VA
Virginia DOT · Bid Tabulation
Contract C0000123843N01
SHOULDER WIDENING, RUMBLE STRIPS, GUARDRAIL
- County
- FREDERICK
- District
- Staunton
- Letting
- March 25, 2026
- Bidders
- 3
Apparent low bid
W-L CONSTRUCTION & PAVING, INC.
$3,958,648.32
Other bidders
ALLAN MYERS VA, INC.
$4,157,777.00
SUPERIOR PAVING CORPORATION
$4,293,906.86
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | W-L CONSTRUCTION & PAVING, INC. $3,958,648.32 | ALLAN MYERS VA, INC. $4,157,777.00 | SUPERIOR PAVING CORPORATION $4,293,906.86 | |||
|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 303SD20-0029 | SILTATION CONTROL EXCAVATION | 510 | CY | $0.0100 | $5.10 | $20.0000 | $10,200.00 | $0.0100 | $5.10 |
| 303SD20-0034 | TEMP. SILT FENCE TYPE A | 3,000 | LF | $0.1000 | $300.00 | $4.0000 | $12,000.00 | $0.0100 | $30.00 |
| 305SP20-0005 | MACHINING SHOULDERS | 28,756 | LF | $5.0000 | $143,780.00 | $5.0000 | $143,780.00 | $5.1500 | $148,093.40 |
| 309SD20-0010 | AGGR. BASE MATL. TY. I NO. 21B | 12,364 | TON | $41.3000 | $510,633.20 | $50.0000 | $618,200.00 | $55.0000 | $680,020.00 |
| 315SD20-0008 | ASPHALT CONCRETE TY. SM- 9.5D CONST | 3,231 | TON | $130.0000 | $420,030.00 | $140.0000 | $452,340.00 | $160.0000 | $516,960.00 |
| 315SD20-0010 | ASPHALT CONCRETE BM-25.0 (T) | 5,842 | TON | $130.0000 | $759,460.00 | $168.2500 | $982,916.50 | $145.0000 | $847,090.00 |
| 315SD20-0015 | RUMBLE STRIP CYLINDRICAL ASPHALT | 100,548 | LF | $0.2100 | $21,115.08 | $0.2100 | $21,115.08 | $0.2200 | $22,120.56 |
| 505SD20-0011 | GUARDRAIL GR-MGS1 | 26,012.5 | LF | $36.0000 | $936,450.00 | $36.0000 | $936,450.00 | $37.4400 | $973,908.00 |
| 505SD20-0013 | GUARDRAIL GR-MGS1, 9' POST | 712.5 | LF | $46.0000 | $32,775.00 | $46.0000 | $32,775.00 | $47.8400 | $34,086.00 |
| 505SD20-0014 | RADIAL GUARDRAIL GR-MGS1 | 575 | LF | $40.0000 | $23,000.00 | $40.0000 | $23,000.00 | $41.6000 | $23,920.00 |
| 505SD20-0017 | GUARDRAIL TERMINAL GR- MGS2 | 49 | EA | $4,000.0000 | $196,000.00 | $4,000.0000 | $196,000.00 | $4,160.0000 | $203,840.00 |
| 505SD20-0018 | GUARDRAIL END ANCHORAGE GR-MGS3 | 50 | EA | $1,500.0000 | $75,000.00 | $1,500.0000 | $75,000.00 | $1,560.0000 | $78,000.00 |
| 505SD20-0019 | GUARDRAIL HEIGHT TRANSITION GR-MGS4 | 19 | EA | $1,500.0000 | $28,500.00 | $1,500.0000 | $28,500.00 | $1,560.0000 | $29,640.00 |
| 505SD20-0027 | GUARDRAIL TERMINAL GR-6 NCHRP 350 | 62.5 | LF | $160.0000 | $10,000.00 | $160.0000 | $10,000.00 | $166.4000 | $10,400.00 |
| 505SD20-0029 | GUARDRAIL TERMINAL GR-11 | 1 | EA | $1,400.0000 | $1,400.00 | $1,400.0000 | $1,400.00 | $145.6000 | $145.60 |
| 505SD20-0030 | GUARDRAIL GR-2 | 862.5 | LF | $36.0000 | $31,050.00 | $36.0000 | $31,050.00 | $37.4400 | $32,292.00 |
| 505SD20-0034 | RAD. GUARDRAIL GR-2 | 12.5 | LF | $40.0000 | $500.00 | $40.0000 | $500.00 | $41.6000 | $520.00 |
| 505SD20-0053 | FIXED OBJECT ATTACH. GR- FOA-2 TY. I | 6 | EA | $3,150.0000 | $18,900.00 | $3,150.0000 | $18,900.00 | $3,276.0000 | $19,656.00 |
| 505SD20-0054 | FIXED OBJECT ATTACH. GR- FOA-2 TY. II | 5 | EA | $750.0000 | $3,750.00 | $750.0000 | $3,750.00 | $780.0000 | $3,900.00 |
| 505SD20-0073 | REMOVE EXISTING GUARDRAIL | 32,062 | LF | $6.0000 | $192,372.00 | $6.0000 | $192,372.00 | $6.2400 | $200,066.88 |
| 505SX20-0004 | NS GUARDRAIL GUARDRAIL END TERMINAL SITE PREPARATION, 4’ MODERATE | 49 | EA | $500.0000 | $24,500.00 | $500.0000 | $24,500.00 | $515.0000 | $25,235.00 |
| 512SD20-0023 | TRUCK MOUNTED ATTENUATOR | 2,000 | HR | $22.0000 | $44,000.00 | $25.0000 | $50,000.00 | $30.0000 | $60,000.00 |
| 512SD20-0024 | GROUP 2 CHANNELIZING DEVICES | 1,200 | DAY | $0.5000 | $600.00 | $10.0000 | $12,000.00 | $1.0000 | $1,200.00 |
| 512SD20-0025 | PORT.CHANGEABLE MESS. SIGN | 2,000 | HR | $9.0000 | $18,000.00 | $8.0000 | $16,000.00 | $8.0000 | $16,000.00 |
| 512SD20-0026 | ELECTRONIC ARROW BOARD | 2,000 | HR | $5.0000 | $10,000.00 | $3.0000 | $6,000.00 | $5.0000 | $10,000.00 |
| 512SD20-0027 | FLAGGER SERVICE | 400 | HR | $26.8300 | $10,732.00 | $1.0000 | $400.00 | $0.0100 | $4.00 |
| 512SD20-0047 | TEMP. PVMT MRKG TY. A, 6" | 156,924 | LF | $0.1400 | $21,969.36 | $0.1400 | $21,969.36 | $0.1400 | $21,969.36 |
| 513SD20-0001 | MOBILIZATION | 1 | LS | $240,410.6400 | $240,410.64 | $99,868.8200 | $99,868.82 | $100,000.0000 | $100,000.00 |
| 515SD20-0013 | FLEXIBLE PAVE.PLANING 0"-2" | 13,778 | SY | $4.1500 | $57,178.70 | $1.0000 | $13,778.00 | $7.5000 | $103,335.00 |
| 521SD20-0001 | MAILBOX POST, SINGLE | 15 | EA | $465.0000 | $6,975.00 | $250.0000 | $3,750.00 | $500.0000 | $7,500.00 |
| 704SD20-0007 | TYPE B CLASS I PVMT LINE MRKG 6" | 156,924 | LF | $0.7600 | $119,262.24 | $0.7600 | $119,262.24 | $0.7900 | $123,969.96 |
Source: public Virginia DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →