WATERPROOFING MEMBRANE | 138 | SF | $16.2500 | $2,242.50 | $12.0000 | $1,656.00 |
| 603.0101 | CULVERT-END SAFETY GRATE | 54 | SF | $28.5000 | $1,539.00 | $46.6900 | $2,521.26 |
| 603.171116 | G.S.E. PIPE (2-2/3X1/2) 15 DIA, 16 GA | 15 | EACH | $1,100.0000 | $16,500.00 | $197.9500 | $2,969.25 |
| 603.171216 | G.S.E.PIPE(2-2/3X1/2 CORR) 18", 16 GA | 4 | EACH | $1,060.0000 | $4,240.00 | $227.8900 | $911.56 |
| 603.171814 | G.S.E.PIPE (2-2/3X1/2 CORR) 36, 14 GA | 3 | EACH | $1,775.0000 | $5,325.00 | $843.3500 | $2,530.05 |
| 603.87020015 | OPT DRNG PIPE 15 IN < 12 IN FILL HT | 219 | LF | $132.0000 | $28,908.00 | $115.0000 | $25,185.00 |
| 603.87050015 | OPT DRNG PIPE 24 IN < 12 IN FILL HT | 37 | LF | $150.0000 | $5,550.00 | $147.0000 | $5,439.00 |
| 603.88020015 | END SECT - OPT 15 IN DIAMETER | 12 | EACH | $210.0000 | $2,520.00 | $98.6900 | $1,184.28 |
| 603.88050015 | END SECT - OPT 24 IN DIAMETER | 2 | EACH | $285.0000 | $570.00 | $196.3900 | $392.78 |
| 606.10 | BOX BEAM GUIDE RAILING | 754 | LF | $51.8800 | $39,117.52 | $51.8800 | $39,117.52 |
| 606.11 | BOX BEAM MEDIAN BARRIER | 103 | LF | $69.8600 | $7,195.58 | $69.8600 | $7,195.58 |
| 606.120101 | BOX BEAM END PIECE | 4 | EACH | $681.9300 | $2,727.72 | $681.9300 | $2,727.72 |
| 606.120102 | BOX BEAM GUIDE RAIL END ASSEMBLY, TYPE I | 6 | EACH | $4,511.5900 | $27,069.54 | $4,511.5900 | $27,069.54 |
| 606.120201 | BOX BEAM GUIDE RAIL END ASSEMB, TYPE IIA | 2 | EACH | $2,292.7300 | $4,585.46 | $2,292.7300 | $4,585.46 |
| 606.1203 | BOX BEAM END ASSEMB, TYPE III | 2 | EACH | $6,563.9800 | $13,127.96 | $6,563.9800 | $13,127.96 |
| 606.1403 | BX BM MED BARR END ASSEMBL, TYPE C | 2 | EACH | $7,483.9800 | $14,967.96 | $7,483.9800 | $14,967.96 |
| 606.53 | RESETTING BOX BEAM GUIDE RAILING | 1,183 | LF | $16.5400 | $19,566.82 | $16.5400 | $19,566.82 |
| 606.5920 | RESET BOX BEAM GUIDERAILNG TURNDOWN TER | 1 | EACH | $841.4800 | $841.48 | $841.4800 | $841.48 |
| 606.70 | REMOVING AND DISP CABLE GUIDERAILING | 132 | LF | $2.5000 | $330.00 | $2.5000 | $330.00 |
| 606.73 | REMOVING AND DISP BOX BEAM GUIDERAILING | 1,066 | LF | $5.0000 | $5,330.00 | $5.0000 | $5,330.00 |
| 606.79 | REM&DISP ANCHORAGE UNITS CABLE GR | 2 | EACH | $675.0000 | $1,350.00 | $675.0000 | $1,350.00 |
| 606.7920 | REM DISP BOX BM GUIDERAIL TURNDOWN TER | 12 | EACH | $160.0000 | $1,920.00 | $160.0000 | $1,920.00 |
| 608.000013 | Plant Prod Qual Adj Asph Siwalk,Driv,Pat | 1 | QU | $105.0000 | $105.00 | $105.0000 | $105.00 |
| 608.020102 | ASP SIDE W, DRVWAY, BICY PATH, VEG CON S | 28 | TON | $490.0000 | $13,720.00 | $275.0000 | $7,700.00 |
| 610.1401 | TOPSOIL - REUSE ON-SITE MATERIALS | 50 | CY | $75.0000 | $3,750.00 | $43.0000 | $2,150.00 |
| 610.1402 | TOPSOIL - ROADSIDE | 27 | CY | $123.0000 | $3,321.00 | $139.0000 | $3,753.00 |
| 610.1605 | Turf Estabment Performance | 3,709 | SY | $11.2000 | $41,540.80 | $12.8000 | $47,475.20 |
| 617.11000024 | EQUIP CLEANING FOR INVASIVE PLANT SPECIE | 1 | LS | $1,000.0000 | $1,000.00 | $1,840.0000 | $1,840.00 |
| 619.01 | BASIC WORK ZONE TRAFFIC CONTROL | 1 | LS | $432,400.0000 | $432,400.00 | $428,627.3900 | $428,627.39 |
| 619.0901 | TEMP PAVE MARKING STRIPES(TRAF PAINT) | 155,342 | LF | $0.2300 | $35,728.66 | $0.1900 | $29,514.98 |
| 619.110613 | PVMS STD SZ FL MTR LD NO EQ CEL CM NTCIP | 8 | CW | $2,600.0000 | $20,800.00 | $530.0000 | $4,240.00 |
| 619.1711 | Temp Positive Barrier Cat 1 Pin Prohibit | 340 | LF | $36.0000 | $12,240.00 | $30.0000 | $10,200.00 |
| 619.1719 | Warning Lights on Temp Pos Barriers | 9 | EACH | $85.0000 | $765.00 | $48.0000 | $432.00 |
| 621.01 | CLEAN CULVERT WITH SPAN OF 50IN OR LESS | 1,608 | LF | $15.3500 | $24,682.80 | $9.5000 | $15,276.00 |
| 621.51000015 | GRADE CLN AND RESHAPE EXISTING DITCHES | 7,153 | LF | $10.6500 | $76,179.45 | $11.5000 | $82,259.50 |
| 621.51950006 | CLEAN EXIST CONC OR ASPHALT GUTTERS | 4,650 | LF | $4.4000 | $20,460.00 | $16.0000 | $74,400.00 |
| 624.01 | CNVNTALY FRMD OR MCHNE FRMD CONC GUTTERS | 601 | SF | $50.0000 | $30,050.00 | $36.0000 | $21,636.00 |
| 624.020101 | ASPHALT CONCRETE GUTTERS | 4 | TON | $490.0000 | $1,960.00 | $590.0000 | $2,360.00 |
| 624.020110 | PLNT PROD QUAL ADJUST TO 624.020101 | 1 | QU | $105.0000 | $105.00 | $105.0000 | $105.00 |
| 625.01 | SURVEY OPERATIONS | 1 | LS | $13,000.0000 | $13,000.00 | $45,000.0000 | $45,000.00 |
| 627.50140008 | CUTTING PAVEMENT | 981 | LF | $3.6500 | $3,580.65 | $3.2500 | $3,188.25 |
| 633.1401 | Rem Repair Deteriorted Asphalt by Surfac | 20 | SY | $204.0000 | $4,080.00 | $244.0000 | $4,880.00 |
| 633.1402 | Rem Repair Deteriorted Asphalt by Surfac | 344 | SY | $137.0000 | $47,128.00 | $169.0000 | $58,136.00 |
| 633.1403 | Rem Repair Deteriorted Asphalt by Surfac | 1,054 | SY | $64.5500 | $68,035.70 | $82.0000 | $86,428.00 |
| 633.15 | REM & RPR OF LSE, BRKN OR SPLD PCC PVMNT | 20 | SY | $204.0000 | $4,080.00 | $180.0000 | $3,600.00 |
| 637.04 | Concrete Cylinder Curing Equipment | 1 | EACH | $1,100.0000 | $1,100.00 | $500.0000 | $500.00 |
| 637.12 | ENGINEER'S FIELD OFFICE - TYPE 2 | 8 | MNTH | $3,300.0000 | $26,400.00 | $2,450.0000 | $19,600.00 |
| 637.34 | OFFICE TECHNOLOGY AND SUPPLIES | 1,000 | DC | $1.0000 | $1,000.00 | $1.0000 | $1,000.00 |
| 645.5101 | GROUND-MOUNTED SIGN PANELS WITHOUT Z-BAR | 6 | SF | $39.0000 | $234.00 | $39.0000 | $234.00 |
| 645.5102 | GR-MOUNT SIGN PANELS L.E. 32 SF W Z-BAR | 379 | SF | $38.7500 | $14,686.25 | $38.7500 | $14,686.25 |
| 645.81 | TYPE A SIGN POSTS | 75 | EACH | $200.0000 | $15,000.00 | $200.0000 | $15,000.00 |
| 645.81090003 | RETROREFLECTIVE SIGN POST STRIP | 8 | EACH | $65.0000 | $520.00 | $65.0000 | $520.00 |
| 645.830301 | TY B POST,GALV,W6X12,NON-BRKAWAY BASE | 2 | EACH | $3,200.0000 | $6,400.00 | $3,200.0000 | $6,400.00 |
| 646.21 | REFERENCE MARKER PANEL | 29 | EACH | $28.0000 | $812.00 | $28.0000 | $812.00 |
| 646.23 | LG DEL,LG SN P MARK,LG SUPL SN P MARK PA | 30 | EACH | $14.0000 | $420.00 | $14.0000 | $420.00 |
| 646.32 | STEEL POST, 2.0 LB/FT | 41 | EACH | $65.0000 | $2,665.00 | $65.0000 | $2,665.00 |
| 647.31 | RELOC SIGN PANEL ASEMB SZ I UNDER 30SF | 19 | EACH | $175.0000 | $3,325.00 | $175.0000 | $3,325.00 |
| 647.61 | REMV DISP GR MT TY A SUP FND SIGN SZ I | 35 | EACH | $20.0000 | $700.00 | $20.0000 | $700.00 |
| 647.83001002 | REM & DSPSL OF DELNTRS &/OR REF MARKERS | 20 | EACH | $15.0000 | $300.00 | $15.0000 | $300.00 |
| 649.11 | CENTERLINE AUDIBLE ROAD DELINEATRS (CARD | 30,484 | LF | $0.2800 | $8,535.52 | $0.6200 | $18,900.08 |
| 685.1102 | Wht Epoxy Reflect Pavnt Strip 20 mil | 95,315 | LF | $0.3700 | $35,266.55 | $0.4200 | $40,032.30 |
| 685.1202 | Yell Epoxy Reflect Pavnt Strip 20 mil | 56,647 | LF | $0.3700 | $20,959.39 | $0.4200 | $23,791.74 |
| 685.3104 | W Epox Refl pav Spe Str 20 mil Port Hand | 3,582 | LF | $2.5000 | $8,955.00 | $2.2500 | $8,059.50 |
| 685.3404 | W Epox Refl pav Symbols 20 mil Port Hand | 3 | EACH | $225.0000 | $675.00 | $225.0000 | $675.00 |
| 697.03 | FIELD CHANGE PAYMENT | 180,000 | DC | $1.0000 | $180,000.00 | $1.0000 | $180,000.00 |
| 698.04 | ASPHALT PRICE ADJUSTMENT | 14,405.4 | DC | $1.0000 | $14,405.40 | $1.0000 | $14,405.40 |
| 698.05 | FUEL PRICE ADJUSTMENT | 1,584 | DC | $1.0000 | $1,584.00 | $1.0000 | $1,584.00 |
| 698.06 | STEEL/IRON PRICE ADJUSTMENT | 100 | DC | $1.0000 | $100.00 | $1.0000 | $100.00 |
| 699.040001 | MOBILIZATION | 1 | LS | $180,000.0000 | $180,000.00 | $191,000.0000 | $191,000.00 |
Source: public New York DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →