SC
South Carolina DOT · Bid Tabulation
Contract 2372300
Intersection Improvement S-540 @ L-1969
- County
- Greenville
- District
- 3
- Letting
- April 14, 2026
- Bidders
- 8
Apparent low bid
REEVES CONSTRUCTION COMPANY
$1,439,000.15
Other bidders
SOUTHERN CONCRETE & CONSTRUCTION, INC.
$1,543,120.55
AOS SPECIALTY CONTRACTORS, INC.
$1,674,862.25
S AND S CONSTRUCTION, INC. OF ANDERSON
$1,896,533.45
EAGLE CONSTRUCTION COMPANY
$1,928,301.00
CIVIL PROS INC
$2,031,140.02
MCMURRIA GRADING LLC
$2,134,068.55
KING ASPHALT, INC.
$2,174,509.70
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | REEVES CONSTRUCTION COMPANY $1,439,000.15 | SOUTHERN CONCRETE & CONSTRUCTION, INC. $1,543,120.55 | AOS SPECIALTY CONTRACTORS, INC. $1,674,862.25 | S AND S CONSTRUCTION, INC. OF ANDERSON $1,896,533.45 | EAGLE CONSTRUCTION COMPANY $1,928,301.00 | CIVIL PROS INC $2,031,140.02 | MCMURRIA GRADING LLC $2,134,068.55 | KING ASPHALT, INC. $2,174,509.70 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 1031000 | MOBILIZATION | 1 | LS | $140,000.0000 | $140,000.00 | $164,850.0000 | $164,850.00 | $100,000.0000 | $100,000.00 | $98,800.0000 | $98,800.00 | $130,000.0000 | $130,000.00 | $95,000.0000 | $95,000.00 | $68,500.0000 | $68,500.00 | $107,500.0000 | $107,500.00 |
| 1032010 | BONDS AND INSURANCE | 1 | LS | $17,150.0000 | $17,150.00 | $11,500.0000 | $11,500.00 | $35,000.0000 | $35,000.00 | $35,600.0000 | $35,600.00 | $17,000.0000 | $17,000.00 | $55,000.0000 | $55,000.00 | $36,704.0000 | $36,704.00 | $9,000.0000 | $9,000.00 |
| 1050800 | CONSTRUCTION STAKES, LINES & GRADES | 1 | EA | $26,000.0000 | $26,000.00 | $9,200.0000 | $9,200.00 | $25,000.0000 | $25,000.00 | $21,500.0000 | $21,500.00 | $59,000.0000 | $59,000.00 | $10,000.0000 | $10,000.00 | $16,500.0000 | $16,500.00 | $35,180.0000 | $35,180.00 |
| 1080300 | CPM PROGRESS SCHEDULE | 1 | LS | $7,700.0000 | $7,700.00 | $8,500.0000 | $8,500.00 | $10,000.0000 | $10,000.00 | $12,900.0000 | $12,900.00 | $5,000.0000 | $5,000.00 | $10,010.0000 | $10,010.00 | $6,000.0000 | $6,000.00 | $6,200.0000 | $6,200.00 |
| 2011000 | CLEARING & GRUBBING WITHIN RIGHT OF WAY | 1 | LS | $48,000.0000 | $48,000.00 | $50,000.0000 | $50,000.00 | $115,500.0000 | $115,500.00 | $137,500.0000 | $137,500.00 | $58,500.0000 | $58,500.00 | $15,000.0000 | $15,000.00 | $27,500.0000 | $27,500.00 | $120,000.0000 | $120,000.00 |
| 2025000 | REMOVAL & DISPOSAL OF EXISTING ASPHALT PAVEMENT | 240 | SY | $17.0000 | $4,080.00 | $45.0000 | $10,800.00 | $55.0000 | $13,200.00 | $25.0000 | $6,000.00 | $25.0000 | $6,000.00 | $15.0000 | $3,600.00 | $41.0000 | $9,840.00 | $38.4500 | $9,228.00 |
| 2031000 | UNCLASSIFIED EXCAVATION | 185 | CY | $61.0000 | $11,285.00 | $65.0000 | $12,025.00 | $89.0000 | $16,465.00 | $100.0000 | $18,500.00 | $200.0000 | $37,000.00 | $100.0000 | $18,500.00 | $30.0000 | $5,550.00 | $48.1000 | $8,898.50 |
| 2033000 | BORROW EXCAVATION | 1,225 | CY | $46.0000 | $56,350.00 | $45.0000 | $55,125.00 | $45.0000 | $55,125.00 | $59.5000 | $72,887.50 | $80.0000 | $98,000.00 | $30.0000 | $36,750.00 | $25.0000 | $30,625.00 | $108.1500 | $132,483.75 |
| 2081001 | FINE GRADING | 1,300 | SY | $8.2500 | $10,725.00 | $4.0000 | $5,200.00 | $7.0000 | $9,100.00 | $11.0000 | $14,300.00 | $6.0000 | $7,800.00 | $10.0000 | $13,000.00 | $13.0000 | $16,900.00 | $11.2000 | $14,560.00 |
| 3059900 | MAINTENANCE STONE | 60 | TON | $120.0000 | $7,200.00 | $65.0000 | $3,900.00 | $60.0000 | $3,600.00 | $50.0000 | $3,000.00 | $54.0000 | $3,240.00 | $60.0000 | $3,600.00 | $42.0000 | $2,520.00 | $111.8500 | $6,711.00 |
| 4011004 | LIQUID ASPHALT BINDER PG64-22 | 119 | TON | $750.0000 | $89,250.00 | $797.5000 | $94,902.50 | $1,000.0000 | $119,000.00 | $900.0000 | $107,100.00 | $900.0000 | $107,100.00 | $775.0000 | $92,225.00 | $896.0000 | $106,624.00 | $815.0000 | $96,985.00 |
| 4012080 | FULL DEPTH ASPH. PAV. PATCHING 8" UNIF | 150 | SY | $190.0000 | $28,500.00 | $214.5000 | $32,175.00 | $250.0000 | $37,500.00 | $300.0000 | $45,000.00 | $250.0000 | $37,500.00 | $253.7700 | $38,065.50 | $280.0000 | $42,000.00 | $252.5000 | $37,875.00 |
| 4013120 | MILLING EXISTING ASPHALT PAVEMENT 2.0" | 3,875 | SY | $4.2500 | $16,468.75 | $12.1000 | $46,887.50 | $5.5000 | $21,312.50 | $16.0000 | $62,000.00 | $9.0000 | $34,875.00 | $10.5600 | $40,920.00 | $190.4000 | $737,800.00 | $7.6500 | $29,643.75 |
| 4020310 | ASPHALT BASE COURSE - TYPE A | 341 | TON | $188.0000 | $64,108.00 | $269.5000 | $91,899.50 | $300.0000 | $102,300.00 | $190.0000 | $64,790.00 | $225.0000 | $76,725.00 | $122.2600 | $41,690.66 | $12.6000 | $4,296.60 | $210.0000 | $71,610.00 |
| 4030320 | ASPHALT INTERMEDIATE COURSE TYPE B | 113 | TON | $340.0000 | $38,420.00 | $310.2000 | $35,052.60 | $450.0000 | $50,850.00 | $200.0000 | $22,600.00 | $300.0000 | $33,900.00 | $231.2500 | $26,131.25 | $197.1000 | $22,272.30 | $237.5000 | $26,837.50 |
| 4040320 | ASPHALT SURFACE COURSE TYPE B | 1,710 | TON | $93.0000 | $159,030.00 | $144.1000 | $246,411.00 | $130.0000 | $222,300.00 | $165.0000 | $282,150.00 | $175.0000 | $299,250.00 | $230.2400 | $393,710.40 | $168.0000 | $287,280.00 | $172.5000 | $294,975.00 |
| 4040360 | ASPHALT SURFACE COURSE TYPE E | 108 | TON | $200.0000 | $21,600.00 | $357.5000 | $38,610.00 | $270.0000 | $29,160.00 | $260.0000 | $28,080.00 | $300.0000 | $32,400.00 | $242.8500 | $26,227.80 | $235.2000 | $25,401.60 | $235.0000 | $25,380.00 |
| 6011000 | TRAFFIC CONTROL | 1 | LS | $105,000.0000 | $105,000.00 | $112,500.0000 | $112,500.00 | $160,000.0000 | $160,000.00 | $169,750.0000 | $169,750.00 | $163,500.0000 | $163,500.00 | $535,000.0000 | $535,000.00 | $37,500.0000 | $37,500.00 | $472,500.0000 | $472,500.00 |
| 6051120 | PERMANENT CONSTRUCTION SIGNS (GROUND MOUNTED) | 368 | SF | $7.0000 | $2,576.00 | $12.1000 | $4,452.80 | $10.5000 | $3,864.00 | $12.6000 | $4,636.80 | $15.0000 | $5,520.00 | $10.9900 | $4,044.32 | $12.0000 | $4,416.00 | $6.3000 | $2,318.40 |
| 6092100 | TEMPORARY CLEAR PAVEMENT MARKERS MONO-DIR.- 4"X4" | 10 | EA | $8.0000 | $80.00 | $8.2500 | $82.50 | $8.2500 | $82.50 | $12.0000 | $120.00 | $9.5000 | $95.00 | $8.2500 | $82.50 | $35.0000 | $350.00 | $7.8900 | $78.90 |
| 6092150 | TEMPORARY YELLOW PAVEMENT MARKERS MONO-DIR.- 4"X4" | 20 | EA | $8.0000 | $160.00 | $8.2500 | $165.00 | $8.2500 | $165.00 | $12.0000 | $240.00 | $9.5000 | $190.00 | $8.2500 | $165.00 | $35.0000 | $700.00 | $7.9000 | $158.00 |
| 6092155 | TEMPORARY YELLOW PAVEMENT MARKERS BI-DIR.- 4"X4" | 60 | EA | $8.0000 | $480.00 | $8.2500 | $495.00 | $8.2500 | $495.00 | $12.0000 | $720.00 | $9.5000 | $570.00 | $8.2500 | $495.00 | $12.5000 | $750.00 | $7.9000 | $474.00 |
| 6240005 | 4" WHITE BROKEN LINES -(GAPS EXCLUDED)-FAST DRY PAINT | 690 | LF | $0.1600 | $110.40 | $0.1700 | $117.30 | $0.2000 | $138.00 | $0.6000 | $414.00 | $0.2500 | $172.50 | $0.1700 | $117.30 | $0.6500 | $448.50 | $0.1600 | $110.40 |
| 6240010 | 4" WHITE SOLID LINES (PVT. EDGE LINES)-FAST DRY PAINT | 390 | LF | $0.1600 | $62.40 | $0.1700 | $66.30 | $0.2000 | $78.00 | $0.6000 | $234.00 | $0.2500 | $97.50 | $0.1700 | $66.30 | $0.6500 | $253.50 | $0.1600 | $62.40 |
| 6240015 | 8"WHITE SOLID LINES (CROSSWALK& CHANNELIZATION)FAST DRY PAINT | 1,380 | LF | $0.2700 | $372.60 | $0.2800 | $386.40 | $0.3000 | $414.00 | $2.5000 | $3,450.00 | $0.4000 | $552.00 | $0.2800 | $386.40 | $0.8500 | $1,173.00 | $0.2500 | $345.00 |
| 6240025 | 24" WHITE SOLID LINES (STOP/DIAGONAL LINES)-FAST DRY PAINT | 2,535 | LF | $1.6000 | $4,056.00 | $1.6500 | $4,182.75 | $1.6500 | $4,182.75 | $1.9500 | $4,943.25 | $2.0000 | $5,070.00 | $1.6500 | $4,182.75 | $2.0500 | $5,196.75 | $1.6000 | $4,056.00 |
| 6240110 | 4"YELLOW SOLID LINE(PVT.EDGE&NO PASSING ZONE)-FAST DRY PAINT | 8,700 | LF | $0.1600 | $1,392.00 | $0.1700 | $1,479.00 | $0.2000 | $1,740.00 | $0.6000 | $5,220.00 | $0.2000 | $1,740.00 | $0.1700 | $1,479.00 | $0.5000 | $4,350.00 | $0.1600 | $1,392.00 |
| 6271005 | 4" WHITE BROKEN LINES(GAPS EXCL.)THERMOPLASTIC- 90 MIL. | 230 | LF | $1.3500 | $310.50 | $1.3800 | $317.40 | $1.4000 | $322.00 | $1.9500 | $448.50 | $1.7500 | $402.50 | $1.3800 | $317.40 | $3.0000 | $690.00 | $1.3000 | $299.00 |
| 6271010 | 4" WHITE SOLID LINES (PVT. EDGE LINES) THERMO.- 90 MIL. | 130 | LF | $1.3500 | $175.50 | $1.3800 | $179.40 | $1.4000 | $182.00 | $1.9500 | $253.50 | $1.7500 | $227.50 | $1.3800 | $179.40 | $3.0000 | $390.00 | $1.3000 | $169.00 |
| 6271015 | 8" WHITE SOLID LINES THERMOPLASTIC - 125 MIL. | 460 | LF | $3.2500 | $1,495.00 | $3.3000 | $1,518.00 | $3.3000 | $1,518.00 | $4.8000 | $2,208.00 | $3.7500 | $1,725.00 | $3.3000 | $1,518.00 | $3.5000 | $1,610.00 | $3.1500 | $1,449.00 |
| 6271025 | 24" WHITE SOLID LINES (STOP/DIAG LINES)-THERMO.-125 MIL | 845 | LF | $9.5000 | $8,027.50 | $9.9000 | $8,365.50 | $10.0000 | $8,450.00 | $12.0000 | $10,140.00 | $11.5000 | $9,717.50 | $9.9000 | $8,365.50 | $8.0000 | $6,760.00 | $9.4500 | $7,985.25 |
| 6271074 | 4" YELLOW SOLID LINES(PVT.EDGE LINES) THERMO- 90 MIL. | 2,900 | LF | $1.3500 | $3,915.00 | $1.3800 | $4,002.00 | $1.4000 | $4,060.00 | $1.5800 | $4,582.00 | $1.7500 | $5,075.00 | $1.3800 | $4,002.00 | $0.4500 | $1,305.00 | $1.3000 | $3,770.00 |
| 6300005 | PERMANENT CLEAR PAVEMENT MARKERS- MONO-DIR.- 4"X4" | 10 | EA | $8.0000 | $80.00 | $8.2500 | $82.50 | $8.2500 | $82.50 | $12.0000 | $120.00 | $9.5000 | $95.00 | $8.2500 | $82.50 | $15.0000 | $150.00 | $7.9000 | $79.00 |
| 6301005 | PERMANENT YELLOW PAVEMENT MARKERS MONO-DIR.- 4"X 4" PERM. YEL. | 20 | EA | $8.0000 | $160.00 | $8.2500 | $165.00 | $8.2500 | $165.00 | $12.0000 | $240.00 | $9.5000 | $190.00 | $8.2500 | $165.00 | $15.0000 | $300.00 | $7.9000 | $158.00 |
| 6301100 | PERMANENT YELLOW PAVEMENT MARKERS BI-DIR.- 4"X4" | 60 | EA | $8.0000 | $480.00 | $8.2500 | $495.00 | $8.2500 | $495.00 | $12.0000 | $720.00 | $9.5000 | $570.00 | $8.2500 | $495.00 | $7.9000 | $474.00 | $7.9000 | $474.00 |
| 6510105 | FLAT SHEET, TYPE III, FIXED SZ. & MSG. SIGN | 10 | SF | $30.0000 | $300.00 | $27.5000 | $275.00 | $38.5000 | $385.00 | $25.0000 | $250.00 | $80.0000 | $800.00 | $27.4500 | $274.50 | $28.0000 | $280.00 | $18.9500 | $189.50 |
| 6531210 | U-SECTION POST FOR SIGN SUPPORTS - 3P | 24 | LF | $9.0000 | $216.00 | $22.0000 | $528.00 | $35.0000 | $840.00 | $18.5000 | $444.00 | $35.0000 | $840.00 | $16.4900 | $395.76 | $17.5000 | $420.00 | $16.8500 | $404.40 |
| 6750275 | FURNISH & INSTALL 1.0" SCHEDULE 80 PVC CONDUIT | 320 | LF | $15.0000 | $4,800.00 | $19.9200 | $6,374.40 | $20.0000 | $6,400.00 | $15.9200 | $5,094.40 | $24.5000 | $7,840.00 | $19.9200 | $6,374.40 | $13.4400 | $4,300.80 | $19.0000 | $6,080.00 |
| 6750278 | FURNISH & INSTALL 2.0" SCHEDULE 80 PVC CONDUIT | 700 | LF | $19.0000 | $13,300.00 | $20.7100 | $14,497.00 | $20.8000 | $14,560.00 | $20.5500 | $14,385.00 | $25.5000 | $17,850.00 | $20.7100 | $14,497.00 | $16.2400 | $11,368.00 | $19.8000 | $13,860.00 |
| 675027O | FURNISH & INSTALL 6.0" SCHEDULE 80 PVC CONDUIT | 70 | LF | $43.0000 | $3,010.00 | $44.0000 | $3,080.00 | $82.0000 | $5,740.00 | $80.0000 | $5,600.00 | $150.0000 | $10,500.00 | $50.0000 | $3,500.00 | $112.0000 | $7,840.00 | $31.6000 | $2,212.00 |
| 6770388 | FURNISH & INSTALL NO. 14 COPPER WIRE, 4 CONDUCTOR - BLACK | 1,350 | LF | $4.3500 | $5,872.50 | $5.8200 | $7,857.00 | $5.8500 | $7,897.50 | $3.5000 | $4,725.00 | $6.2500 | $8,437.50 | $5.8200 | $7,857.00 | $5.0400 | $6,804.00 | $5.6000 | $7,560.00 |
| 6770389 | FURNISH & INSTALL NO. 14 COPPER WIRE, 4 CONDUCTOR - GRAY | 2,360 | LF | $4.3500 | $10,266.00 | $5.9300 | $13,994.80 | $5.8500 | $13,806.00 | $5.5000 | $12,980.00 | $6.2500 | $14,750.00 | $5.9300 | $13,994.80 | $5.0400 | $11,894.40 | $5.6500 | $13,334.00 |
| 6770393 | FURNISH & INSTALL NO. 14 COPPER WIRE, 8 CONDUCTOR (BLACK) | 500 | LF | $5.4500 | $2,725.00 | $6.1500 | $3,075.00 | $6.2000 | $3,100.00 | $6.0000 | $3,000.00 | $6.7500 | $3,375.00 | $6.1500 | $3,075.00 | $5.6000 | $2,800.00 | $5.9000 | $2,950.00 |
| 6770413 | FURNISH & INSTL NO. 14 COPPER WIRE,1-CONDUCTOR FOR LOOP WIRE | 1,630 | LF | $3.2500 | $5,297.50 | $1.2700 | $2,070.10 | $1.2500 | $2,037.50 | $1.9800 | $3,227.40 | $2.0000 | $3,260.00 | $1.2700 | $2,070.10 | $1.6800 | $2,738.40 | $1.2000 | $1,956.00 |
| 6780495 | SAWCUT FOR LOOP DETECTOR | 630 | LF | $9.5000 | $5,985.00 | $10.9500 | $6,898.50 | $11.0000 | $6,930.00 | $8.9000 | $5,607.00 | $10.0000 | $6,300.00 | $10.9500 | $6,898.50 | $8.4000 | $5,292.00 | $10.5000 | $6,615.00 |
| 6800499 | FURNISH & INSTALL ELECTRICAL SERVICE FOR TRAFFIC SIGNAL | 1 | EA | $2,700.0000 | $2,700.00 | $1,745.6700 | $1,745.67 | $1,750.0000 | $1,750.00 | $2,450.0000 | $2,450.00 | $2,700.0000 | $2,700.00 | $1,745.6700 | $1,745.67 | $2,240.0000 | $2,240.00 | $1,670.0000 | $1,670.00 |
| 6800518 | F&I-13"X24"X18"D.ELEC.FLUSH UNDGRD.ENCLOS- (STR.POLY.CONC.)HD | 7 | EA | $925.0000 | $6,475.00 | $914.2900 | $6,400.03 | $920.0000 | $6,440.00 | $765.0000 | $5,355.00 | $900.0000 | $6,300.00 | $914.2900 | $6,400.03 | $728.0000 | $5,096.00 | $875.0000 | $6,125.00 |
| 680052C | F&I-17"X30"X24"D.ELEC.FLUSH UNDGRD.ENCLOS- (STR.POLY.CONC.)HD | 1 | EA | $1,100.0000 | $1,100.00 | $1,156.1000 | $1,156.10 | $1,160.0000 | $1,160.00 | $1,100.0000 | $1,100.00 | $1,250.0000 | $1,250.00 | $1,156.1000 | $1,156.10 | $1,064.0000 | $1,064.00 | $1,100.0000 | $1,100.00 |
| 6825092 | FURNISH & INSTALL 3/8" GALVANIZED STEEL CABLE | 350 | LF | $9.5000 | $3,325.00 | $10.4000 | $3,640.00 | $10.5000 | $3,675.00 | $8.5000 | $2,975.00 | $10.0000 | $3,500.00 | $10.4000 | $3,640.00 | $8.4000 | $2,940.00 | $9.9500 | $3,482.50 |
| 6825484 | FURNISH & INSTALL 10' BREAK- AWAY ALUM PEDESTAL POLE AND BASE | 4 | EA | $2,700.0000 | $10,800.00 | $2,072.9500 | $8,291.80 | $2,080.0000 | $8,320.00 | $2,300.0000 | $9,200.00 | $2,700.0000 | $10,800.00 | $2,072.9500 | $8,291.80 | $2,240.0000 | $8,960.00 | $1,980.0000 | $7,920.00 |
| 6845511 | F&I - CONTR 332/336 CABINET ASSEMBLY - BASE MOUNTED 123 | 1 | EA | $26,000.0000 | $26,000.00 | $26,180.0000 | $26,180.00 | $26,275.0000 | $26,275.00 | $28,000.0000 | $28,000.00 | $32,000.0000 | $32,000.00 | $26,180.0000 | $26,180.00 | $28,000.0000 | $28,000.00 | $25,000.0000 | $25,000.00 |
| 6865723 | FURNISH & INSTALL - 12" 3 SECTION SIGNAL HEAD 123 | 8 | EA | $925.0000 | $7,400.00 | $880.0000 | $7,040.00 | $885.0000 | $7,080.00 | $1,200.0000 | $9,600.00 | $1,400.0000 | $11,200.00 | $880.0000 | $7,040.00 | $1,176.0000 | $9,408.00 | $845.0000 | $6,760.00 |
| 6865782 | F&I - 1-WAY-1SECT.HAND/MAN COUNTDOWN PEDESTRIAN SIGNAL HEAD | 8 | EA | $925.0000 | $7,400.00 | $896.1000 | $7,168.80 | $990.0000 | $7,920.00 | $1,188.0000 | $9,504.00 | $1,350.0000 | $10,800.00 | $985.7100 | $7,885.68 | $1,120.0000 | $8,960.00 | $945.0000 | $7,560.00 |
| 6865797 | F&I-PED PUSH BUT.SOLID STATE W/ TONE ASSEM 9"X15"&SIGN (R- 10-3E or R10-4a) | 8 | EA | $490.0000 | $3,920.00 | $622.2000 | $4,977.60 | $690.0000 | $5,520.00 | $1,200.0000 | $9,600.00 | $675.0000 | $5,400.00 | $684.4200 | $5,475.36 | $560.0000 | $4,480.00 | $655.0000 | $5,240.00 |
| 6865834 | BACKPLATE W/ RETROREFL.BORDERS FOR TRAFF. SIG. | 8 | EA | $325.0000 | $2,600.00 | $330.6000 | $2,644.80 | $365.0000 | $2,920.00 | $360.0000 | $2,880.00 | $400.0000 | $3,200.00 | $363.6600 | $2,909.28 | $336.0000 | $2,688.00 | $348.0000 | $2,784.00 |
| 6887951 | FURNISH & INSTALL CONCRETE CABINET FOUNDATION | 1 | EA | $2,700.0000 | $2,700.00 | $1,479.0000 | $1,479.00 | $1,630.0000 | $1,630.00 | $2,900.0000 | $2,900.00 | $3,375.0000 | $3,375.00 | $1,626.9000 | $1,626.90 | $2,800.0000 | $2,800.00 | $1,550.0000 | $1,550.00 |
| 7142513 | 18" R. C. PIPE CUL. BEVELED END SECTN-CL 3 | 2 | EA | $1,600.0000 | $3,200.00 | $800.0000 | $1,600.00 | $3,300.0000 | $6,600.00 | $1,000.0000 | $2,000.00 | $900.0000 | $1,800.00 | $1,500.0000 | $3,000.00 | $450.0000 | $900.00 | $570.0000 | $1,140.00 |
| 7143618 | 18" SMOOTH WALL PIPE | 488 | LF | $210.0000 | $102,480.00 | $150.0000 | $73,200.00 | $135.0000 | $65,880.00 | $240.0000 | $117,120.00 | $86.0000 | $41,968.00 | $147.8200 | $72,136.16 | $127.0000 | $61,976.00 | $172.5000 | $84,180.00 |
| 7191205 | CATCH BASIN -TYPE 9 | 1 | EA | $3,700.0000 | $3,700.00 | $5,400.0000 | $5,400.00 | $6,700.0000 | $6,700.00 | $3,950.0000 | $3,950.00 | $4,600.0000 | $4,600.00 | $5,000.0000 | $5,000.00 | $4,900.0000 | $4,900.00 | $12,500.0000 | $12,500.00 |
| 7191605 | CATCH BASIN -TYPE 16 | 7 | EA | $6,900.0000 | $48,300.00 | $6,800.0000 | $47,600.00 | $8,000.0000 | $56,000.00 | $7,400.0000 | $51,800.00 | $7,700.0000 | $53,900.00 | $6,500.0000 | $45,500.00 | $6,950.0000 | $48,650.00 | $10,200.0000 | $71,400.00 |
| 7192105 | MANHOLE | 1 | EA | $3,600.0000 | $3,600.00 | $5,800.0000 | $5,800.00 | $5,800.0000 | $5,800.00 | $3,900.0000 | $3,900.00 | $4,500.0000 | $4,500.00 | $5,000.0000 | $5,000.00 | $4,850.0000 | $4,850.00 | $11,000.0000 | $11,000.00 |
| 719619L | 36" X 60" JUNCTION BOX (TOP ONLY) | 2 | EA | $3,100.0000 | $6,200.00 | $2,500.0000 | $5,000.00 | $2,375.0000 | $4,750.00 | $2,600.0000 | $5,200.00 | $3,000.0000 | $6,000.00 | $900.0000 | $1,800.00 | $2,900.0000 | $5,800.00 | $6,500.0000 | $13,000.00 |
| 71961AA | 60" X 60" JUNCTION BOX (TOP ONLY) | 1 | EA | $4,400.0000 | $4,400.00 | $3,500.0000 | $3,500.00 | $1,405.0000 | $1,405.00 | $3,100.0000 | $3,100.00 | $3,500.0000 | $3,500.00 | $1,100.0000 | $1,100.00 | $3,500.0000 | $3,500.00 | $7,200.0000 | $7,200.00 |
| 7199200 | 4' SLOPE FLUME (6" CURB STYLE WITH CUTOFFS) | 32 | LF | $215.0000 | $6,880.00 | $200.0000 | $6,400.00 | $250.0000 | $8,000.00 | $1,250.0000 | $40,000.00 | $3,000.0000 | $96,000.00 | $180.0000 | $5,760.00 | $2,800.0000 | $89,600.00 | $300.0000 | $9,600.00 |
| 7201000 | CONCRETE CURB (9" X 15") | 12 | LF | $70.0000 | $840.00 | $65.0000 | $780.00 | $54.5000 | $654.00 | $85.0000 | $1,020.00 | $100.0000 | $1,200.00 | $100.0000 | $1,200.00 | $84.0000 | $1,008.00 | $160.0000 | $1,920.00 |
| 7201100 | CONCRETE CURB (TRANSITION) | 12 | LF | $38.0000 | $456.00 | $35.0000 | $420.00 | $54.5000 | $654.00 | $85.0000 | $1,020.00 | $100.0000 | $1,200.00 | $100.0000 | $1,200.00 | $84.0000 | $1,008.00 | $160.0000 | $1,920.00 |
| 7203210 | CONCRETE CURB AND GUTTER(2'-0") VERTICAL FACE | 2,060 | LF | $44.5000 | $91,670.00 | $35.0000 | $72,100.00 | $42.4000 | $87,344.00 | $43.5000 | $89,610.00 | $42.0000 | $86,520.00 | $65.0000 | $133,900.00 | $39.2000 | $80,752.00 | $55.0000 | $113,300.00 |
| 7204100 | CONCRETE SIDEWALK(4" UNIFORM) | 580 | SY | $115.0000 | $66,700.00 | $95.0000 | $55,100.00 | $75.0000 | $43,500.00 | $95.0000 | $55,100.00 | $97.0000 | $56,260.00 | $89.0000 | $51,620.00 | $97.3000 | $56,434.00 | $125.0000 | $72,500.00 |
| 7204900 | DETECTABLE WARNING MATERIAL | 105 | SF | $49.0000 | $5,145.00 | $45.0000 | $4,725.00 | $50.0000 | $5,250.00 | $170.0000 | $17,850.00 | $180.0000 | $18,900.00 | $41.0000 | $4,305.00 | $168.0000 | $17,640.00 | $65.0000 | $6,825.00 |
| 7205000 | CONCRETE DRIVEWAY(6" UNIFORM) | 150 | SY | $155.0000 | $23,250.00 | $145.0000 | $21,750.00 | $150.0000 | $22,500.00 | $135.0000 | $20,250.00 | $128.0000 | $19,200.00 | $110.0000 | $16,500.00 | $130.0000 | $19,500.00 | $127.5000 | $19,125.00 |
| 7209000 | PEDESTRIAN RAMP CONSTRUCTION | 170 | SY | $135.0000 | $22,950.00 | $125.0000 | $21,250.00 | $150.0000 | $25,500.00 | $330.0000 | $56,100.00 | $375.0000 | $63,750.00 | $115.0000 | $19,550.00 | $336.0000 | $57,120.00 | $130.0000 | $22,100.00 |
| 8041020 | RIP-RAP (CLASS B) | 30 | TON | $185.0000 | $5,550.00 | $85.0000 | $2,550.00 | $125.0000 | $3,750.00 | $125.0000 | $3,750.00 | $88.0000 | $2,640.00 | $75.0000 | $2,250.00 | $90.0000 | $2,700.00 | $225.0000 | $6,750.00 |
| 8048210 | GEOTEXTILE FOR EROSION CONTROL UNDER RIPRAP(CLASS 2)TYPE C | 36 | SY | $20.5000 | $738.00 | $15.0000 | $540.00 | $12.0000 | $432.00 | $6.0000 | $216.00 | $20.0000 | $720.00 | $3.0000 | $108.00 | $4.2000 | $151.20 | $37.8000 | $1,360.80 |
| 8091010 | RIGHT OF WAY MARKER(REBAR AND CAP) | 19 | EA | $135.0000 | $2,565.00 | $200.0000 | $3,800.00 | $350.0000 | $6,650.00 | $200.0000 | $3,800.00 | $275.0000 | $5,225.00 | $110.0000 | $2,090.00 | $165.0000 | $3,135.00 | $390.0000 | $7,410.00 |
| 8091050 | RIGHT OF WAY PLAT | 1 | LS | $1,900.0000 | $1,900.00 | $5,500.0000 | $5,500.00 | $3,865.0000 | $3,865.00 | $4,500.0000 | $4,500.00 | $6,000.0000 | $6,000.00 | $11,660.0000 | $11,660.00 | $3,500.0000 | $3,500.00 | $6,525.0000 | $6,525.00 |
| 8100101 | PERMANENT GRASSING FOR SMALL PROJECTS | 0.6 | ACRE | $6,500.0000 | $3,900.00 | $4,000.0000 | $2,400.00 | $3,865.0000 | $2,319.00 | $6,000.0000 | $3,600.00 | $4,600.0000 | $2,760.00 | $2,200.0000 | $1,320.00 | $3,650.0000 | $2,190.00 | $6,550.0000 | $3,930.00 |
| 8151201 | HYDRAULIC EROSION CONTROL PRODUCT (HECP) - TYPE 1 | 0.83 | ACRE | $1,550.0000 | $1,286.50 | $4,500.0000 | $3,735.00 | $2,760.0000 | $2,290.80 | $3,000.0000 | $2,490.00 | $1,900.0000 | $1,577.00 | $3,000.0000 | $2,490.00 | $1,850.0000 | $1,535.50 | $1,175.0000 | $975.25 |
| 8151203 | HYDRAULIC EROSION CONTROL PRODUCT (HECP) - TYPE 3 | 0.83 | ACRE | $3,500.0000 | $2,905.00 | $4,500.0000 | $3,735.00 | $4,140.0000 | $3,436.20 | $6,000.0000 | $4,980.00 | $3,800.0000 | $3,154.00 | $3,500.0000 | $2,905.00 | $4,100.0000 | $3,403.00 | $3,600.0000 | $2,988.00 |
| 8152004 | INLET STRUCTURE FILTER - TYPE F (WEIGHTED) | 56 | LF | $16.0000 | $896.00 | $12.0000 | $672.00 | $18.0000 | $1,008.00 | $16.8000 | $940.80 | $25.0000 | $1,400.00 | $12.0000 | $672.00 | $12.0000 | $672.00 | $11.2000 | $627.20 |
| 8152006 | INLET STRUCTURE FILTER- TYPE F (NON-WEIGHTED) | 56 | LF | $16.0000 | $896.00 | $12.0000 | $672.00 | $14.5000 | $812.00 | $16.8000 | $940.80 | $20.0000 | $1,120.00 | $12.0000 | $672.00 | $10.0000 | $560.00 | $11.2000 | $627.20 |
| 8152007 | SEDIMENT TUBES FOR DITCH CHECKS | 80 | LF | $16.0000 | $1,280.00 | $8.0000 | $640.00 | $12.0000 | $960.00 | $16.8000 | $1,344.00 | $20.0000 | $1,600.00 | $10.0000 | $800.00 | $9.0000 | $720.00 | $11.2000 | $896.00 |
| 8153000 | SILT FENCE | 1,700 | LF | $3.2500 | $5,525.00 | $4.5000 | $7,650.00 | $5.5000 | $9,350.00 | $3.8500 | $6,545.00 | $4.0000 | $6,800.00 | $5.0000 | $8,500.00 | $3.5000 | $5,950.00 | $3.8500 | $6,545.00 |
| 8154010 | CLEANING SILT BASINS | 196 | CY | $13.5000 | $2,646.00 | $3.0000 | $588.00 | $45.0000 | $8,820.00 | $6.0000 | $1,176.00 | $80.0000 | $15,680.00 | $65.0000 | $12,740.00 | $10.0000 | $1,960.00 | $89.5000 | $17,542.00 |
| 8156490 | STABILIZED CONSTRUCTION ENTRANCE | 550 | SY | $33.0000 | $18,150.00 | $1.0000 | $550.00 | $8.0000 | $4,400.00 | $25.8300 | $14,206.50 | $31.0000 | $17,050.00 | $10.0000 | $5,500.00 | $19.0000 | $10,450.00 | $31.5000 | $17,325.00 |
Source: public South Carolina DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.