Virginia DOT · Bid Tabulation
Contract C0000121531B68
BRIDGE REPLACEMENT OVER SEACOCK SWAMP
- County
- SOUTHAMPTON
- District
- Hampton Roads
- Letting
- March 25, 2026
- Bidders
- 7
Apparent low bid
CROFTON CONSTRUCTION SERVICES, INCORPORATED
$3,979,800.00
Other bidders
ALLAN MYERS VA, INC.
$4,087,777.00
CATON CONSTRUCTION GROUP, INC.
$4,696,300.00
ABERNATHY CONSTRUCTION CORPORATION
$4,946,793.70
KOKOSING CONSTRUCTION COMPANY, INC.
$5,734,812.70
CROWDER CONSTRUCTION COMPANY
$6,017,820.10
RBA ENGINEERING INTERNATIONAL, PLLC
$6,296,514.00
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | CROFTON CONSTRUCTION SERVICES, INCORPORATED $3,979,800.00 | ALLAN MYERS VA, INC. $4,087,777.00 | CATON CONSTRUCTION GROUP, INC. $4,696,300.00 | ABERNATHY CONSTRUCTION CORPORATION $4,946,793.70 | KOKOSING CONSTRUCTION COMPANY, INC. $5,734,812.70 | CROWDER CONSTRUCTION COMPANY $6,017,820.10 | RBA ENGINEERING INTERNATIONAL, PLLC $6,296,514.00 | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 301SD20-0002 | CLEARING AND GRUBBING | 0.5 | ACRE | $2.0000 | $1.00 | $10,000.0000 | $5,000.00 | $92,000.0000 | $46,000.00 | $155,000.0000 | $77,500.00 | $206,786.0000 | $103,393.00 | $60,000.0000 | $30,000.00 | $31,150.0000 | $15,575.00 |
| 303SD20-0001 | REGULAR EXCAVATION | 386 | CY | $131.0000 | $50,566.00 | $67.0000 | $25,862.00 | $187.8700 | $72,517.82 | $155.0000 | $59,830.00 | $145.0000 | $55,970.00 | $300.0000 | $115,800.00 | $149.0000 | $57,514.00 |
| 303SD20-0028 | DEWATERING BASIN EC-8 | 2 | EA | $3,150.0000 | $6,300.00 | $1,512.9100 | $3,025.82 | $2,550.0000 | $5,100.00 | $850.0000 | $1,700.00 | $2,350.0000 | $4,700.00 | $8,500.0000 | $17,000.00 | $605.0000 | $1,210.00 |
| 303SD20-0029 | SILTATION CONTROL EXCAVATION | 64 | CY | $1.0000 | $64.00 | $1.0000 | $64.00 | $221.0400 | $14,146.56 | $24.0000 | $1,536.00 | $1.0000 | $64.00 | $150.0000 | $9,600.00 | $150.0000 | $9,600.00 |
| 303SD20-0033 | TEMP. SILT FENCE TYPE B | 1,070 | LF | $11.5000 | $12,305.00 | $12.0000 | $12,840.00 | $15.0000 | $16,050.00 | $9.0000 | $9,630.00 | $25.0000 | $26,750.00 | $3.5000 | $3,745.00 | $7.0000 | $7,490.00 |
| 308SD20-0006 | AGGR. MATL. NO. 21A OR 21B | 51 | TON | $240.0000 | $12,240.00 | $175.0000 | $8,925.00 | $476.3400 | $24,293.34 | $101.0000 | $5,151.00 | $310.0000 | $15,810.00 | $232.2200 | $11,843.22 | $64.0000 | $3,264.00 |
| 315SD20-0008 | ASPHALT CONCRETE TY. SM- 9.5D CONST | 26 | TON | $232.0000 | $6,032.00 | $400.0000 | $10,400.00 | $352.4500 | $9,163.70 | $370.0000 | $9,620.00 | $318.4000 | $8,278.40 | $180.2500 | $4,686.50 | $243.0000 | $6,318.00 |
| 315SD20-0010 | ASPHALT CONCRETE BM-25.0 | 62 | TON | $285.0000 | $17,670.00 | $300.0000 | $18,600.00 | $260.0000 | $16,120.00 | $360.0000 | $22,320.00 | $310.7000 | $19,263.40 | $221.4500 | $13,729.90 | $298.0000 | $18,476.00 |
| 401SD20-0001 | STRUCTURE EXCAVATION CONST. | 560 | CY | $41.0000 | $22,960.00 | $100.0000 | $56,000.00 | $55.0000 | $30,800.00 | $85.0000 | $47,600.00 | $225.0000 | $126,000.00 | $150.0000 | $84,000.00 | $149.0000 | $83,440.00 |
| 401SD20-0002 | SELECT BACKFILL ABUTMENT ZONE | 1,294 | TON | $80.0000 | $103,520.00 | $70.0000 | $90,580.00 | $75.0000 | $97,050.00 | $88.0000 | $113,872.00 | $150.0000 | $194,100.00 | $125.0000 | $161,750.00 | $81.0000 | $104,814.00 |
| 401SD20-0004 | GEOCOMPOSITE WALL DRAIN | 40 | SY | $41.0000 | $1,640.00 | $100.0000 | $4,000.00 | $55.0000 | $2,200.00 | $55.0000 | $2,200.00 | $300.0000 | $12,000.00 | $110.0000 | $4,400.00 | $33.0000 | $1,320.00 |
| 401SD20-0007 | COFFERDAM | 7 | EA | $41,000.0000 | $287,000.00 | $1,000.0000 | $7,000.00 | $94,172.0700 | $659,204.49 | $45,000.0000 | $315,000.00 | $2,500.0000 | $17,500.00 | $102,150.0000 | $715,050.00 | $196,361.0000 | $1,374,527.00 |
| 401SX20-0001 | NS BRIDGE TEMPORARY WORK BRIDGE | 1 | LS | $1.0000 | $1.00 | $5,000.0000 | $5,000.00 | $797,925.4500 | $797,925.45 | $675,000.0000 | $675,000.00 | $1,000.0000 | $1,000.00 | $250,000.0000 | $250,000.00 | $939,357.0000 | $939,357.00 |
| 403SD20-0004 | DYNAMIC PILE TEST | 4 | EA | $4,200.0000 | $16,800.00 | $3,202.2100 | $12,808.84 | $7,500.0000 | $30,000.00 | $7,400.0000 | $29,600.00 | $2,215.0000 | $8,860.00 | $25,000.0000 | $100,000.00 | $6,200.0000 | $24,800.00 |
| 403SD20-0014 | PRESTRESSED CONCRETE STEEL STRAND PILES 18” | 1,690 | LF | $187.0000 | $316,030.00 | $200.0000 | $338,000.00 | $140.3600 | $237,208.40 | $158.0000 | $267,020.00 | $315.0000 | $532,350.00 | $56.0000 | $94,640.00 | $386.0000 | $652,340.00 |
| 403SD20-0016 | PRESTRESSED CONCRETE STEEL STRAND PILES 24” | 608 | LF | $234.0000 | $142,272.00 | $230.0000 | $139,840.00 | $215.9500 | $131,297.60 | $302.0000 | $183,616.00 | $700.0000 | $425,600.00 | $97.0000 | $58,976.00 | $464.0000 | $282,112.00 |
| 403SD20-0044 | DRIVING TEST FOR 18" PRESTR. CONC. PILE | 150 | LF | $240.0000 | $36,000.00 | $800.0000 | $120,000.00 | $164.7600 | $24,714.00 | $221.0000 | $33,150.00 | $275.0000 | $41,250.00 | $56.0000 | $8,400.00 | $42.0000 | $6,300.00 |
| 403SD20-0051 | DRIVING TEST FOR 24" PRESTR. CONC. PILE | 172 | LF | $297.0000 | $51,084.00 | $1,000.0000 | $172,000.00 | $223.6000 | $38,459.20 | $295.0000 | $50,740.00 | $550.0000 | $94,600.00 | $97.0000 | $16,684.00 | $37.0000 | $6,364.00 |
| 404SD20-0001 | CONCRETE CLASS B2 | 60 | CY | $635.0000 | $38,100.00 | $440.0000 | $26,400.00 | $590.7000 | $35,442.00 | $1,400.0000 | $84,000.00 | $625.0000 | $37,500.00 | $2,495.0600 | $149,703.60 | $515.0000 | $30,900.00 |
| 404SD20-0007 | CONC. CL. A4 MOD. LTWT LOW SHRINK., SPR. STRUCT. CONST. | 132 | CY | $2,610.0000 | $344,520.00 | $750.0000 | $99,000.00 | $1,700.0000 | $224,400.00 | $2,200.0000 | $290,400.00 | $1,500.0000 | $198,000.00 | $4,500.0000 | $594,000.00 | $857.0000 | $113,124.00 |
| 404SD20-0009 | BRIDGE DECK GROOVING CONST. | 522 | SY | $72.0000 | $37,584.00 | $10.0000 | $5,220.00 | $13.5000 | $7,047.00 | $20.0000 | $10,440.00 | $12.2500 | $6,394.50 | $40.0000 | $20,880.00 | $31.0000 | $16,182.00 |
| 404SD20-0010 | COVER DEPTH SURVEY CONST. | 522 | SY | $11.0000 | $5,742.00 | $5.0000 | $2,610.00 | $8.6200 | $4,499.64 | $9.0000 | $4,698.00 | $6.7000 | $3,497.40 | $5.1500 | $2,688.30 | $12.0000 | $6,264.00 |
| 404SD20-0011 | CONCRETE CLASS A3, SUBSTRUCT. CONST. | 146.4 | CY | $2,345.0000 | $343,308.00 | $2,300.0000 | $336,720.00 | $1,700.0000 | $248,880.00 | $2,610.0000 | $382,104.00 | $3,100.0000 | $453,840.00 | $4,000.0000 | $585,600.00 | $1,075.0000 | $157,380.00 |
| 404SP20-0003 | VA ADJACENT MEMBER CONN. BLOCK-OUTS | 226 | CF | $385.0000 | $87,010.00 | $422.0000 | $95,372.00 | $576.4100 | $130,268.66 | $790.0000 | $178,540.00 | $550.0000 | $124,300.00 | $634.8100 | $143,467.06 | $189.0000 | $42,714.00 |
| 405SX20-0004 | NS PRESTRESSED CONCRETE SLAB 3'- 10"X18"X(+55'-60') | 21 | EA | $27,180.0000 | $570,780.00 | $25,000.0000 | $525,000.00 | $36,600.0000 | $768,600.00 | $25,100.0000 | $527,100.00 | $35,000.0000 | $735,000.00 | $45,000.0000 | $945,000.00 | $28,525.0000 | $599,025.00 |
| 406SD20-0003 | CR REINF. STEEL CL. I SPR. STRUCT. CONST. | 15,834 | LB | $4.0000 | $63,336.00 | $3.2500 | $51,460.50 | $3.2500 | $51,460.50 | $3.7000 | $58,585.80 | $4.7500 | $75,211.50 | $5.0000 | $79,170.00 | $4.0000 | $63,336.00 |
| 406SD20-0006 | REINFORCING STEEL SUBSTRUCT. CONST. | 1,815 | LB | $3.0000 | $5,445.00 | $5.0000 | $9,075.00 | $2.3100 | $4,192.65 | $10.1000 | $18,331.50 | $2.6500 | $4,809.75 | $2.0000 | $3,630.00 | $5.0000 | $9,075.00 |
| 406SD20-0008 | CR REINF. STEEL CL. I SUBSTRUCT. CONST. | 19,528 | LB | $4.0000 | $78,112.00 | $3.2500 | $63,466.00 | $3.2500 | $63,466.00 | $3.7000 | $72,253.60 | $5.5000 | $107,404.00 | $5.0000 | $97,640.00 | $4.0000 | $78,112.00 |
| 410SD20-0010 | RAILING KANSAS CORRAL 32" W/OUT CURB CONST. | 350 | LF | $686.0000 | $240,100.00 | $250.0000 | $87,500.00 | $390.0000 | $136,500.00 | $805.0000 | $281,750.00 | $700.0000 | $245,000.00 | $365.0000 | $127,750.00 | $123.0000 | $43,050.00 |
| 413SX20-0002 | NS DISM. & REM. EXIST. STR. NO.6018 | 1 | LS | $406,439.0000 | $406,439.00 | $1,112,117.3400 | $1,112,117.34 | $160,000.0000 | $160,000.00 | $590,000.0000 | $590,000.00 | $1,277,000.0000 | $1,277,000.00 | $855,078.8900 | $855,078.89 | $489,227.0000 | $489,227.00 |
| 413SX20-0003 | NS ENV.& WORKER PROTECT. (STR. NO. 6018) | 1 | LS | $20,000.0000 | $20,000.00 | $122,190.0000 | $122,190.00 | $6,000.0000 | $6,000.00 | $9,900.0000 | $9,900.00 | $1,500.0000 | $1,500.00 | $50,000.0000 | $50,000.00 | $60,188.0000 | $60,188.00 |
| 413SX20-0004 | NS MATERIAL DISPOSAL (STR. NO. 6018) | 1 | LS | $93,000.0000 | $93,000.00 | $3,000.0000 | $3,000.00 | $13,998.5300 | $13,998.53 | $3,600.0000 | $3,600.00 | $1,500.0000 | $1,500.00 | $50,000.0000 | $50,000.00 | $57,212.0000 | $57,212.00 |
| 414SD20-0008 | DRY RIPRAP CL. AI | 5 | TON | $380.0000 | $1,900.00 | $450.0000 | $2,250.00 | $750.0000 | $3,750.00 | $204.0000 | $1,020.00 | $380.0000 | $1,900.00 | $366.6900 | $1,833.45 | $209.0000 | $1,045.00 |
| 414SD20-0012 | DRY RIPRAP CL.I 26" | 188 | TON | $222.0000 | $41,736.00 | $160.0000 | $30,080.00 | $160.0000 | $30,080.00 | $129.0000 | $24,252.00 | $335.0000 | $62,980.00 | $265.5500 | $49,923.40 | $94.0000 | $17,672.00 |
| 430SX20-0001 | NS NBIS ACCESS, UNDER BRIDGE NO. 6018 | 1 | DAY | $1.0000 | $1.00 | $2,500.0000 | $2,500.00 | $20,000.0000 | $20,000.00 | $3,300.0000 | $3,300.00 | $6,750.0000 | $6,750.00 | $7,500.0000 | $7,500.00 | $14,923.0000 | $14,923.00 |
| 502SD20-0014 | CURB, STD. CG-3 | 109 | LF | $90.0000 | $9,810.00 | $120.0000 | $13,080.00 | $50.0000 | $5,450.00 | $170.0000 | $18,530.00 | $185.0000 | $20,165.00 | $92.7000 | $10,104.30 | $53.0000 | $5,777.00 |
| 505SD20-0011 | GUARDRAIL GR-MGS1 | 200 | LF | $48.0000 | $9,600.00 | $33.0000 | $6,600.00 | $29.0000 | $5,800.00 | $34.0000 | $6,800.00 | $29.0000 | $5,800.00 | $29.8700 | $5,974.00 | $50.0000 | $10,000.00 |
| 505SD20-0017 | GUARDRAIL TERMINAL GR- MGS2 | 4 | EA | $4,800.0000 | $19,200.00 | $3,000.0000 | $12,000.00 | $3,075.0000 | $12,300.00 | $3,300.0000 | $13,200.00 | $3,075.0000 | $12,300.00 | $3,167.2500 | $12,669.00 | $5,580.0000 | $22,320.00 |
| 505SD20-0055 | FIXED OBJECT ATTACH. GR- FOA-5 | 4 | EA | $5,400.0000 | $21,600.00 | $4,500.0000 | $18,000.00 | $4,950.0000 | $19,800.00 | $5,600.0000 | $22,400.00 | $4,950.0000 | $19,800.00 | $5,098.5000 | $20,394.00 | $6,200.0000 | $24,800.00 |
| 507SD20-0027 | HIGH VISIBILITY FENCE, 4 FEET | 784 | LF | $3.0000 | $2,352.00 | $5.0000 | $3,920.00 | $4.7500 | $3,724.00 | $8.0000 | $6,272.00 | $25.0000 | $19,600.00 | $3.5000 | $2,744.00 | $10.0000 | $7,840.00 |
| 508SD20-0004 | DEMO. OF PAVEMENT FLEXIBLE | 131 | SY | $83.0000 | $10,873.00 | $40.0000 | $5,240.00 | $75.0000 | $9,825.00 | $15.0000 | $1,965.00 | $110.0000 | $14,410.00 | $103.0000 | $13,493.00 | $50.0000 | $6,550.00 |
| 511SD20-0001 | ALLAYING DUST | 300 | HR | $1.0000 | $300.00 | $1.0000 | $300.00 | $85.0000 | $25,500.00 | $60.0000 | $18,000.00 | $117.0000 | $35,100.00 | $100.0000 | $30,000.00 | $84.0000 | $25,200.00 |
| 512SD20-0013 | TYPE 3 BARRICADE 8' | 8 | EA | $600.0000 | $4,800.00 | $800.0000 | $6,400.00 | $1,078.3400 | $8,626.72 | $600.0000 | $4,800.00 | $815.0000 | $6,520.00 | $374.5900 | $2,996.72 | $590.0000 | $4,720.00 |
| 512SD20-0014 | TEMPORARY SIGN | 464 | SF | $75.0000 | $34,800.00 | $60.0000 | $27,840.00 | $22.0000 | $10,208.00 | $53.0000 | $24,592.00 | $35.0000 | $16,240.00 | $9.8500 | $4,570.40 | $33.0000 | $15,312.00 |
| 512SD20-0025 | PORT.CHANGEABLE MESS. SIGN | 672 | HR | $12.0000 | $8,064.00 | $30.0000 | $20,160.00 | $5.0000 | $3,360.00 | $9.0000 | $6,048.00 | $3.5000 | $2,352.00 | $7.2000 | $4,838.40 | $13.0000 | $8,736.00 |
| 512SD20-0029 | WARNING LIGHT TY. B | 2,920 | DAY | $2.0000 | $5,840.00 | $2.0000 | $5,840.00 | $0.5000 | $1,460.00 | $1.0000 | $2,920.00 | $0.6000 | $1,752.00 | $1.0400 | $3,036.80 | $2.5000 | $7,300.00 |
| 512SD20-0031 | TRAFFIC BARRIER SER. CONC. MB-7D PC | 106 | LF | $179.0000 | $18,974.00 | $95.0000 | $10,070.00 | $92.2200 | $9,775.32 | $64.0000 | $6,784.00 | $120.0000 | $12,720.00 | $82.0000 | $8,692.00 | $440.0000 | $46,640.00 |
| 513SD20-0001 | MOBILIZATION | 1 | LS | $220,000.0000 | $220,000.00 | $200,000.0000 | $200,000.00 | $233,790.7700 | $233,790.77 | $191,000.0000 | $191,000.00 | $315,000.0000 | $315,000.00 | $300,891.0000 | $300,891.00 | $400,878.0000 | $400,878.00 |
| 514SD20-0003 | FIELD OFFICE TY.III | 12 | MO | $3,035.0000 | $36,420.00 | $3,000.0000 | $36,000.00 | $4,945.0000 | $59,340.00 | $3,600.0000 | $43,200.00 | $8,500.0000 | $102,000.00 | $3,435.0000 | $41,220.00 | $12,400.0000 | $148,800.00 |
| 515SD20-0004 | FLEXIBLE PAVE.PLANING 0"-2" | 75 | SY | $140.0000 | $10,500.00 | $50.0000 | $3,750.00 | $128.2300 | $9,617.25 | $110.0000 | $8,250.00 | $76.7000 | $5,752.50 | $108.1500 | $8,111.25 | $146.0000 | $10,950.00 |
| 517SD20-0001 | CONSTRUCTION SURVEYING CONSTR. | 1 | LS | $38,000.0000 | $38,000.00 | $25,000.0000 | $25,000.00 | $26,900.0000 | $26,900.00 | $15,000.0000 | $15,000.00 | $50,000.0000 | $50,000.00 | $31,400.0000 | $31,400.00 | $45,307.0000 | $45,307.00 |
| 601SD20-0001 | SEL TREE REMOVAL TRIM AND CLEAN | 0.4 | ACRE | $5.0000 | $2.00 | $81,000.0000 | $32,400.00 | $1,000.0000 | $400.00 | $23,000.0000 | $9,200.00 | $40,000.0000 | $16,000.00 | $46,179.8000 | $18,471.92 | $31,900.0000 | $12,760.00 |
| 602SD20-0004 | TOPSOIL CLASS B | 258 | CY | $111.0000 | $28,638.00 | $90.0000 | $23,220.00 | $257.0500 | $66,318.90 | $43.0000 | $11,094.00 | $120.0000 | $30,960.00 | $61.0000 | $15,738.00 | $81.0000 | $20,898.00 |
| 603SD20-0002 | TEMPORARY SEED | 96 | LB | $18.0000 | $1,728.00 | $40.0000 | $3,840.00 | $12.0000 | $1,152.00 | $21.0000 | $2,016.00 | $15.0000 | $1,440.00 | $3.1900 | $306.24 | $22.0000 | $2,112.00 |
| 603SD20-0003 | REGULAR SEED | 174 | LB | $20.0000 | $3,480.00 | $20.0000 | $3,480.00 | $13.0000 | $2,262.00 | $22.0000 | $3,828.00 | $17.5000 | $3,045.00 | $2.9900 | $520.26 | $22.0000 | $3,828.00 |
| 603SD20-0004 | OVERSEEDING | 139 | LB | $28.0000 | $3,892.00 | $25.0000 | $3,475.00 | $13.0000 | $1,807.00 | $22.0000 | $3,058.00 | $17.5000 | $2,432.50 | $3.1900 | $443.41 | $22.0000 | $3,058.00 |
| 603SD20-0008 | HYDRAULIC EROSION CONTROL PRODUCT TYPE 2 | 4,054 | SY | $2.0000 | $8,108.00 | $1.0000 | $4,054.00 | $1.0000 | $4,054.00 | $6.3000 | $25,540.20 | $0.5000 | $2,027.00 | $0.8800 | $3,567.52 | $4.0000 | $16,216.00 |
| 603SD20-0009 | HYDRAULIC EROSION CONTROL PRODUCT TYPE 3 | 6,401 | SY | $2.0000 | $12,802.00 | $1.5000 | $9,601.50 | $1.0000 | $6,401.00 | $6.6000 | $42,246.60 | $0.7500 | $4,800.75 | $0.9800 | $6,272.98 | $5.0000 | $32,005.00 |
| 603SD20-0014 | FERTILIZER NITROGEN - N | 96 | LB | $9.0000 | $864.00 | $15.0000 | $1,440.00 | $2.5000 | $240.00 | $17.0000 | $1,632.00 | $2.0000 | $192.00 | $5.1500 | $494.40 | $24.0000 | $2,304.00 |
| 603SD20-0015 | FERTILIZER PHOSPHOROUS - P | 67 | LB | $6.0000 | $402.00 | $15.0000 | $1,005.00 | $2.5000 | $167.50 | $17.0000 | $1,139.00 | $2.0000 | $134.00 | $5.1500 | $345.05 | $24.0000 | $1,608.00 |
| 603SD20-0016 | FERTILIZER POTASSIUM - K | 67 | LB | $6.0000 | $402.00 | $15.0000 | $1,005.00 | $2.5000 | $167.50 | $17.0000 | $1,139.00 | $2.0000 | $134.00 | $5.1500 | $345.05 | $24.0000 | $1,608.00 |
| 603SD20-0017 | LIME | 5.3 | TON | $670.0000 | $3,551.00 | $500.0000 | $2,650.00 | $475.0000 | $2,517.50 | $1,600.0000 | $8,480.00 | $200.0000 | $1,060.00 | $123.6000 | $655.08 | $2,290.0000 | $12,137.00 |
| 605SX20-0017 | NS SEED MIXTURE WETLAND MIXTURE | 100 | LB | $52.0000 | $5,200.00 | $35.0000 | $3,500.00 | $45.0000 | $4,500.00 | $23.0000 | $2,300.00 | $30.0000 | $3,000.00 | $53.5600 | $5,356.00 | $26.0000 | $2,600.00 |
Source: public Virginia DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →