Wisconsin DOT · Bid Tabulation
Contract 20260414015
Mount Pleasant - Racine; North Ohio Street to Fairway Drive
- County
- Racine
- Letting
- April 14, 2026
- Bidders
- 5
Apparent low bid
A.W. OAKES & SON, INC.
$3,657,257.57
Other bidders
MUSSON BROS., INC.
$3,763,157.15
ZIGNEGO COMPANY, INC.
$3,820,726.26
STARK PAVEMENT CORPORATION
$3,935,457.67
LALONDE CONTRACTORS INCORPORATED
$3,977,320.59
Bid Items - unit price and extension by bidder
| Item | Description | Qty | UOM | A.W. OAKES & SON, INC. $3,657,257.57 | MUSSON BROS., INC. $3,763,157.15 | ZIGNEGO COMPANY, INC. $3,820,726.26 | STARK PAVEMENT CORPORATION $3,935,457.67 | LALONDE CONTRACTORS INCORPORATED $3,977,320.59 | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | Unit Price | Extension | ||||
| 201.0105 | Clearing | 7 | STA | $100.0000 | $700.00 | $100.0000 | $700.00 | $100.0000 | $700.00 | $101.0000 | $707.00 | $100.0000 | $700.00 |
| 201.0120 | Clearing | 46 | ID | $25.0000 | $1,150.00 | $10.0000 | $460.00 | $10.0000 | $460.00 | $10.1000 | $464.60 | $10.0000 | $460.00 |
| 201.0205 | Grubbing | 7 | STA | $1,200.0000 | $8,400.00 | $700.0000 | $4,900.00 | $700.0000 | $4,900.00 | $707.0000 | $4,949.00 | $700.0000 | $4,900.00 |
| 201.0220 | Grubbing | 46 | ID | $100.0000 | $4,600.00 | $40.0000 | $1,840.00 | $40.0000 | $1,840.00 | $40.4000 | $1,858.40 | $40.0000 | $1,840.00 |
| 204.0100 | Removing Concrete Pavement | 24,100 | SY | $7.0000 | $168,700.00 | $4.1000 | $98,810.00 | $4.5100 | $108,691.00 | $13.1000 | $315,710.00 | $7.0000 | $168,700.00 |
| 204.0155 | Removing Concrete Sidewalk | 66 | SY | $15.0000 | $990.00 | $26.5000 | $1,749.00 | $10.0000 | $660.00 | $9.0000 | $594.00 | $15.2600 | $1,007.16 |
| 204.0195 | Removing Concrete Bases | 10 | EACH | $350.0000 | $3,500.00 | $211.0000 | $2,110.00 | $500.0000 | $5,000.00 | $348.4600 | $3,484.60 | $331.8700 | $3,318.70 |
| 204.0210 | Removing Manholes | 1 | EACH | $735.0000 | $735.00 | $704.0000 | $704.00 | $1,250.0000 | $1,250.00 | $735.0000 | $735.00 | $700.0000 | $700.00 |
| 204.0220 | Removing Inlets | 21 | EACH | $365.0000 | $7,665.00 | $376.0000 | $7,896.00 | $550.0000 | $11,550.00 | $498.7500 | $10,473.75 | $475.0000 | $9,975.00 |
| 204.0245 | Removing Storm Sewer (size) 003. 18-Inch | 282 | LF | $22.0000 | $6,204.00 | $38.0000 | $10,264.00 | $35.0000 | $9,870.00 | $14.7000 | $4,145.40 | $14.0000 | $3,948.00 |
| 204.9060.S | Removing (item description) 001. Removing Traffic Signals | 1 | EACH | $3,000.0000 | $3,000.00 | $2,552.9400 | $2,552.94 | $2,552.9400 | $2,552.94 | $2,680.5900 | $2,680.59 | $2,552.9400 | $2,552.94 |
| 205.0100 | Excavation Common | 14,858 | CY | $14.0000 | $208,012.00 | $11.0000 | $163,438.00 | $18.4000 | $273,387.20 | $8.3200 | $123,618.56 | $18.9600 | $281,707.68 |
| 213.0100 | Finishing Roadway (project) 001. 2390-09-73 | 1 | EACH | $2,470.1000 | $2,470.10 | $100.0000 | $100.00 | $1,000.0000 | $1,000.00 | $2,500.0000 | $2,500.00 | $3,208.0000 | $3,208.00 |
| 305.0120 | Base Aggregate Dense 1 1/4-Inch | 14,875 | TON | $15.0000 | $223,125.00 | $0.1000 | $1,487.50 | $16.5400 | $246,032.50 | $8.4500 | $125,693.75 | $22.1400 | $329,332.50 |
| 415.0085 | Concrete Pavement 8 1/2-Inch | 21,390 | SY | $61.9000 | $1,324,041.00 | $62.0000 | $1,326,180.00 | $72.0000 | $1,540,080.00 | $58.7500 | $1,256,662.50 | $64.3100 | $1,375,590.90 |
| 415.4100 | Concrete Pavement Joint Filling | 22,320 | SY | $2.0000 | $44,640.00 | $1.9000 | $42,408.00 | $1.5000 | $33,480.00 | $2.2000 | $49,104.00 | $1.8400 | $41,068.80 |
| 416.0610 | Drilled Tie Bars | 52 | EACH | $10.0000 | $520.00 | $10.0000 | $520.00 | $20.0000 | $1,040.00 | $18.0000 | $936.00 | $18.0400 | $938.08 |
| 416.0620 | Drilled Dowel Bars | 270 | EACH | $15.0000 | $4,050.00 | $20.0000 | $5,400.00 | $20.0000 | $5,400.00 | $25.0000 | $6,750.00 | $22.3700 | $6,039.90 |
| 465.0125 | Asphaltic Surface Temporary | 60 | TON | $290.0000 | $17,400.00 | $135.0000 | $8,100.00 | $135.0000 | $8,100.00 | $135.0000 | $8,100.00 | $135.0000 | $8,100.00 |
| 520.8000 | Concrete Collars for Pipe | 10 | EACH | $465.0000 | $4,650.00 | $280.0000 | $2,800.00 | $1,000.0000 | $10,000.00 | $1,214.8500 | $12,148.50 | $1,157.0000 | $11,570.00 |
| 601.0150 | Concrete Curb Integral Type D | 5,840 | LF | $6.0000 | $35,040.00 | $20.0000 | $116,800.00 | $16.0000 | $93,440.00 | $28.0000 | $163,520.00 | $19.8500 | $115,924.00 |
| 601.0405 | Concrete Curb & Gutter 18-Inch Type A | 1,590 | LF | $28.0000 | $44,520.00 | $23.0000 | $36,570.00 | $23.0000 | $36,570.00 | $25.5000 | $40,545.00 | $34.7600 | $55,268.40 |
| 601.0409 | Concrete Curb & Gutter 30-Inch Type A | 1,190 | LF | $31.0000 | $36,890.00 | $26.0000 | $30,940.00 | $27.4000 | $32,606.00 | $26.5000 | $31,535.00 | $44.8200 | $53,335.80 |
| 601.0600 | Concrete Curb Pedestrian | 216 | LF | $50.0000 | $10,800.00 | $40.0000 | $8,640.00 | $35.6000 | $7,689.60 | $55.0000 | $11,880.00 | $49.7200 | $10,739.52 |
| 602.0410 | Concrete Sidewalk 5-Inch | 18,987 | SF | $7.1000 | $134,807.70 | $8.0000 | $151,896.00 | $6.6500 | $126,263.55 | $8.5000 | $161,389.50 | $8.1000 | $153,794.70 |
| 602.0505 | Curb Ramp Detectable Warning Field Yellow | 166 | SF | $55.0000 | $9,130.00 | $45.0000 | $7,470.00 | $47.5000 | $7,885.00 | $50.0000 | $8,300.00 | $43.8700 | $7,282.42 |
| 602.0605 | Curb Ramp Detectable Warning Field Radial Yellow | 95 | SF | $75.0000 | $7,125.00 | $58.0000 | $5,510.00 | $67.7500 | $6,436.25 | $60.0000 | $5,700.00 | $64.8300 | $6,158.85 |
| 602.0810 | Concrete Driveway 6-Inch | 415 | SY | $72.0000 | $29,880.00 | $72.0000 | $29,880.00 | $78.5000 | $32,577.50 | $85.0000 | $35,275.00 | $72.1800 | $29,954.70 |
| 608.0312 | Storm Sewer Pipe Reinforced Concrete Class III 12-Inch | 1,473 | LF | $107.0000 | $157,611.00 | $96.0000 | $141,408.00 | $98.0000 | $144,354.00 | $101.8500 | $150,025.05 | $97.0000 | $142,881.00 |
| 608.0315 | Storm Sewer Pipe Reinforced Concrete Class III 15-Inch | 50 | LF | $110.0000 | $5,500.00 | $233.0000 | $11,650.00 | $135.0000 | $6,750.00 | $103.9500 | $5,197.50 | $99.0000 | $4,950.00 |
| 608.0318 | Storm Sewer Pipe Reinforced Concrete Class III 18-Inch | 50 | LF | $115.0000 | $5,750.00 | $189.0000 | $9,450.00 | $135.0000 | $6,750.00 | $141.7500 | $7,087.50 | $135.0000 | $6,750.00 |
| 611.0420 | Reconstructing Manholes | 1 | EACH | $1,600.0000 | $1,600.00 | $1,500.0000 | $1,500.00 | $1,250.0000 | $1,250.00 | $2,641.8000 | $2,641.80 | $2,516.0000 | $2,516.00 |
| 611.0530 | Manhole Covers Type J | 10 | EACH | $650.0000 | $6,500.00 | $809.0000 | $8,090.00 | $975.0000 | $9,750.00 | $761.2500 | $7,612.50 | $725.0000 | $7,250.00 |
| 611.0624 | Inlet Covers Type H | 57 | EACH | $900.0000 | $51,300.00 | $1,090.0000 | $62,130.00 | $950.0000 | $54,150.00 | $992.2500 | $56,558.25 | $945.0000 | $53,865.00 |
| 611.2003 | Manholes 3-FT Diameter | 1 | EACH | $4,400.0000 | $4,400.00 | $1,950.0000 | $1,950.00 | $3,500.0000 | $3,500.00 | $2,677.5000 | $2,677.50 | $2,550.0000 | $2,550.00 |
| 611.2004 | Manholes 4-FT Diameter | 8 | EACH | $4,100.0000 | $32,800.00 | $2,390.0000 | $19,120.00 | $4,200.0000 | $33,600.00 | $3,045.0000 | $24,360.00 | $2,900.0000 | $23,200.00 |
| 611.2006 | Manholes 6-FT Diameter | 2 | EACH | $9,100.0000 | $18,200.00 | $6,050.0000 | $12,100.00 | $8,000.0000 | $16,000.00 | $7,323.7500 | $14,647.50 | $6,975.0000 | $13,950.00 |
| 611.3004 | Inlets 4-FT Diameter | 16 | EACH | $3,050.0000 | $48,800.00 | $2,140.0000 | $34,240.00 | $3,350.0000 | $53,600.00 | $2,520.0000 | $40,320.00 | $2,400.0000 | $38,400.00 |
| 611.3230 | Inlets 2x3-FT | 40 | EACH | $2,800.0000 | $112,000.00 | $1,430.0000 | $57,200.00 | $2,500.0000 | $100,000.00 | $1,927.8000 | $77,112.00 | $1,836.0000 | $73,440.00 |
| 611.8110 | Adjusting Manhole Covers | 9 | EACH | $720.0000 | $6,480.00 | $612.0000 | $5,508.00 | $750.0000 | $6,750.00 | $588.0000 | $5,292.00 | $560.0000 | $5,040.00 |
| 611.8115 | Adjusting Inlet Covers | 1 | EACH | $720.0000 | $720.00 | $612.0000 | $612.00 | $750.0000 | $750.00 | $588.0000 | $588.00 | $560.0000 | $560.00 |
| 619.1000 | Mobilization | 1 | EACH | $170,000.0000 | $170,000.00 | $660,091.1500 | $660,091.15 | $89,000.0000 | $89,000.00 | $408,286.8300 | $408,286.83 | $206,083.9100 | $206,083.91 |
| 620.0300 | Concrete Median Sloped Nose | 165 | SF | $16.0000 | $2,640.00 | $15.0000 | $2,475.00 | $26.9000 | $4,438.50 | $45.0000 | $7,425.00 | $20.0800 | $3,313.20 |
| 624.0100 | Water | 349 | MGAL | $45.0000 | $15,705.00 | $0.0100 | $3.49 | $50.0000 | $17,450.00 | $10.6000 | $3,699.40 | $0.0100 | $3.49 |
| 625.0100 | Topsoil | 1,180 | SY | $6.0000 | $7,080.00 | $10.0000 | $11,800.00 | $5.0000 | $5,900.00 | $8.9300 | $10,537.40 | $11.0000 | $12,980.00 |
| 628.1504 | Silt Fence | 413 | LF | $3.0000 | $1,239.00 | $2.0000 | $826.00 | $3.0000 | $1,239.00 | $2.1000 | $867.30 | $2.1400 | $883.82 |
| 628.1520 | Silt Fence Maintenance | 413 | LF | $0.0100 | $4.13 | $0.2500 | $103.25 | $0.0100 | $4.13 | $0.2600 | $107.38 | $0.0300 | $12.39 |
| 628.1905 | Mobilizations Erosion Control | 9 | EACH | $50.0000 | $450.00 | $225.0000 | $2,025.00 | $50.0000 | $450.00 | $236.2500 | $2,126.25 | $100.0000 | $900.00 |
| 628.1910 | Mobilizations Emergency Erosion Control | 5 | EACH | $50.0000 | $250.00 | $225.0000 | $1,125.00 | $50.0000 | $250.00 | $236.2500 | $1,181.25 | $25.0000 | $125.00 |
| 628.2008 | Erosion Mat Urban Class I Type B | 1,180 | SY | $2.0000 | $2,360.00 | $1.8500 | $2,183.00 | $2.0000 | $2,360.00 | $1.9400 | $2,289.20 | $1.9900 | $2,348.20 |
| 628.7005 | Inlet Protection Type A | 70 | EACH | $50.0000 | $3,500.00 | $35.0000 | $2,450.00 | $50.0000 | $3,500.00 | $36.7500 | $2,572.50 | $50.0000 | $3,500.00 |
| 628.7015 | Inlet Protection Type C | 55 | EACH | $50.0000 | $2,750.00 | $65.0000 | $3,575.00 | $50.0000 | $2,750.00 | $68.2500 | $3,753.75 | $50.0000 | $2,750.00 |
| 628.7020 | Inlet Protection Type D | 3 | EACH | $100.0000 | $300.00 | $125.0000 | $375.00 | $100.0000 | $300.00 | $131.2500 | $393.75 | $120.0000 | $360.00 |
| 628.7560 | Tracking Pads | 2 | EACH | $1.0000 | $2.00 | $500.0000 | $1,000.00 | $1.0000 | $2.00 | $1.0600 | $2.12 | $0.0100 | $0.02 |
| 629.0210 | Fertilizer Type B | 9 | CWT | $100.0000 | $900.00 | $125.0000 | $1,125.00 | $100.0000 | $900.00 | $131.2500 | $1,181.25 | $80.0000 | $720.00 |
| 630.0130 | Seeding Mixture No. 30 | 53 | LB | $8.5000 | $450.50 | $10.5000 | $556.50 | $8.5000 | $450.50 | $11.0300 | $584.59 | $10.0000 | $530.00 |
| 630.0200 | Seeding Temporary | 32 | LB | $5.0000 | $160.00 | $7.5000 | $240.00 | $5.0000 | $160.00 | $7.8800 | $252.16 | $2.0000 | $64.00 |
| 630.0500 | Seed Water | 27 | MGAL | $5.0000 | $135.00 | $25.0000 | $675.00 | $5.0000 | $135.00 | $26.2500 | $708.75 | $6.0000 | $162.00 |
| 631.0300 | Sod Water | 45 | MGAL | $20.0000 | $900.00 | $65.0000 | $2,925.00 | $20.0000 | $900.00 | $68.2500 | $3,071.25 | $20.0000 | $900.00 |
| 631.1000 | Sod Lawn | 2,202 | SY | $9.0000 | $19,818.00 | $7.1000 | $15,634.20 | $8.0000 | $17,616.00 | $7.4600 | $16,426.92 | $8.0000 | $17,616.00 |
| 634.0614 | Posts Wood 4x6-Inch X 14-FT | 55 | EACH | $115.0000 | $6,325.00 | $115.0000 | $6,325.00 | $115.0000 | $6,325.00 | $120.7500 | $6,641.25 | $125.0000 | $6,875.00 |
| 637.2210 | Signs Type II Reflective H | 311.44 | SF | $21.0000 | $6,540.24 | $22.5000 | $7,007.40 | $21.0000 | $6,540.24 | $23.6300 | $7,359.33 | $21.1000 | $6,571.38 |
| 637.2230 | Signs Type II Reflective F | 49.25 | SF | $23.0000 | $1,132.75 | $27.5000 | $1,354.38 | $22.9000 | $1,127.83 | $28.8800 | $1,422.34 | $23.1000 | $1,137.68 |
| 638.2102 | Moving Signs Type II | 18 | EACH | $100.0000 | $1,800.00 | $125.0000 | $2,250.00 | $20.0000 | $360.00 | $131.2500 | $2,362.50 | $50.0000 | $900.00 |
| 638.2602 | Removing Signs Type II | 41 | EACH | $20.0000 | $820.00 | $25.0000 | $1,025.00 | $100.0000 | $4,100.00 | $26.2500 | $1,076.25 | $10.0000 | $410.00 |
| 642.5001 | Field Office Type B | 1 | EACH | $14,000.0000 | $14,000.00 | $25,000.0000 | $25,000.00 | $20,000.0000 | $20,000.00 | $20,000.0000 | $20,000.00 | $26,664.0000 | $26,664.00 |
| 643.0300 | Traffic Control Drums | 44,295 | DAY | $0.2500 | $11,073.75 | $0.2000 | $8,859.00 | $0.2000 | $8,859.00 | $0.2100 | $9,301.95 | $0.2000 | $8,859.00 |
| 643.0420 | Traffic Control Barricades Type III | 6,278 | DAY | $0.5000 | $3,139.00 | $0.5000 | $3,139.00 | $0.5000 | $3,139.00 | $0.5300 | $3,327.34 | $0.5000 | $3,139.00 |
| 643.0500 | Traffic Control Flexible Tubular Marker Posts | 584 | EACH | $20.0000 | $11,680.00 | $20.0000 | $11,680.00 | $20.0000 | $11,680.00 | $21.2000 | $12,380.80 | $20.0000 | $11,680.00 |
| 643.0600 | Traffic Control Flexible Tubular Marker Bases | 508 | EACH | $5.0000 | $2,540.00 | $5.0000 | $2,540.00 | $5.0000 | $2,540.00 | $5.3000 | $2,692.40 | $5.0000 | $2,540.00 |
| 643.0705 | Traffic Control Warning Lights Type A | 13,475 | DAY | $0.1000 | $1,347.50 | $0.0500 | $673.75 | $0.0500 | $673.75 | $0.0600 | $808.50 | $0.0500 | $673.75 |
| 643.0715 | Traffic Control Warning Lights Type C | 6,760 | DAY | $0.1000 | $676.00 | $0.0500 | $338.00 | $0.0500 | $338.00 | $0.0600 | $405.60 | $0.0500 | $338.00 |
| 643.0810 | Traffic Control Connected Arrow Boards | 586 | DAY | $20.0000 | $11,720.00 | $18.0000 | $10,548.00 | $18.0000 | $10,548.00 | $19.0800 | $11,180.88 | $18.0000 | $10,548.00 |
| 643.0900 | Traffic Control Signs | 11,142 | DAY | $0.3500 | $3,899.70 | $0.3500 | $3,899.70 | $0.3500 | $3,899.70 | $0.3700 | $4,122.54 | $0.3500 | $3,899.70 |
| 643.1050 | Traffic Control Signs PCMS | 14 | DAY | $75.0000 | $1,050.00 | $75.0000 | $1,050.00 | $75.0000 | $1,050.00 | $79.5000 | $1,113.00 | $75.0000 | $1,050.00 |
| 643.1220 | Traffic Control Connected Work Zone Start and End Location Markers | 447 | DAY | $10.0000 | $4,470.00 | $10.0000 | $4,470.00 | $10.0000 | $4,470.00 | $10.6000 | $4,738.20 | $10.0000 | $4,470.00 |
| 643.3165 | Temporary Marking Line Paint 6-Inch | 21,577 | LF | $0.4000 | $8,630.80 | $0.3700 | $7,983.49 | $0.3700 | $7,983.49 | $0.3900 | $8,415.03 | $0.3700 | $7,983.49 |
| 643.3505 | Temporary Marking Arrow Paint | 11 | EACH | $115.0000 | $1,265.00 | $115.0000 | $1,265.00 | $115.0000 | $1,265.00 | $121.9000 | $1,340.90 | $115.0000 | $1,265.00 |
| 643.3805 | Temporary Marking Stop Line Paint 18-Inch | 237 | LF | $6.0000 | $1,422.00 | $5.5000 | $1,303.50 | $5.5000 | $1,303.50 | $5.8300 | $1,381.71 | $5.5000 | $1,303.50 |
| 643.3960 | Temporary Marking Removable Mask Out Tape 6-Inch | 244 | LF | $3.0000 | $732.00 | $2.6000 | $634.40 | $2.6000 | $634.40 | $2.7600 | $673.44 | $2.6000 | $634.40 |
| 643.5000 | Traffic Control | 1 | EACH | $35,000.0000 | $35,000.00 | $33,500.0000 | $33,500.00 | $33,500.0000 | $33,500.00 | $35,510.0000 | $35,510.00 | $33,500.0000 | $33,500.00 |
| 644.1430 | Temporary Pedestrian Surface Plate | 60 | SF | $6.0000 | $360.00 | $18.0000 | $1,080.00 | $12.0000 | $720.00 | $19.0800 | $1,144.80 | $18.0000 | $1,080.00 |
| 644.1601 | Temporary Pedestrian Curb Ramp | 21 | DAY | $20.0000 | $420.00 | $20.0000 | $420.00 | $24.0000 | $504.00 | $21.2000 | $445.20 | $20.0000 | $420.00 |
| 644.1605 | Temporary Pedestrian Detectable Warning Field | 20 | SF | $20.0000 | $400.00 | $20.0000 | $400.00 | $4.0000 | $80.00 | $5.3000 | $106.00 | $20.0000 | $400.00 |
| 644.1810 | Temporary Pedestrian Barricade | 610 | LF | $5.0000 | $3,050.00 | $5.0000 | $3,050.00 | $5.0000 | $3,050.00 | $5.3000 | $3,233.00 | $5.0000 | $3,050.00 |
| 644.1900.S | Temporary Audible Message Devices | 178 | DAY | $5.0000 | $890.00 | $5.0000 | $890.00 | $5.0000 | $890.00 | $5.3000 | $943.40 | $5.0000 | $890.00 |
| 646.1020 | Marking Line Epoxy 4-Inch | 6,879 | LF | $0.7500 | $5,159.25 | $0.7500 | $5,159.25 | $0.7500 | $5,159.25 | $0.8900 | $6,122.31 | $0.7500 | $5,159.25 |
| 646.3020 | Marking Line Epoxy 8-Inch | 662 | LF | $1.5000 | $993.00 | $1.5000 | $993.00 | $1.5000 | $993.00 | $1.7900 | $1,184.98 | $1.5000 | $993.00 |
| 646.5020 | Marking Arrow Epoxy | 26 | EACH | $225.0000 | $5,850.00 | $225.0000 | $5,850.00 | $225.0000 | $5,850.00 | $268.4200 | $6,978.92 | $225.0000 | $5,850.00 |
| 646.5120 | Marking Word Epoxy | 2 | EACH | $250.0000 | $500.00 | $245.0000 | $490.00 | $245.0000 | $490.00 | $292.2800 | $584.56 | $245.0000 | $490.00 |
| 646.6120 | Marking Stop Line Epoxy 18-Inch | 166 | LF | $14.0000 | $2,324.00 | $13.2500 | $2,199.50 | $13.2500 | $2,199.50 | $15.8100 | $2,624.46 | $13.2500 | $2,199.50 |
| 646.6464 | Cold Weather Marking Epoxy 4-Inch | 6,878 | LF | $1.2000 | $8,253.60 | $1.1500 | $7,909.70 | $1.1500 | $7,909.70 | $1.3700 | $9,422.86 | $1.1500 | $7,909.70 |
| 646.6468 | Cold Weather Marking Epoxy 8-Inch | 662 | LF | $2.5000 | $1,655.00 | $2.3000 | $1,522.60 | $2.3000 | $1,522.60 | $2.7400 | $1,813.88 | $2.3000 | $1,522.60 |
| 646.7420 | Marking Crosswalk Epoxy Transverse Line 6-Inch | 472 | LF | $11.0000 | $5,192.00 | $10.5000 | $4,956.00 | $10.5000 | $4,956.00 | $12.5300 | $5,914.16 | $10.5000 | $4,956.00 |
| 646.8120 | Marking Curb Epoxy | 54 | LF | $9.0000 | $486.00 | $8.2500 | $445.50 | $8.2500 | $445.50 | $9.8400 | $531.36 | $8.2500 | $445.50 |
| 646.8220 | Marking Island Nose Epoxy | 2 | EACH | $300.0000 | $600.00 | $275.0000 | $550.00 | $275.0000 | $550.00 | $328.0700 | $656.14 | $275.0000 | $550.00 |
| 646.9000 | Marking Removal Line 4-Inch | 3,997 | LF | $0.6000 | $2,398.20 | $0.5000 | $1,998.50 | $0.5000 | $1,998.50 | $0.5300 | $2,118.41 | $0.5000 | $1,998.50 |
| 646.9300 | Marking Removal Special Marking | 2 | EACH | $125.0000 | $250.00 | $115.0000 | $230.00 | $115.0000 | $230.00 | $121.9000 | $243.80 | $115.0000 | $230.00 |
| 650.4000 | Construction Staking Storm Sewer | 67 | EACH | $150.0000 | $10,050.00 | $120.0000 | $8,040.00 | $120.0000 | $8,040.00 | $132.0000 | $8,844.00 | $120.0000 | $8,040.00 |
| 650.4500 | Construction Staking Subgrade | 3,239 | LF | $1.0000 | $3,239.00 | $0.0100 | $32.39 | $0.0100 | $32.39 | $0.0200 | $64.78 | $0.0100 | $32.39 |
| 650.7000 | Construction Staking Concrete Pavement | 3,239 | LF | $2.0000 | $6,478.00 | $0.0100 | $32.39 | $0.0100 | $32.39 | $0.0200 | $64.78 | $1.5000 | $4,858.50 |
| 650.8501 | Construction Staking Electrical Installations (project) 001. 2390-09-73 | 1 | EACH | $2,500.0000 | $2,500.00 | $850.0000 | $850.00 | $850.0000 | $850.00 | $935.0000 | $935.00 | $850.0000 | $850.00 |
| 650.9000 | Construction Staking Curb Ramps | 21 | EACH | $150.0000 | $3,150.00 | $130.0000 | $2,730.00 | $130.0000 | $2,730.00 | $143.0000 | $3,003.00 | $130.0000 | $2,730.00 |
| 650.9500 | Construction Staking Sidewalk (project) 001. 2390-09-73 | 1 | EACH | $2,500.0000 | $2,500.00 | $2,500.0000 | $2,500.00 | $2,500.0000 | $2,500.00 | $2,750.0000 | $2,750.00 | $2,500.0000 | $2,500.00 |
| 650.9911 | Construction Staking Supplemental Control (project) 001. 2390-09-73 | 1 | EACH | $3,500.0000 | $3,500.00 | $10,000.0000 | $10,000.00 | $10,000.0000 | $10,000.00 | $11,000.0000 | $11,000.00 | $10,000.0000 | $10,000.00 |
| 650.9920 | Construction Staking Slope Stakes | 886 | LF | $1.0000 | $886.00 | $1.1000 | $974.60 | $1.1000 | $974.60 | $1.2100 | $1,072.06 | $1.1000 | $974.60 |
| 652.0225 | Conduit Rigid Nonmetallic Schedule 40 2-Inch | 60 | LF | $7.0000 | $420.00 | $6.5400 | $392.40 | $6.5400 | $392.40 | $6.8700 | $412.20 | $6.5400 | $392.40 |
| 652.0235 | Conduit Rigid Nonmetallic Schedule 40 3-Inch | 745 | LF | $9.0000 | $6,705.00 | $8.4300 | $6,280.35 | $8.4300 | $6,280.35 | $8.8500 | $6,593.25 | $8.4300 | $6,280.35 |
| 652.0615 | Conduit Special 3-Inch | 540 | LF | $26.0000 | $14,040.00 | $24.8700 | $13,429.80 | $24.8700 | $13,429.80 | $26.1100 | $14,099.40 | $24.8700 | $13,429.80 |
| 653.0140 | Pull Boxes Steel 24x42-Inch | 13 | EACH | $1,400.0000 | $18,200.00 | $1,360.6400 | $17,688.32 | $1,360.6400 | $17,688.32 | $1,428.6700 | $18,572.71 | $1,360.6400 | $17,688.32 |
| 653.0905 | Removing Pull Boxes | 16 | EACH | $125.0000 | $2,000.00 | $114.8600 | $1,837.76 | $114.8600 | $1,837.76 | $120.6000 | $1,929.60 | $114.8600 | $1,837.76 |
| 654.0101 | Concrete Bases Type 1 | 4 | EACH | $950.0000 | $3,800.00 | $915.3100 | $3,661.24 | $915.3100 | $3,661.24 | $961.0800 | $3,844.32 | $915.3100 | $3,661.24 |
| 654.0102 | Concrete Bases Type 2 | 2 | EACH | $1,500.0000 | $3,000.00 | $1,451.6600 | $2,903.32 | $1,451.6600 | $2,903.32 | $1,524.2400 | $3,048.48 | $1,451.6600 | $2,903.32 |
| 654.0120 | Concrete Bases Type 10-Special | 2 | EACH | $10,000.0000 | $20,000.00 | $9,836.2100 | $19,672.42 | $9,836.2100 | $19,672.42 | $10,328.0200 | $20,656.04 | $9,836.2100 | $19,672.42 |
| 654.0217 | Concrete Control Cabinet Bases Type 9 Special | 1 | EACH | $3,000.0000 | $3,000.00 | $2,603.4300 | $2,603.43 | $2,603.4300 | $2,603.43 | $2,733.6000 | $2,733.60 | $2,603.4300 | $2,603.43 |
| 655.0230 | Cable Traffic Signal 5-14 AWG | 611 | LF | $1.6500 | $1,008.15 | $1.5500 | $947.05 | $1.5500 | $947.05 | $1.6300 | $995.93 | $1.5500 | $947.05 |
| 655.0240 | Cable Traffic Signal 7-14 AWG | 463 | LF | $2.0000 | $926.00 | $1.9500 | $902.85 | $1.9500 | $902.85 | $2.0500 | $949.15 | $1.9500 | $902.85 |
| 655.0250 | Cable Traffic Signal 9-14 AWG | 256 | LF | $2.2000 | $563.20 | $2.0200 | $517.12 | $2.0200 | $517.12 | $2.1200 | $542.72 | $2.0200 | $517.12 |
| 655.0260 | Cable Traffic Signal 12-14 AWG | 195 | LF | $3.0000 | $585.00 | $2.9500 | $575.25 | $2.9500 | $575.25 | $3.1000 | $604.50 | $2.9500 | $575.25 |
| 655.0270 | Cable Traffic Signal 15-14 AWG | 536 | LF | $3.5000 | $1,876.00 | $3.4400 | $1,843.84 | $3.4400 | $1,843.84 | $3.6100 | $1,934.96 | $3.4400 | $1,843.84 |
| 655.0285 | Cable Traffic Signal 21-12 AWG | 332 | LF | $4.5000 | $1,494.00 | $4.3300 | $1,437.56 | $4.3300 | $1,437.56 | $4.5500 | $1,510.60 | $4.3300 | $1,437.56 |
| 655.0515 | Electrical Wire Traffic Signals 10 AWG | 1,608 | LF | $1.2500 | $2,010.00 | $1.1200 | $1,800.96 | $1.1200 | $1,800.96 | $1.1800 | $1,897.44 | $1.1200 | $1,800.96 |
| 655.0900 | Traffic Signal EVP Detector Cable | 464 | LF | $1.5000 | $696.00 | $1.3500 | $626.40 | $1.3500 | $626.40 | $1.4200 | $658.88 | $1.3500 | $626.40 |
| 656.0201 | Electrical Service Meter Breaker Pedestal (location) 001. CTH C & Spring Valley Dr | 1 | EACH | $1,850.0000 | $1,850.00 | $1,755.7300 | $1,755.73 | $1,755.7300 | $1,755.73 | $1,843.5200 | $1,843.52 | $1,755.7300 | $1,755.73 |
| 657.0100 | Pedestal Bases | 4 | EACH | $350.0000 | $1,400.00 | $339.1400 | $1,356.56 | $339.1400 | $1,356.56 | $356.1000 | $1,424.40 | $339.1400 | $1,356.56 |
| 657.0255 | Transformer Bases Breakaway 11 1/2-Inch Bolt Circle | 2 | EACH | $800.0000 | $1,600.00 | $777.0200 | $1,554.04 | $777.0200 | $1,554.04 | $815.8700 | $1,631.74 | $777.0200 | $1,554.04 |
| 657.0305 | Poles Type 2 | 2 | EACH | $3,000.0000 | $6,000.00 | $2,745.4600 | $5,490.92 | $2,745.4600 | $5,490.92 | $2,882.7300 | $5,765.46 | $2,745.4600 | $5,490.92 |
| 657.0347 | Poles Type 9-Special | 2 | EACH | $14,000.0000 | $28,000.00 | $13,647.5800 | $27,295.16 | $13,647.5800 | $27,295.16 | $14,329.9600 | $28,659.92 | $13,647.5800 | $27,295.16 |
| 657.0420 | Traffic Signal Standards Aluminum 13-FT | 2 | EACH | $1,000.0000 | $2,000.00 | $974.5300 | $1,949.06 | $974.5300 | $1,949.06 | $1,023.2600 | $2,046.52 | $974.5300 | $1,949.06 |
| 657.0425 | Traffic Signal Standards Aluminum 15-FT | 2 | EACH | $1,050.0000 | $2,100.00 | $1,031.9100 | $2,063.82 | $1,031.9100 | $2,063.82 | $1,083.5100 | $2,167.02 | $1,031.9100 | $2,063.82 |
| 657.0546 | Monotube Arms 45-FT-Special | 2 | EACH | $7,000.0000 | $14,000.00 | $6,691.1900 | $13,382.38 | $6,691.1900 | $13,382.38 | $7,025.7500 | $14,051.50 | $6,691.1900 | $13,382.38 |
| 658.0173 | Traffic Signal Face 3S 12-Inch | 11 | EACH | $850.0000 | $9,350.00 | $830.2200 | $9,132.42 | $830.2200 | $9,132.42 | $871.7300 | $9,589.03 | $830.2200 | $9,132.42 |
| 658.0174 | Traffic Signal Face 4S 12-Inch | 4 | EACH | $1,100.0000 | $4,400.00 | $1,074.1200 | $4,296.48 | $1,074.1200 | $4,296.48 | $1,127.8300 | $4,511.32 | $1,074.1200 | $4,296.48 |
| 658.0175 | Traffic Signal Face 5S 12-Inch | 2 | EACH | $1,350.0000 | $2,700.00 | $1,294.1800 | $2,588.36 | $1,294.1800 | $2,588.36 | $1,358.8900 | $2,717.78 | $1,294.1800 | $2,588.36 |
| 658.0416 | Pedestrian Signal Face 16-Inch | 4 | EACH | $550.0000 | $2,200.00 | $535.2800 | $2,141.12 | $535.2800 | $2,141.12 | $562.0400 | $2,248.16 | $535.2800 | $2,141.12 |
| 658.5070 | Signal Mounting Hardware (location) 001. CTH C & Spring Valley Dr | 1 | EACH | $5,500.0000 | $5,500.00 | $5,306.6100 | $5,306.61 | $5,306.6100 | $5,306.61 | $5,571.9400 | $5,571.94 | $5,306.6100 | $5,306.61 |
| 661.0201 | Temporary Traffic Signals for Intersections (location) 001. CTH C & Spring Valley Dr | 1 | EACH | $41,000.0000 | $41,000.00 | $40,057.5600 | $40,057.56 | $40,057.5600 | $40,057.56 | $42,060.4400 | $42,060.44 | $40,057.5600 | $40,057.56 |
| 690.0150 | Sawing Asphalt | 362 | LF | $2.0000 | $724.00 | $1.2000 | $434.40 | $1.3900 | $503.18 | $1.8600 | $673.32 | $1.2000 | $434.40 |
| 690.0250 | Sawing Concrete | 5,146 | LF | $2.0000 | $10,292.00 | $2.2500 | $11,578.50 | $2.1500 | $11,063.90 | $2.2300 | $11,475.58 | $2.2500 | $11,578.50 |
| 715.0720 | Incentive Compressive Strength Concrete Pavement | 6,501 | DOL | $1.0000 | $6,501.00 | $1.0000 | $6,501.00 | $1.0000 | $6,501.00 | $1.0000 | $6,501.00 | $1.0000 | $6,501.00 |
| 740.0440 | Incentive IRI Ride | 5,870 | DOL | $1.0000 | $5,870.00 | $1.0000 | $5,870.00 | $1.0000 | $5,870.00 | $1.0000 | $5,870.00 | $1.0000 | $5,870.00 |
| ASP.1T0A | On-the-Job Training Apprentice at $5.00/HR | 1,200 | HRS | $5.0000 | $6,000.00 | $5.0000 | $6,000.00 | $5.0000 | $6,000.00 | $5.0000 | $6,000.00 | $5.0000 | $6,000.00 |
| ASP.1T0G | On-the-Job Training Graduate at $5.00/HR | 4,800 | HRS | $5.0000 | $24,000.00 | $5.0000 | $24,000.00 | $5.0000 | $24,000.00 | $5.0000 | $24,000.00 | $5.0000 | $24,000.00 |
| SPV.0035 | Special 001. Backfill Slurry | 10 | CY | $100.0000 | $1,000.00 | $153.0000 | $1,530.00 | $350.0000 | $3,500.00 | $127.0500 | $1,270.50 | $121.0000 | $1,210.00 |
| SPV.0060 | Special 108. Vehicular Video Detection System 4 Cameras | 19 | EACH | $17,693.7500 | $177,050.00 | $16,954.1100 | $169,332.88 | $17,722.8600 | $180,282.88 | $21,288.0775 | $217,292.12 | $20,274.3600 | $206,944.88 |
Source: public Wisconsin DOT letting records, republished by BidTabs.us. Figures are reproduced as submitted at letting.
Want the analysis, not just the numbers?
DOTestimate turns these same tabs into price-trend analysis, quick estimates, and contractor intel.
Explore DOTestimate →