NY
New York DOT · Bid Tabulation
Contract D265662
BRIDGE PRESERVATION NY Route 2 Congress Street Over Hudson River, Cities of Troy and Watervliet.
- County
- Albany, Rensselaer
- Letting
- February 26, 2026
- Bidders
- 1
Apparent low bid
D A COLLINS CONSTRUCTION CO INC
$15,455,796.69
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | D A COLLINS CONSTRUCTION CO INC $15,455,796.69 | |
|---|---|---|---|---|---|
| Unit Price | Extension | ||||
| 203.02 | UNCLASSIFIED EXCAVATION AND DISPOSAL | 414 | CY | $215.0000 | $89,010.00 |
| 203.07 | SELECT GRANULAR FILL | 80 | CY | $24.5000 | $1,960.00 |
| 203.21 | SELECT STRUCTURE FILL | 21 | CY | $785.0000 | $16,485.00 |
| 204.01 | CONTROLLED LOW STRENGTH MATERIAL (CLSM) | 8 | CY | $1,000.0000 | $8,000.00 |
| 206.01 | STRUCTURE EXCAVATION | 21 | CY | $565.0000 | $11,865.00 |
| 206.0201 | TRENCH AND CULVERT EXCAVATION | 87 | CY | $250.0000 | $21,750.00 |
| 206.03 | CONDUIT EXCAV & BACKFL INC/SURFACE RESTR | 266 | LF | $34.0000 | $9,044.00 |
| 206.03120010 | CONDUIT INSTALL ON ABOVE GRADE STRUC | 450 | LF | $26.5000 | $11,925.00 |
| 206.03120011 | CONDUIT INSTALLED ON ABOVE GRADE STRUC | 2,326 | LF | $55.5000 | $129,093.00 |
| 207.20 | GEOTEXTILE BEDDING | 25 | SY | $54.0000 | $1,350.00 |
| 210.481201 | REMOVE DISPOSE MISCELLANEOUS ACM (BV14) | 2,070 | SF | $47.0000 | $97,290.00 |
| 304.12 | SUBBASE COURSE, TYPE 2 | 204 | CY | $280.0000 | $57,120.00 |
| 404.0982 | 9.5 F2 Top Cour Asph 80 Ser Comp | 301 | TON | $290.0000 | $87,290.00 |
| 404.1989 | 19 F9 Binder Cour Asph 80 Ser Comp | 49 | TON | $290.0000 | $14,210.00 |
| 404.3789 | 37.5 F9 Base Cour Asph 80 Ser Comp | 154 | TON | $290.0000 | $44,660.00 |
| 407.0103 | STRAIGHT TACK COAT | 300 | GAL | $21.5000 | $6,450.00 |
| 418.7603 | ASPHALT PAVEMENT JOINT ADHESIVE | 1,730 | LF | $4.2500 | $7,352.50 |
| 490.30 | MISC COLD MILLING OF BITUMINOUS CONCRETE | 2,213 | SY | $13.0000 | $28,769.00 |
| 520.09000010 | SAW CUTTING ASPHALT CONCRETE | 264 | LF | $5.3000 | $1,399.20 |
| 552.17 | SHIELDS AND SHORING | 336 | SF | $1.1500 | $386.40 |
| 555.0021 | Concrete for Structures, Performance | 269 | CY | $3,000.0000 | $807,000.00 |
| 555.9902 | Performance Concrete Quality F Struct | 1 | QU | $7.5000 | $7.50 |
| 556.0202 | EPOXY-COATED BAR REINFORCEMENT FOR STRUC | 22,171 | LB | $5.4000 | $119,723.40 |
| 556.0205 | STAINLESS STEEL BAR REINFMNT FOR STRCTRS | 8,737 | LB | $8.0000 | $69,896.00 |
| 556.03 | STUD SHEAR CONNECTORS FOR BRIDGES | 2,373 | EACH | $25.0000 | $59,325.00 |
| 557.1012 | Structural Approach Slab | 361 | SY | $795.0000 | $286,995.00 |
| 557.30 | SIDEWALKS AND SAFETY WALKS | 43 | SY | $844.0000 | $36,292.00 |
| 557.66130105 | UHPC GIRDER STRENGTHENING | 34 | CF | $2,611.0000 | $88,774.00 |
| 557.75010216 | ULTRA-HIGH PERFM CONC LINK SLAB | 480 | CF | $460.0000 | $220,800.00 |
| 557.9901 | Performance Concrete Quality Adjustment | 1 | QU | $9.0000 | $9.00 |
| 557.9902 | Performance Concrete Quality Adjustment | 1 | QU | $12.0000 | $12.00 |
| 558.02 | LONGT. SAWCUT GRVNG OF STRUCT SLAB SUF | 271 | SY | $29.5000 | $7,994.50 |
| 559.01 | Protect Seal Struct Conc New Bridge Dek | 2,340 | SF | $2.8500 | $6,669.00 |
| 559.02 | Protective Sealing of New Struct Concret | 9,572 | SF | $2.8500 | $27,280.20 |
| 564.510001 | STRUCTURAL STEEL | 334 | LB | $46.5000 | $15,531.00 |
| 564.510002 | STRUCTURAL STEEL | 4,986 | LB | $72.0000 | $358,992.00 |
| 564.700001 | STRUCTURAL STEEL REPLACEMENT | 20 | EACH | $6,550.0000 | $131,000.00 |
| 564.700002 | STRUCTURAL STEEL REPLACEMENT | 21 | EACH | $6,850.0000 | $143,850.00 |
| 564.700003 | STRUCTURAL STEEL REPLACEMENT | 1 | EACH | $6,900.0000 | $6,900.00 |
| 564.700004 | STRUCTURAL STEEL REPLACEMENT | 4 | EACH | $7,450.0000 | $29,800.00 |
| 564.700005 | STRUCTURAL STEEL REPLACEMENT | 2 | EACH | $7,050.0000 | $14,100.00 |
| 564.700006 | STRUCTURAL STEEL REPLACEMENT | 5 | EACH | $6,950.0000 | $34,750.00 |
| 564.700007 | STRUCTURAL STEEL REPLACEMENT | 6 | EACH | $5,650.0000 | $33,900.00 |
| 565.1522 | TYPE M.R. EXPAN BEAR (226 TO 450 KIPS) | 24 | EACH | $7,200.0000 | $172,800.00 |
| 565.1525 | TYPE M.R. EXPAN BEARING (OVER 900 KIPS) | 9 | EACH | $16,600.0000 | $149,400.00 |
| 565.1725 | TYPE M.R. FIXED BEARING (OVER 900 KIPS) | 9 | EACH | $15,000.0000 | $135,000.00 |
| 565.2025 | TYPE E.B. FIXED BEARING (OVER 225 KIPS) | 9 | EACH | $4,900.0000 | $44,100.00 |
| 565.20310003 | Elastomeric Sliding Bearings (Expansion) | 36 | EACH | $4,950.0000 | $178,200.00 |
| 565.2034 | TYPE E.B EXPAN BEARING (169 TO 225 KIPS) | 24 | EACH | $4,350.0000 | $104,400.00 |
| 565.2035 | TYPE E.B EXPAN BEARING (OVER 225 KIPS) | 20 | EACH | $6,950.0000 | $139,000.00 |
| 566.13142001 | ELASTERIC EXPNSON JOT SYST W WEAR PLATES | 304 | LF | $2,750.0000 | $836,000.00 |
| 568.51 | STEEL BRIDGE RAILING (FOUR RAIL) | 234 | LF | $385.0000 | $90,090.00 |
| 569.05 | SINGLE SLOPE(FULL SECT)CONC BRDG BARR | 81 | LF | $1,200.0000 | $97,200.00 |
| 569.99 | Performance Concrete Quality Adjustment | 1 | QU | $9.0900 | $9.09 |
| 570.01 | LEAD EXPOSURE CONTROL PLAN | 1 | LS | $2,650.0000 | $2,650.00 |
| 570.02 | MEDICAL TESTING | 3,000 | DC | $1.0000 | $3,000.00 |
| 570.03 | PERSONAL EXP MONITORING SAMPLE ANAL | 3,000 | DC | $1.0000 | $3,000.00 |
| 570.04 | DECONTAMINATION FACILITIES | 15 | CW | $21.5000 | $322.50 |
| 570.150001 | CLASS A CONTAINMENT FOR PAINT REMOVAL | 1 | LS | $90,400.0000 | $90,400.00 |
| 571.03 | DISPOSAL HAZARD PAINT WASTE CONTAIN LEAD | 17,615 | LB | $0.2100 | $3,699.15 |
| 572.020001 | STRUCTURAL STEEL PAINTING: SHOP APPLIED | 1 | LS | $1.1500 | $1.15 |
| 573.010001 | STRUCT STEEL PAINT FIELD APP TOTAL REMOV | 1 | LS | $513,000.0000 | $513,000.00 |
| 576.03210011 | CLEANING SCUPPERS | 16 | EACH | $410.0000 | $6,560.00 |
| 580.01 | REMOVAL OF STRUCTURAL CONCRETE | 176 | CY | $3,220.0000 | $566,720.00 |
| 580.04 | REMOVAL OF CONCRETE APPROACH SLAB | 3,340 | SF | $12.0000 | $40,080.00 |
| 582.0052 | Removal and Replacement of Struct Conc | 2,474 | SF | $350.0000 | $865,900.00 |
| 582.0061 | Removal and Replacement of Struct Conc | 174 | SF | $590.0000 | $102,660.00 |
| 585.01 | STRUCTURAL LIFTING OPERATIONS - TYPE A | 113 | EACH | $12,800.0000 | $1,446,400.00 |
| 585.02 | STRUCTURAL LIFTING OPERATIONS - TYPE B | 18 | EACH | $62,300.0000 | $1,121,400.00 |
| 586.0201 | DRILL GROUT BOLTS OR REINFORMENT BARS | 1,357 | EACH | $130.0000 | $176,410.00 |
| 586.10 | FIELD DRILL HOLES IN EXISTING STR STEEL | 731 | EACH | $65.0000 | $47,515.00 |
| 587.02 | BRIDGE RAILING REMOVAL AND STORAGE | 577 | LF | $39.5000 | $22,791.50 |
| 587.03 | INSTALLATION OF STORED BRIDGE RAILING | 577 | LF | $150.0000 | $86,550.00 |
| 589.520001 | REMOVAL OF EXISTING STEEL | 20 | EACH | $3,350.0000 | $67,000.00 |
| 589.520002 | REMOVAL OF EXISTING STEEL | 21 | EACH | $3,600.0000 | $75,600.00 |
| 589.520003 | REMOVAL OF EXISTING STEEL | 1 | EACH | $3,350.0000 | $3,350.00 |
| 589.520004 | REMOVAL OF EXISTING STEEL | 4 | EACH | $3,350.0000 | $13,400.00 |
| 589.520005 | REMOVAL OF EXISTING STEEL | 2 | EACH | $3,350.0000 | $6,700.00 |
| 589.520006 | REMOVAL OF EXISTING STEEL | 5 | EACH | $3,350.0000 | $16,750.00 |
| 589.520007 | REMOVAL OF EXISTING STEEL | 6 | EACH | $3,350.0000 | $20,100.00 |
| 589.520008 | REMOVAL OF EXISTING STEEL | 131 | EACH | $2,500.0000 | $327,500.00 |
| 603.6003 | REINF CONC PIPE CLASS III, 18 DIA | 54 | LF | $430.0000 | $23,220.00 |
| 603.77 | CONCRETE COLLARS | 1 | EACH | $5,250.0000 | $5,250.00 |
| 603.99050002 | CONCRETE PLUGS FOR SEWER PIPE | 4 | EACH | $965.0000 | $3,860.00 |
| 604.13000011 | ABANDONING DRAINAGE STRUCTURES | 4 | EACH | $2,450.0000 | $9,800.00 |
| 604.302192 | RECT DRAIN STRU TY U PARA BAR #12PCB FRM | 18 | LF | $1,000.0000 | $18,000.00 |
| 606.3043 | SNGL-SLOPE CONC MED BARR (CAST-IN-PLACE) | 50 | LF | $615.0000 | $30,750.00 |
| 607.61000005 | REMOVE AND RESET CHAIN LINK FENCING | 120 | LF | $80.0000 | $9,600.00 |
| 608.01030008 | REM & REPLC CONC SDWALK & SUBBASE CRSE | 46 | SY | $835.0000 | $38,410.00 |
| 608.020102 | ASP SIDE W, DRVWAY, BICY PATH, VEG CON S | 2 | TON | $560.0000 | $1,120.00 |
| 609.0301 | STONE CURB - BRIDGE (TYPE A) | 80 | LF | $205.0000 | $16,400.00 |
| 609.0302 | STONE CURB - BRIDGE (TYPE F1) | 48 | LF | $270.0000 | $12,960.00 |
| 609.06000008 | CURB REMOVAL | 54 | LF | $79.5000 | $4,293.00 |
| 619.01 | BASIC WORK ZONE TRAFFIC CONTROL | 1 | LS | $2,183,000.0000 | $2,183,000.00 |
| 619.04 | TYPE III CONSTRUCTION BARRICADE | 4 | EACH | $62.0000 | $248.00 |
| 619.0804 | COVER EXIST PVMT MARK LTRS OR SYM (TAPE) | 2 | EACH | $320.0000 | $640.00 |
| 619.100103 | INTERIM PAVE MARKING, STRIPE(REMOV TAPE) | 9,120 | LF | $5.8500 | $53,352.00 |
| 619.100203 | INTERIM PAVE MARKING, SYMBOL(REMOV TAPE) | 2 | EACH | $320.0000 | $640.00 |
| 619.100303 | INTERIM PAVE MARKING, LETTER(REMOV TAPE) | 8 | EACH | $105.0000 | $840.00 |
| 619.111113 | PVMS STD SIZ LC MATR LED NO EQU, NTCIP | 2 | EACH | $45,700.0000 | $91,400.00 |
| 619.1711 | Temp Positive Barrier Cat 1 Pin Prohibit | 480 | LF | $44.5000 | $21,360.00 |
| 619.1715 | Temp Positive Barrier Cat 5 Pin Prohibit | 4,080 | LF | $63.5000 | $259,080.00 |
| 619.1716 | Temp Positive Barrier Cat 6 Pin Required | 1,920 | LF | $58.5000 | $112,320.00 |
| 619.1719 | Warning Lights on Temp Pos Barriers | 172 | EACH | $27.0000 | $4,644.00 |
| 619.24 | Nighttime Operations (Entire Project) | 1 | LS | $35,200.0000 | $35,200.00 |
| 625.01 | SURVEY OPERATIONS | 1 | LS | $36,500.0000 | $36,500.00 |
| 637.04 | Concrete Cylinder Curing Equipment | 1 | EACH | $1,850.0000 | $1,850.00 |
| 655.1122 | WELDED FRAME AND RETICULINE GRATE 22 | 4 | EACH | $3,100.0000 | $12,400.00 |
| 655.16000011 | REMOVE AND DISPOSE OF FRAMES AND GRATES | 4 | EACH | $950.0000 | $3,800.00 |
| 662.60000108 | FURNISHING ELECTRICAL SERVICE | 3,000 | DC | $1.0000 | $3,000.00 |
| 665.98000103 | REMOVE AND INSTALL NEW NAVIGATION LIGHTS | 1 | LS | $16,400.0000 | $16,400.00 |
| 665.98000116 | NAVIGATION LIGHTS (AC POWER SOURCE) | 1 | LS | $120,000.0000 | $120,000.00 |
| 670.35250025 | REMOVE ABANDONED UTILITY PIPE | 266 | LF | $32.0000 | $8,512.00 |
| 670.41091111 | GAL ST NEMA TYPE 4 JNCT BX SURF MNT | 6 | EACH | $2,750.0000 | $16,500.00 |
| 680.520406 | TRAF SIG COND, PVC CTD GALV STL, 2" | 3,040 | LF | $80.0000 | $243,200.00 |
| 680.53000111 | S.S. NEMA 4X STR MT PULLBOX 16IX12IX8I | 10 | EACH | $2,850.0000 | $28,500.00 |
| 680.730310 | SIGNAL CABLE, 3 CONDUCTOR, 10 AWG | 3,040 | LF | $9.0500 | $27,512.00 |
| 680.90920008 | ELEC MTR SOC 200A SP 240/120V W/BP SWITC | 2 | EACH | $1,550.0000 | $3,100.00 |
| 680.9401 | Watertight Disconnect Box | 2 | EACH | $1,550.0000 | $3,100.00 |
| 685.0101 | Wht Epoxy Reflect Pavnt Strip 15 mil | 7,171 | LF | $1.2500 | $8,963.75 |
| 685.0201 | Yell Epoxy Reflect Pavnt Strip 15 mil | 5,313 | LF | $1.2500 | $6,641.25 |
| 685.06150106 | WH EPXY REFLECT CROSS HATCHINGS- 15 MILS | 1,462 | LF | $3.8000 | $5,555.60 |
| 685.2303 | W Epox Refl pav Letters 15 mil Port Hand | 12 | EACH | $80.0000 | $960.00 |
| 685.2403 | W Epox Refl pav Symbols 15 mil Port Hand | 7 | EACH | $240.0000 | $1,680.00 |
| 697.03 | FIELD CHANGE PAYMENT | 700,000 | DC | $1.0000 | $700,000.00 |
| 698.04 | ASPHALT PRICE ADJUSTMENT | 100 | DC | $1.0000 | $100.00 |
| 698.05 | FUEL PRICE ADJUSTMENT | 367 | DC | $1.0000 | $367.00 |
| 698.06 | STEEL/IRON PRICE ADJUSTMENT | 100 | DC | $1.0000 | $100.00 |
| 699.040001 | MOBILIZATION | 1 | LS | $550,000.0000 | $550,000.00 |
Source: public New York DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →